Pune Ring Road Cost Rises by Rs. 105.02 bn as Maharashtra Bills Mount
ROADS & HIGHWAYS

Pune Ring Road Cost Rises by Rs. 105.02 bn as Maharashtra Bills Mount

The Maharashtra government has approved an additional Rs. 105.02 bn for the Pune Ring Road after the National Highways Authority of India (NHAI) failed to take up a key stretch on a priority basis. The package will be transferred to the Maharashtra State Road Development Corporation (MSRDC), taking the project’s total estimated cost to Rs. 532.13 bn.

The Cabinet sub-committee on infrastructure approved the revised administrative sanction on August 18, 2026. The allocation covers civil works and land acquisition for the package previously assigned to the NHAI. The government said MSRDC was already incurring land acquisition expenses and that completing the stretch was necessary for the ring road to meet its intended objective.

The project cost had risen to Rs. 427.11 bn in 2024 after the state approved an escalation of Rs. 203.75 bn. The eastern stretch was initially estimated at Rs. 101.6 bn in September 2021, but its revised length increased from 68.19 km to 72.335 km and its estimated cost rose to Rs. 199.33 bn in 2024. The western stretch’s cost increased from Rs. 121.76 bn to Rs. 227.78 bn over the same period.

The ring road comprises eastern and western sections designed to reduce congestion around Pune. The eastern section links Urse on the Mumbai-Pune Expressway with Solu and Sortapwadi, while the western section runs from Urse to Varve Budruk on the Pune-Satara road. A 31.805-km section is also shared by the proposed Pune-Chhatrapati Sambhajinagar Greenfield Expressway and the eastern ring road.

The additional spending comes as Maharashtra faces competing financial commitments. Outstanding public debt is projected to reach Rs. 1.1 tn in 2026-27, while the revenue deficit is estimated at Rs. 405.52 bn. The state has also budgeted for welfare and agricultural support, including the Rs. 1,500 monthly Ladki Bahin payment, a farm loan waiver and Rs. 5,000 assistance per farmer in 304 tehsils. Its fiscal deficit is estimated at Rs. 1.5 tn, or 2.8 per cent of Gross State Domestic Product, with the revenue deficit at 0.7 per cent.

The Maharashtra government has approved an additional Rs. 105.02 bn for the Pune Ring Road after the National Highways Authority of India (NHAI) failed to take up a key stretch on a priority basis. The package will be transferred to the Maharashtra State Road Development Corporation (MSRDC), taking the project’s total estimated cost to Rs. 532.13 bn. The Cabinet sub-committee on infrastructure approved the revised administrative sanction on August 18, 2026. The allocation covers civil works and land acquisition for the package previously assigned to the NHAI. The government said MSRDC was already incurring land acquisition expenses and that completing the stretch was necessary for the ring road to meet its intended objective. The project cost had risen to Rs. 427.11 bn in 2024 after the state approved an escalation of Rs. 203.75 bn. The eastern stretch was initially estimated at Rs. 101.6 bn in September 2021, but its revised length increased from 68.19 km to 72.335 km and its estimated cost rose to Rs. 199.33 bn in 2024. The western stretch’s cost increased from Rs. 121.76 bn to Rs. 227.78 bn over the same period. The ring road comprises eastern and western sections designed to reduce congestion around Pune. The eastern section links Urse on the Mumbai-Pune Expressway with Solu and Sortapwadi, while the western section runs from Urse to Varve Budruk on the Pune-Satara road. A 31.805-km section is also shared by the proposed Pune-Chhatrapati Sambhajinagar Greenfield Expressway and the eastern ring road. The additional spending comes as Maharashtra faces competing financial commitments. Outstanding public debt is projected to reach Rs. 1.1 tn in 2026-27, while the revenue deficit is estimated at Rs. 405.52 bn. The state has also budgeted for welfare and agricultural support, including the Rs. 1,500 monthly Ladki Bahin payment, a farm loan waiver and Rs. 5,000 assistance per farmer in 304 tehsils. Its fiscal deficit is estimated at Rs. 1.5 tn, or 2.8 per cent of Gross State Domestic Product, with the revenue deficit at 0.7 per cent.

Related Stories

Gold Stories

Next Story
Infrastructure Transport

Thiruvananthapuram Airport to Get Rs. 25 bn Terminal Expansion

Thiruvananthapuram International Airport, managed by Adani Airports, will undergo a Rs. 25 bn terminal expansion under Project Anantha. The project is intended to increase international passenger-handling capacity and improve operational efficiency at the Kerala airport. The groundbreaking ceremony is scheduled for October 15, coinciding with the airport completing five years under its current management. The development will cover approximately 92,552 square metres and raise annual international passenger capacity from 3.5 mn to around 11.5 mn. Project Anantha forms part of a wider transforma..

Next Story
Infrastructure Transport

PM Modi Inaugurates Leh Airport Terminal Costing Rs. 6.4 bn

Prime Minister Narendra Modi inaugurated the new passenger terminal at Leh Airport on October 15, 2026, adding capacity at one of the world’s highest commercial airports. The facility, built at a cost of Rs. 6.4 bn, has been designed to handle 3.5 mn passengers annually and support rising air travel demand in Ladakh. The terminal covers 23,810 square metres and combines modern airport infrastructure with design elements inspired by Ladakh’s local art and cultural heritage. A video shared by Union Civil Aviation Minister Ram Mohan Naidu Kinjarapu showed the check-in area, airline counters, ..

Next Story
Infrastructure Transport

Kerala Examines Land Acquisition for Kannur Airport Expansion

The Kerala government is examining the land acquisition process for the proposed expansion of Kannur International Airport and plans to take an early decision on difficulties faced by affected families, Chief Minister V D Satheesan told the state Assembly on Thursday. He was responding to a submission by MLA T K Govindan. The proposed project involves extending the airport runway from 3,050 metres to 4,000 metres. The government granted administrative sanction on December 27, 2016, to acquire 99.92 hectares, but the process remains incomplete despite a notification issued in 2017. The governme..