NHAI Eyes November Opening For One Carriageway Of Kulur Bridge
ROADS & HIGHWAYS

NHAI Eyes November Opening For One Carriageway Of Kulur Bridge

The National Highways Authority of India is targeting the opening of one carriageway of the long delayed Kulur bridge in Mangaluru by the end of November as work on the six-lane structure over the Gurupura (Phalguni) river continues to lag. The bridge on National Highway 66 is located about seven kilometres north of Mangaluru city centre and is being built between two existing structures, a 1952-era bowstring arch used for southbound traffic and a reinforced concrete girder bridge carrying northbound movement.

NHAI officials indicated that girder launching has been pending, with a total of 60 girders already fabricated and stored at the Baikampady yard awaiting installation. They said the remaining work, including completion of pier caps atop the bridge piers, was expected to take several months and contractors have been instructed to accelerate the pace. Most of the required pier caps have been finished, with only a small number of locations still pending at the most recent review.

The new bridge has been designed with a total width of 41 metres, comprising a 28-metre-wide main carriageway accommodating six lanes, with a separate service road alongside. Once the main carriageway becomes operational, vehicular movement on the existing 1952 arch bridge will be restricted and the older structure is to be permanently closed to traffic. A new service road and footpath are planned beside the old bridge, but construction of the service road has been deferred until pipelines running along the older structure are relocated.

The Kulur project has faced repeated delays over the years, prompting local political representatives, including Dakshina Kannada member of parliament Capt Brijesh Chowta, to press NHAI for expedited completion. Officials have told authorities and the contractor that remaining works must be finished before the onset of the monsoon season because heavy rainfall typically disrupts coastal construction activity. The Kulur stretch forms part of wider upgrades along NH 66 in and around Mangaluru, where several bridge and flyover projects at Pumpwell, Thokkottu and Gurupura have experienced extended delays due to funding constraints, contractor issues and land related hurdles.

With NHAI targeting a partial opening by the end of November, commuters on the Mangaluru-Udupi route are likely to see some relief on the long pending crossing, even as full completion of the bridge, including the service road and pedestrian pathways, remains contingent on further progress in the months ahead. Authorities will monitor progress and adjust timelines as necessary.

The National Highways Authority of India is targeting the opening of one carriageway of the long delayed Kulur bridge in Mangaluru by the end of November as work on the six-lane structure over the Gurupura (Phalguni) river continues to lag. The bridge on National Highway 66 is located about seven kilometres north of Mangaluru city centre and is being built between two existing structures, a 1952-era bowstring arch used for southbound traffic and a reinforced concrete girder bridge carrying northbound movement. NHAI officials indicated that girder launching has been pending, with a total of 60 girders already fabricated and stored at the Baikampady yard awaiting installation. They said the remaining work, including completion of pier caps atop the bridge piers, was expected to take several months and contractors have been instructed to accelerate the pace. Most of the required pier caps have been finished, with only a small number of locations still pending at the most recent review. The new bridge has been designed with a total width of 41 metres, comprising a 28-metre-wide main carriageway accommodating six lanes, with a separate service road alongside. Once the main carriageway becomes operational, vehicular movement on the existing 1952 arch bridge will be restricted and the older structure is to be permanently closed to traffic. A new service road and footpath are planned beside the old bridge, but construction of the service road has been deferred until pipelines running along the older structure are relocated. The Kulur project has faced repeated delays over the years, prompting local political representatives, including Dakshina Kannada member of parliament Capt Brijesh Chowta, to press NHAI for expedited completion. Officials have told authorities and the contractor that remaining works must be finished before the onset of the monsoon season because heavy rainfall typically disrupts coastal construction activity. The Kulur stretch forms part of wider upgrades along NH 66 in and around Mangaluru, where several bridge and flyover projects at Pumpwell, Thokkottu and Gurupura have experienced extended delays due to funding constraints, contractor issues and land related hurdles. With NHAI targeting a partial opening by the end of November, commuters on the Mangaluru-Udupi route are likely to see some relief on the long pending crossing, even as full completion of the bridge, including the service road and pedestrian pathways, remains contingent on further progress in the months ahead. Authorities will monitor progress and adjust timelines as necessary.

Related Stories

Gold Stories

Next Story
Resources

NCC Founder and Padma Shri Awardee AVS Raju Passes Away at 89

Dr Alluri Venkata Satyanarayana Raju, founder and Chairman Emeritus of NCC Limited and a Padma Shri awardee, passed away in Hyderabad on 13 October 2026. He was 89.Born on 18 April 1937 in Antarvedipalem village in Andhra Pradesh's erstwhile East Godavari district, Raju began his entrepreneurial journey in 1956. He established Nagarjuna Construction Company (NCC) Limited in 1978, which subsequently emerged as one of India's leading construction and infrastructure companies.Under his leadership, NCC became a public limited company in 1990 and expanded into one of India's prominent listed constr..

Next Story
Infrastructure Transport

Embraer to Acquire 51 Per Cent Stake in Mahindra Aerospace Arm

Brazilian aerospace major Embraer will acquire a 51 per cent equity stake in Novavayu Aerospace, a step-down subsidiary of Mahindra and Mahindra, under an Investment Agreement notified by the automobile company in an exchange filing. The transaction will give Embraer control of the aerospace business. Following completion of the acquisition, Novavayu Aerospace will cease to be a wholly owned subsidiary and become an associate of Mahindra Defence Systems, which is a step-down wholly owned subsidiary of Mahindra and Mahindra. The agreement is expected to be completed on or before December 1. Mah..

Next Story
Infrastructure Urban

RBI Opens Special Dollar Window for Three State-Run OMCs

The Reserve Bank of India (RBI) has opened a special facility to meet the entire daily US dollar requirements of three public sector oil marketing companies (OMCs), in a move aimed at easing pressure on the Indian rupee. The facility will take effect on October 12, 2026, and remain available until further notice. Indian Oil Corporation, Hindustan Petroleum Corporation and Bharat Petroleum Corporation are eligible to use the arrangement. Under the facility, the RBI will sell US dollars to the three companies through designated banks, allowing them to meet their oil-import payments without sourc..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

SPECIAL OFFER
QR Code