NICE Toll Collection Reaches Rs. 47.56 bn, Kumaraswamy Alleges
ROADS & HIGHWAYS

NICE Toll Collection Reaches Rs. 47.56 bn, Kumaraswamy Alleges

Union Minister for Heavy Industries and Steel HD Kumaraswamy has alleged that Nandi Infrastructure Corridor Enterprises (NICE) collected Rs. 47.56 bn in toll between 2008 and 2025, nearly three times the original project cost, despite the infrastructure project remaining incomplete. He demanded an immediate halt to toll collection on the road.

Addressing a press conference at the Janata Dal (Secular) headquarters in Bengaluru, Kumaraswamy said the original project cost was Rs. 15.84 bn. He stated that annual toll receipts rose from Rs. 55.9 mn in 2008-09 to Rs. 7.35 bn in 2024-25. He linked the collection to a Toll Concession Agreement signed in 2000 between the state Public Works Department and NICE.

According to Kumaraswamy, the agreement required a four-lane concrete road, service roads and maintenance areas to be completed before toll collection began. He said these conditions had not been fully met when toll collection started in 2008. He also referred to a Karnataka High Court judgment dated July 29, which he said found that changes to the original agreement through an Outline Development Plan amounted to a violation of statutory and constitutional provisions.

Kumaraswamy alleged that the project alignment was altered without Cabinet approval, increasing land allocation for the Peripheral Road from 2,193 acres to 2,747 acres and for the toll road from 6,999 acres to 9,468 acres. He also raised allegations of roads being constructed over lake areas, citing a 2021 complaint based on locations identified through the Dishaank application.

He said NICE had also generated Rs. 3.84 bn through land sales, Rs. 1.08 bn as advances for joint development and construction projects, and Rs. 3.38 bn from convention centres. Kumaraswamy noted that the Supreme Court had not stayed the High Court judgment and had listed NICE's challenge for November 2, with 25 lawyers appearing. He urged the state government to act under the court proceedings and original agreements, rejecting suggestions that toll collection could continue for another 10 years.

Union Minister for Heavy Industries and Steel HD Kumaraswamy has alleged that Nandi Infrastructure Corridor Enterprises (NICE) collected Rs. 47.56 bn in toll between 2008 and 2025, nearly three times the original project cost, despite the infrastructure project remaining incomplete. He demanded an immediate halt to toll collection on the road. Addressing a press conference at the Janata Dal (Secular) headquarters in Bengaluru, Kumaraswamy said the original project cost was Rs. 15.84 bn. He stated that annual toll receipts rose from Rs. 55.9 mn in 2008-09 to Rs. 7.35 bn in 2024-25. He linked the collection to a Toll Concession Agreement signed in 2000 between the state Public Works Department and NICE. According to Kumaraswamy, the agreement required a four-lane concrete road, service roads and maintenance areas to be completed before toll collection began. He said these conditions had not been fully met when toll collection started in 2008. He also referred to a Karnataka High Court judgment dated July 29, which he said found that changes to the original agreement through an Outline Development Plan amounted to a violation of statutory and constitutional provisions. Kumaraswamy alleged that the project alignment was altered without Cabinet approval, increasing land allocation for the Peripheral Road from 2,193 acres to 2,747 acres and for the toll road from 6,999 acres to 9,468 acres. He also raised allegations of roads being constructed over lake areas, citing a 2021 complaint based on locations identified through the Dishaank application. He said NICE had also generated Rs. 3.84 bn through land sales, Rs. 1.08 bn as advances for joint development and construction projects, and Rs. 3.38 bn from convention centres. Kumaraswamy noted that the Supreme Court had not stayed the High Court judgment and had listed NICE's challenge for November 2, with 25 lawyers appearing. He urged the state government to act under the court proceedings and original agreements, rejecting suggestions that toll collection could continue for another 10 years.

Related Stories

Gold Stories

Next Story
Infrastructure Transport

Alluri Sitarama Raju International Airport

An airport can be structurally complete and still not be ready to fly. At Alluri Sitarama Raju International Airport at Bhogapuram, that distinction defines the project. Developed under a public-private partnership (PPP) between GMR Group and the Government of Andhra Pradesh at a cost of over Rs 56.40 billion, the greenfield airport began commercial operations on August 17, 2026, with an initial capacity of 6 million passengers annually. Its 77,342-sq-m terminal, 3,800-m Code 4E runway, 18 aircraft stands and 55-m ATC tower establish the scale. The more revealing story, however, is how the pro..

Next Story
Infrastructure Energy

Newmark India Completes First Year, Eyes Growth in 2027 Triveni Power Transmission Wins Silver at MUSE Creative Awards

Triveni Power Transmission Limited (TPTL) has won Silver in the Website – Branding category at the 2026 MUSE Creative Awards: Season 2, gaining international recognition for its newly developed corporate website. The platform highlights the company's engineering heritage, independent corporate identity and global growth ambitions.The MUSE Creative Awards recognise excellence in creative communication across digital platforms, branding, advertising, content and marketing. TPTL was selected from more than 5,000 submissions worldwide, evaluated anonymously by an international jury comprising 77..

Next Story
Real Estate

Newmark India Completes First Year, Eyes Growth in 2027

Newmark India has completed its first year of operations, strengthening its presence in the country's commercial real estate sector. The company has established its leadership and operational framework, expanded across key markets and secured mandates from a diverse client base.Entering its second year, Newmark India plans to accelerate sustainable growth through integrated services, technology adoption, talent development and stronger client partnerships. The company aims to combine Newmark's global expertise with local market knowledge to serve occupiers, investors and developers.Sathish Raj..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

SPECIAL OFFER
QR Code