Rs. 87 mn Bridge Near Karwar Lies Unused After Planning Lapses
ROADS & HIGHWAYS

Rs. 87 mn Bridge Near Karwar Lies Unused After Planning Lapses

The Comptroller and Auditor General (CAG) has flagged planning and execution failures in a compliance audit of road and bridge projects for the year ended March 2024. The review found inflated estimates, inadequate project sequencing and poor use of materials in works undertaken by a public works department.

A bridge linking Siddarnayawad village with Umblejoog village near Karwar in Uttara Kannada district has remained unused since its completion in January 2022. The structure, built at a cost of Rs. 87 mn, has no approach roads connecting it to the existing road network, leaving it non-operational.

The audit said the department had not planned the roads properly through the Planning and Road Asset Management Centre while preparing estimates. It also failed to reuse available excavated soil, wet mix macadam and granular sub-base. Auditors identified inaccurate embankment calculations, excessive tender premiums and departures from Indian Road Congress and Ministry of Road Transport and Highways design standards.

Errors in the Schedule of Rates, including incorrect conversion factors, further raised the estimated costs. The audit said the department did not examine alternatives such as cement-treated sub-base, reclaimed asphalt pavement or plastic-based bitumen roads. It classified the bridge spending as unfruitful because land acquisition for the approach roads had not started when the project was reviewed.

The department told auditors that landowners had agreed during an initial survey and that acquisition was under way, with approach road construction planned afterwards. The auditors recommended expediting acquisition and requiring confirmation of land availability before future construction begins.

The report also examined a queue complex behind the Male Mahadeshwara temple at MM Hills. The work was awarded to Damodar Raju in April 2021 for Rs. 187 mn without a specified completion period. In a separate case involving improvements to the state highway to Hulsur in Aland, the audit called for recovery of Rs. 50 mn in excess payment and attributed the avoidable liability to delayed finalisation.

The Comptroller and Auditor General (CAG) has flagged planning and execution failures in a compliance audit of road and bridge projects for the year ended March 2024. The review found inflated estimates, inadequate project sequencing and poor use of materials in works undertaken by a public works department. A bridge linking Siddarnayawad village with Umblejoog village near Karwar in Uttara Kannada district has remained unused since its completion in January 2022. The structure, built at a cost of Rs. 87 mn, has no approach roads connecting it to the existing road network, leaving it non-operational. The audit said the department had not planned the roads properly through the Planning and Road Asset Management Centre while preparing estimates. It also failed to reuse available excavated soil, wet mix macadam and granular sub-base. Auditors identified inaccurate embankment calculations, excessive tender premiums and departures from Indian Road Congress and Ministry of Road Transport and Highways design standards. Errors in the Schedule of Rates, including incorrect conversion factors, further raised the estimated costs. The audit said the department did not examine alternatives such as cement-treated sub-base, reclaimed asphalt pavement or plastic-based bitumen roads. It classified the bridge spending as unfruitful because land acquisition for the approach roads had not started when the project was reviewed. The department told auditors that landowners had agreed during an initial survey and that acquisition was under way, with approach road construction planned afterwards. The auditors recommended expediting acquisition and requiring confirmation of land availability before future construction begins. The report also examined a queue complex behind the Male Mahadeshwara temple at MM Hills. The work was awarded to Damodar Raju in April 2021 for Rs. 187 mn without a specified completion period. In a separate case involving improvements to the state highway to Hulsur in Aland, the audit called for recovery of Rs. 50 mn in excess payment and attributed the avoidable liability to delayed finalisation.

Related Stories

Gold Stories

Next Story
Building Material

From Rough to Refined: How Modern Plastering Is Changing Wall Finishes

When Rohan first walked into his newly constructed home, he imagined what it would become—a warm living room, a bright bedroom, and walls smooth enough to complement his carefully chosen interiors.But there was one problem.The walls didn't look anything like the finished home he had imagined.They were uneven in places, rough to the touch, and covered with visible patches and minor surface imperfections. Rohan initially thought paint would fix everything.His contractor had a different answer.“Before the paint, we need to get the plastering right.”That conversation made Rohan realise somet..

Next Story
Infrastructure Urban

Embraer to Acquire 51 Per Cent Stake in Mahindra Aerospace Arm

Brazilian aerospace major Embraer will acquire a 51 per cent equity stake in Novavayu Aerospace, a step-down subsidiary of Mahindra and Mahindra, under an Investment Agreement notified by the automobile company in an exchange filing. The transaction will give Embraer control of the aerospace business. Following completion of the acquisition, Novavayu Aerospace will cease to be a wholly owned subsidiary and become an associate of Mahindra Defence Systems, which is a step-down wholly owned subsidiary of Mahindra and Mahindra. The agreement is expected to be completed on or before December 1. Mah..

Next Story
Infrastructure Urban

RBI Opens Special Dollar Window for Three State-Run OMCs

The Reserve Bank of India (RBI) has opened a special facility to meet the entire daily US dollar requirements of three public sector oil marketing companies (OMCs), in a move aimed at easing pressure on the Indian rupee. The facility will take effect on October 12, 2026, and remain available until further notice. Indian Oil Corporation, Hindustan Petroleum Corporation and Bharat Petroleum Corporation are eligible to use the arrangement. Under the facility, the RBI will sell US dollars to the three companies through designated banks, allowing them to meet their oil-import payments without sourc..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

SPECIAL OFFER
QR Code