NHAI Eyes November Opening For One Carriageway Of Kulur Bridge
ROADS & HIGHWAYS

NHAI Eyes November Opening For One Carriageway Of Kulur Bridge

The National Highways Authority of India is targeting the opening of one carriageway of the long delayed Kulur bridge in Mangaluru by the end of November as work on the six-lane structure over the Gurupura (Phalguni) river continues to lag. The bridge on National Highway 66 is located about seven kilometres north of Mangaluru city centre and is being built between two existing structures, a 1952-era bowstring arch used for southbound traffic and a reinforced concrete girder bridge carrying northbound movement.

NHAI officials indicated that girder launching has been pending, with a total of 60 girders already fabricated and stored at the Baikampady yard awaiting installation. They said the remaining work, including completion of pier caps atop the bridge piers, was expected to take several months and contractors have been instructed to accelerate the pace. Most of the required pier caps have been finished, with only a small number of locations still pending at the most recent review.

The new bridge has been designed with a total width of 41 metres, comprising a 28-metre-wide main carriageway accommodating six lanes, with a separate service road alongside. Once the main carriageway becomes operational, vehicular movement on the existing 1952 arch bridge will be restricted and the older structure is to be permanently closed to traffic. A new service road and footpath are planned beside the old bridge, but construction of the service road has been deferred until pipelines running along the older structure are relocated.

The Kulur project has faced repeated delays over the years, prompting local political representatives, including Dakshina Kannada member of parliament Capt Brijesh Chowta, to press NHAI for expedited completion. Officials have told authorities and the contractor that remaining works must be finished before the onset of the monsoon season because heavy rainfall typically disrupts coastal construction activity. The Kulur stretch forms part of wider upgrades along NH 66 in and around Mangaluru, where several bridge and flyover projects at Pumpwell, Thokkottu and Gurupura have experienced extended delays due to funding constraints, contractor issues and land related hurdles.

With NHAI targeting a partial opening by the end of November, commuters on the Mangaluru-Udupi route are likely to see some relief on the long pending crossing, even as full completion of the bridge, including the service road and pedestrian pathways, remains contingent on further progress in the months ahead. Authorities will monitor progress and adjust timelines as necessary.

The National Highways Authority of India is targeting the opening of one carriageway of the long delayed Kulur bridge in Mangaluru by the end of November as work on the six-lane structure over the Gurupura (Phalguni) river continues to lag. The bridge on National Highway 66 is located about seven kilometres north of Mangaluru city centre and is being built between two existing structures, a 1952-era bowstring arch used for southbound traffic and a reinforced concrete girder bridge carrying northbound movement. NHAI officials indicated that girder launching has been pending, with a total of 60 girders already fabricated and stored at the Baikampady yard awaiting installation. They said the remaining work, including completion of pier caps atop the bridge piers, was expected to take several months and contractors have been instructed to accelerate the pace. Most of the required pier caps have been finished, with only a small number of locations still pending at the most recent review. The new bridge has been designed with a total width of 41 metres, comprising a 28-metre-wide main carriageway accommodating six lanes, with a separate service road alongside. Once the main carriageway becomes operational, vehicular movement on the existing 1952 arch bridge will be restricted and the older structure is to be permanently closed to traffic. A new service road and footpath are planned beside the old bridge, but construction of the service road has been deferred until pipelines running along the older structure are relocated. The Kulur project has faced repeated delays over the years, prompting local political representatives, including Dakshina Kannada member of parliament Capt Brijesh Chowta, to press NHAI for expedited completion. Officials have told authorities and the contractor that remaining works must be finished before the onset of the monsoon season because heavy rainfall typically disrupts coastal construction activity. The Kulur stretch forms part of wider upgrades along NH 66 in and around Mangaluru, where several bridge and flyover projects at Pumpwell, Thokkottu and Gurupura have experienced extended delays due to funding constraints, contractor issues and land related hurdles. With NHAI targeting a partial opening by the end of November, commuters on the Mangaluru-Udupi route are likely to see some relief on the long pending crossing, even as full completion of the bridge, including the service road and pedestrian pathways, remains contingent on further progress in the months ahead. Authorities will monitor progress and adjust timelines as necessary.

Related Stories

Gold Stories

Next Story
Infrastructure Transport

Bevel Gears India Opens Aerospace Gear Plant Near Bengaluru

Bevel Gears India (BGI) has inaugurated a 70,000 sq ft manufacturing facility near Kempegowda International Airport in Bengaluru, dedicated exclusively to aerospace and defence gearing.The facility has been developed to manufacture flight-critical gearing with dedicated production, inspection and quality infrastructure. It will produce spiral and straight bevel gears, zerol and angular bevels, beveloids, hypoid and high-ratio hypoid gears, curvic couplings and precision parallel-axis gearing.The plant will cater to aero-engine, helicopter, UAV, actuation and aerospace gearbox programmes, suppo..

Next Story
Infrastructure Urban

Tata Hitachi Opens New Warehouse at Kharagpur Plant

Tata Hitachi Construction Machinery Company has inaugurated a new warehouse at its Kharagpur manufacturing facility in West Bengal to strengthen its supply chain and improve customer support across India.The facility was inaugurated by Sandeep Singh, Managing Director, Tata Hitachi, in the presence of Hiroshi Hosokawa, President – Spare Parts & Service Business Unit and Executive Officer, along with the company’s senior leadership and employees.The new warehouse is designed to enhance warehousing and inventory management capabilities, enabling more efficient handling and availability o..

Next Story
Infrastructure Urban

Vishnu Chemicals, DCX Chrome Form JV for Chromium Plant

Vishnu Chemicals Limited (VCL) has entered into a definitive joint venture agreement with France-based DCX Chrome SAS to establish a greenfield high-purity chromium metal manufacturing facility in Visakhapatnam, Andhra Pradesh.The two companies will hold equal 50% stakes in the proposed venture. The facility will have an installed capacity of 6,000 metric tonnes per annum and will manufacture high-purity chromium metal for applications across the aerospace, defence, energy, oil and gas, and chemical processing sectors.Under the partnership, DCX Chrome will provide its proprietary aluminothermi..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

SPECIAL OFFER
QR Code