Rs. 87 mn Bridge Near Karwar Lies Unused After Planning Lapses
ROADS & HIGHWAYS

Rs. 87 mn Bridge Near Karwar Lies Unused After Planning Lapses

The Comptroller and Auditor General (CAG) has flagged planning and execution failures in a compliance audit of road and bridge projects for the year ended March 2024. The review found inflated estimates, inadequate project sequencing and poor use of materials in works undertaken by a public works department.

A bridge linking Siddarnayawad village with Umblejoog village near Karwar in Uttara Kannada district has remained unused since its completion in January 2022. The structure, built at a cost of Rs. 87 mn, has no approach roads connecting it to the existing road network, leaving it non-operational.

The audit said the department had not planned the roads properly through the Planning and Road Asset Management Centre while preparing estimates. It also failed to reuse available excavated soil, wet mix macadam and granular sub-base. Auditors identified inaccurate embankment calculations, excessive tender premiums and departures from Indian Road Congress and Ministry of Road Transport and Highways design standards.

Errors in the Schedule of Rates, including incorrect conversion factors, further raised the estimated costs. The audit said the department did not examine alternatives such as cement-treated sub-base, reclaimed asphalt pavement or plastic-based bitumen roads. It classified the bridge spending as unfruitful because land acquisition for the approach roads had not started when the project was reviewed.

The department told auditors that landowners had agreed during an initial survey and that acquisition was under way, with approach road construction planned afterwards. The auditors recommended expediting acquisition and requiring confirmation of land availability before future construction begins.

The report also examined a queue complex behind the Male Mahadeshwara temple at MM Hills. The work was awarded to Damodar Raju in April 2021 for Rs. 187 mn without a specified completion period. In a separate case involving improvements to the state highway to Hulsur in Aland, the audit called for recovery of Rs. 50 mn in excess payment and attributed the avoidable liability to delayed finalisation.

The Comptroller and Auditor General (CAG) has flagged planning and execution failures in a compliance audit of road and bridge projects for the year ended March 2024. The review found inflated estimates, inadequate project sequencing and poor use of materials in works undertaken by a public works department. A bridge linking Siddarnayawad village with Umblejoog village near Karwar in Uttara Kannada district has remained unused since its completion in January 2022. The structure, built at a cost of Rs. 87 mn, has no approach roads connecting it to the existing road network, leaving it non-operational. The audit said the department had not planned the roads properly through the Planning and Road Asset Management Centre while preparing estimates. It also failed to reuse available excavated soil, wet mix macadam and granular sub-base. Auditors identified inaccurate embankment calculations, excessive tender premiums and departures from Indian Road Congress and Ministry of Road Transport and Highways design standards. Errors in the Schedule of Rates, including incorrect conversion factors, further raised the estimated costs. The audit said the department did not examine alternatives such as cement-treated sub-base, reclaimed asphalt pavement or plastic-based bitumen roads. It classified the bridge spending as unfruitful because land acquisition for the approach roads had not started when the project was reviewed. The department told auditors that landowners had agreed during an initial survey and that acquisition was under way, with approach road construction planned afterwards. The auditors recommended expediting acquisition and requiring confirmation of land availability before future construction begins. The report also examined a queue complex behind the Male Mahadeshwara temple at MM Hills. The work was awarded to Damodar Raju in April 2021 for Rs. 187 mn without a specified completion period. In a separate case involving improvements to the state highway to Hulsur in Aland, the audit called for recovery of Rs. 50 mn in excess payment and attributed the avoidable liability to delayed finalisation.

Related Stories

Gold Stories

Next Story
Resources

Kalpataru Projects International elevates Amit Uplenchwar as Joint MD and CEO

Kalpataru Projects International (KPIL) has elevated Amit Uplenchwar as Joint Managing Director and CEO (designate), following approval by its board on 5 November 2026. He will take charge as Additional Director, Joint Managing Director and CEO from 1 January 2027 for a five-year term ending 31 December 2031, subject to shareholders' approval.Uplenchwar brings over three decades of experience in corporate strategy, business operations, business development, mergers and acquisitions, and international business management. His experience spans transportation, power, water, oil and gas, aerospace..

Next Story
Resources

HCC appoints Vivek Singhal as CEO

Hindustan Construction Company (HCC) has appointed Vivek Singhal as Chief Executive Officer, effective 5 November 2026. He brings over four decades of experience in infrastructure and engineering, procurement and construction (EPC), covering project execution, business leadership, business development and profit and loss management.Singhal has spent 16 years in international markets, delivering projects and managing assets worth approximately Rs 285 billion across five countries. His experience spans airports, metro rail, urban transport, hydropower, bridges and other infrastructure sectors.He..

Next Story
Infrastructure Energy

Essar Signs PPA for 300 MW Hybrid Renewable Energy Project

Essar Renewables, the renewable energy arm of Essar Power, has signed a Power Purchase Agreement (PPA) with NHPC for a 300 MW renewable energy project in Andhra Pradesh. The agreement follows the company’s successful bid for the project two years ago. Essar Power will invest approximately Rs. 45 bn in the development. The project will combine solar and wind generation with Battery Energy Storage Systems (BESS), enabling the supply of reliable and dispatchable renewable power. It forms part of Essar Power’s plan to build a diversified energy portfolio of approximately 5 GW across renewable,..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

SPECIAL OFFER
QR Code