Power Cable Shifting Delays Sardar Patel Road Widening
ROADS & HIGHWAYS

Power Cable Shifting Delays Sardar Patel Road Widening

The State Highways Department’s Rs. 480 mn project to widen Sardar Patel Road between the Highway Research Station and Anna University has reached 50 per cent completion. The 1.85-km project began in December 2025 with a 12-month deadline, but work has been delayed by about two months because high-tension (HT) cables along the route have not yet been shifted.

Officials said the remaining work could be completed within two months after the cables are moved. Progress had initially been steady, but rising bitumen prices and delays in obtaining support from the Tamil Nadu Power Distribution Corporation for shifting the cables have slowed construction.

The section between Anna University and Madhya Kailash has been completed. The department has sought permission from the National Green Tribunal to cut trees in Guindy National Park for widening the section between the Cancer Institute and the park. Work near Gandhi Mandapam is also under way.

Temporary arches installed for Gandhi Jayanthi and the death anniversary of Kamarajar on October 2 remain in place. Officials said the structures would be removed in the coming days, allowing work to resume. Once the cable shifting is complete, the department plans to align the median and install lighting along the road.

A Tamil Nadu Power Distribution Corporation official said the shifting of the Ring Main Unit, or RMU, was scheduled for Saturday and would take one to two days. Residents have raised concerns about the slow progress on the arterial road, which serves Anna University, Guindy National Park, Gandhi Mandapam, the Kamarajar Memorial and Lok Bhavan.

The road carries heavy traffic during peak hours, with vehicles from Rajiv Gandhi Salai often backing up between the Indian Institute of Technology Madras campus and the Gandhi Mandapam Road intersection. Residents have urged the authorities to complete the project before the monsoon intensifies, citing concerns about prolonged congestion and disruption.

The State Highways Department’s Rs. 480 mn project to widen Sardar Patel Road between the Highway Research Station and Anna University has reached 50 per cent completion. The 1.85-km project began in December 2025 with a 12-month deadline, but work has been delayed by about two months because high-tension (HT) cables along the route have not yet been shifted. Officials said the remaining work could be completed within two months after the cables are moved. Progress had initially been steady, but rising bitumen prices and delays in obtaining support from the Tamil Nadu Power Distribution Corporation for shifting the cables have slowed construction. The section between Anna University and Madhya Kailash has been completed. The department has sought permission from the National Green Tribunal to cut trees in Guindy National Park for widening the section between the Cancer Institute and the park. Work near Gandhi Mandapam is also under way. Temporary arches installed for Gandhi Jayanthi and the death anniversary of Kamarajar on October 2 remain in place. Officials said the structures would be removed in the coming days, allowing work to resume. Once the cable shifting is complete, the department plans to align the median and install lighting along the road. A Tamil Nadu Power Distribution Corporation official said the shifting of the Ring Main Unit, or RMU, was scheduled for Saturday and would take one to two days. Residents have raised concerns about the slow progress on the arterial road, which serves Anna University, Guindy National Park, Gandhi Mandapam, the Kamarajar Memorial and Lok Bhavan. The road carries heavy traffic during peak hours, with vehicles from Rajiv Gandhi Salai often backing up between the Indian Institute of Technology Madras campus and the Gandhi Mandapam Road intersection. Residents have urged the authorities to complete the project before the monsoon intensifies, citing concerns about prolonged congestion and disruption.

Related Stories

Gold Stories

Next Story
Real Estate

Address Maker sells over 200 Apollo Address plots in six weeks

The Address Maker Group has sold more than two-thirds of the inventory at its Apollo Address villa-plot development in Nelamangala, North-West Bengaluru, within six weeks of its launch. With over 200 plots purchased and approximately 100 remaining, the project has recorded the fastest sales pace in the developer's history.Spread across 23 acres within a larger 90-acre township, Apollo Address offers villa plots ranging from 1,200 to 2,400 sq ft. Inspired by classical Greek architecture, the development features planned infrastructure, landscaped open spaces and residential amenities.Nearly 30 ..

Next Story
Equipment

Zoomlion strengthens equipment partnerships in Australia

Zoomlion Heavy Industry Science & Technology has reaffirmed its commitment to expanding operations in Australia, with Chairman and CEO Zhan Chunxin meeting customers and business partners in Sydney to strengthen long-term partnerships and discuss opportunities for closer collaboration.The meeting, held on 4 November 2026, focused on equipment quality, technical support, spare parts availability, local training and customer service improvements. Representatives from the tower crane, concrete machinery, earthmoving, aerial work platform, agricultural machinery and financial sectors participa..

Next Story
Real Estate

Rahul Mehta Architects unveils Mumbai cruise terminal design

Rahul Mehta Architects has unveiled the architectural design of the Mumbai International Cruise Terminal (MICT), described as India's first organised international cruise terminal. Located at Indira Dock, the project aims to transform Mumbai's historic waterfront into a destination combining cruise operations, retail, hospitality and public spaces.Appointed by maritime and logistics group JM Baxi, the architectural practice has designed the terminal to meet international cruise operational standards while creating a year-round public destination. The project has been developed under a public-p..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

SPECIAL OFFER
QR Code