Soil Tests Underway For 13.5-km Elevated Corridor Along East Coast Road
ROADS & HIGHWAYS

Soil Tests Underway For 13.5-km Elevated Corridor Along East Coast Road

Soil investigations have started along the East Coast Road in Chennai for the 13.5-km Thiruvanmiyur–Uthandi elevated corridor. The contractor has set up temporary barricades on medians while conducting tests at 430 locations where pillars are planned. The corridor will be a four-lane structure and is expected to take a little over three years to build. Excavation of shallow boreholes and trial pits will mark the initial field work.

The project carries a budget of Rs 21 billion (Rs 21 bn) and aims to ease traffic congestion on the popular coastal stretch. Geotechnical teams will extract soil samples to determine the depth and sequence of sand, clay, soft rock and hard rock layers. Investigations will extend to depths of up to 25 metres to inform foundation design. Laboratory testing will assess bearing capacity, compressibility and groundwater conditions to support safe design.

An engineer associated with the work said samples would be analysed by the design department to determine foundation types and other structural parameters. The tests are scheduled over the next few months and will guide the design of pile foundations and related structures. Officials indicated that soil data will also influence construction sequencing and resource allocation. The design department will model load transfer and select suitable pile lengths and diameters based on the soil profiles.

Local travel is expected to be affected during the testing phase by temporary barricades and periodic drilling activities, and authorities have advised motorists to follow diversion signage. Project managers plan to incorporate the geotechnical findings into detailed drawings before commencing major piling and superstructure work. Once underway, the elevated corridor is intended to improve travel times and urban connectivity along the East Coast Road. Stakeholders expect the findings to reduce unforeseen delays during construction and to refine cost estimates.

Soil investigations have started along the East Coast Road in Chennai for the 13.5-km Thiruvanmiyur–Uthandi elevated corridor. The contractor has set up temporary barricades on medians while conducting tests at 430 locations where pillars are planned. The corridor will be a four-lane structure and is expected to take a little over three years to build. Excavation of shallow boreholes and trial pits will mark the initial field work. The project carries a budget of Rs 21 billion (Rs 21 bn) and aims to ease traffic congestion on the popular coastal stretch. Geotechnical teams will extract soil samples to determine the depth and sequence of sand, clay, soft rock and hard rock layers. Investigations will extend to depths of up to 25 metres to inform foundation design. Laboratory testing will assess bearing capacity, compressibility and groundwater conditions to support safe design. An engineer associated with the work said samples would be analysed by the design department to determine foundation types and other structural parameters. The tests are scheduled over the next few months and will guide the design of pile foundations and related structures. Officials indicated that soil data will also influence construction sequencing and resource allocation. The design department will model load transfer and select suitable pile lengths and diameters based on the soil profiles. Local travel is expected to be affected during the testing phase by temporary barricades and periodic drilling activities, and authorities have advised motorists to follow diversion signage. Project managers plan to incorporate the geotechnical findings into detailed drawings before commencing major piling and superstructure work. Once underway, the elevated corridor is intended to improve travel times and urban connectivity along the East Coast Road. Stakeholders expect the findings to reduce unforeseen delays during construction and to refine cost estimates.

Related Stories

Gold Stories

Next Story
Infrastructure Urban

Sabarmati Riverfront Two Plots Up for Auction at Rs2.24 bn Base Price

Two commercial plots on the western bank of the Sabarmati Riverfront will be auctioned with a base price of Rs 112 crore each, equivalent to Rs 1.12 bn apiece and Rs 2.24 billion in total. The parcels are located adjacent to the Metro Rail Bridge in Ahmedabad and form the first commercial offering after a prolonged pause. The Riverfront Development Corporation has framed the sale as part of a phased commercial release to revive development along the riverfront. The combined base valuation has been set by the corporation to reflect market rates along the riverfront. The corporation has fixed a ..

Next Story
Infrastructure Urban

Andhra Pradesh to Connect Over One Million Streetlights

Andhra Pradesh will undertake a statewide smart streetlighting programme across all 123 Urban Local Bodies (ULBs), bringing around 1.05 million (mn) streetlights under an AI enabled monitoring and management system. The programme will be implemented by Energy Efficiency Services Limited (EESL) with the Commissioner and Director of Municipal Administration under the state Municipal Administration and Urban Development Department. The project aims to convert conventional streetlighting into a digitally managed municipal service monitored and maintained remotely. The initial phase will cover abou..

Next Story
Infrastructure Urban

AMC To Procure Four Machines For Guard Rail Cleaning

Ahmedabad Municipal Corporation will introduce four specialised machines for cleaning guard railings along major roads and the central verges of BRTS and Metro corridors. The civic body plans to replace manual labour with mechanised cleaning to improve maintenance of road infrastructure and greenery. The purchase is estimated at Rs 82.8 million (mn), excluding GST. The proposal sets the base price of each machine at about Rs 20.7 million (mn) so four units total Rs 82.8 million (mn) before GST. 18 per cent GST will be applicable separately. During the warranty period each machine will operate ..

Advertisement