Sridhar Babu Sets September 30 Deadline for Road Widening
ROADS & HIGHWAYS

Sridhar Babu Sets September 30 Deadline for Road Widening

Information Technology and Industries Minister D Sridhar Babu (the minister) inspected the Bahadurpally–Kompally road widening project at Dulapally and instructed officials to complete the works within the stipulated timelines. During the inspection he reviewed the project progress and ordered the removal of bottlenecks that were delaying operations along the corridor. The minister called for a focused effort to expedite pending activities and to ensure contractor mobilisation and resource allocation proceed without further hindrance.

He directed the authorities to complete the shifting of electrical poles along the forest stretch by August 15 and to finish the road widening works by September 30. The minister also instructed the Hyderabad Metropolitan Development Authority (HMDA) to prepare and submit detailed proposals for stormwater drains to the City Municipal Corporation (CMC) for examination and necessary action. The objective was to ensure adequate drainage along the corridor and to prevent waterlogging once the carriageway widening is complete.

He asked officials to prioritise land acquisition processes in Dulapally and Bahadurpally and to resolve title and compensation issues expeditiously. The minister expected close coordination between revenue, public works and utility departments to accelerate clearances and to enable uninterrupted construction. Officials were urged to monitor contractor progress and to report bottlenecks promptly so that remedial measures could be implemented. The aim was to adhere to the deadline and to minimise time overruns that increase costs.

The minister instructed officials to furnish regular progress updates and to submit timelines for pending subactivities to his office for periodic review. He recommended proactive management of environmental and safety clearances and the deployment of traffic management plans during construction to reduce inconvenience to commuters. Completion of the widened corridor will improve connectivity between residential and industrial zones and support smoother movement of goods and people along the route.

Information Technology and Industries Minister D Sridhar Babu (the minister) inspected the Bahadurpally–Kompally road widening project at Dulapally and instructed officials to complete the works within the stipulated timelines. During the inspection he reviewed the project progress and ordered the removal of bottlenecks that were delaying operations along the corridor. The minister called for a focused effort to expedite pending activities and to ensure contractor mobilisation and resource allocation proceed without further hindrance. He directed the authorities to complete the shifting of electrical poles along the forest stretch by August 15 and to finish the road widening works by September 30. The minister also instructed the Hyderabad Metropolitan Development Authority (HMDA) to prepare and submit detailed proposals for stormwater drains to the City Municipal Corporation (CMC) for examination and necessary action. The objective was to ensure adequate drainage along the corridor and to prevent waterlogging once the carriageway widening is complete. He asked officials to prioritise land acquisition processes in Dulapally and Bahadurpally and to resolve title and compensation issues expeditiously. The minister expected close coordination between revenue, public works and utility departments to accelerate clearances and to enable uninterrupted construction. Officials were urged to monitor contractor progress and to report bottlenecks promptly so that remedial measures could be implemented. The aim was to adhere to the deadline and to minimise time overruns that increase costs. The minister instructed officials to furnish regular progress updates and to submit timelines for pending subactivities to his office for periodic review. He recommended proactive management of environmental and safety clearances and the deployment of traffic management plans during construction to reduce inconvenience to commuters. Completion of the widened corridor will improve connectivity between residential and industrial zones and support smoother movement of goods and people along the route.

Related Stories

Gold Stories

Next Story
Resources

Schindler named among Forbes’ World’s Best Employers 2026

Schindler has been named among Forbes’ World’s Best Employers 2026, a global ranking recognising companies for their workplace environments.Compiled by Forbes in partnership with Statista, the ranking is based on independent employee feedback, including whether employees would recommend their organisation to friends and family.The company said the recognition reflected its focus on creating a workplace where employees can develop their expertise and build careers. ..

Next Story
Infrastructure Urban

India needs an export-execution mindset: Vishesh Jain

Interview with Vishesh Jain, Founder & CEO, EximpleWhat gaps in India’s global trade ecosystem led you to build Eximple, and what problem did you see businesses struggling with most?Eximple came out of a problem that all three founders had seen from different choke points in the trade ecosystem. India has millions of MSMEs and manufacturers, and many of them can make products that are genuinely competitive on quality. Yet only a small fraction is able to build meaningful international businesses. In our experience, the gap is usually not manufacturing capability; it is the ability to exe..

Next Story
Building Material

Nuvoco reports 13.5% revenue growth in Q2 FY27

Nuvoco Vistas Corp. Ltd. reported consolidated revenue of Rs 27.9 billion for Q2 FY27, up 13.5% year on year. Cement sales volume rose 9% to 4.7 million tonnes (MMT), while EBITDA increased 11% to Rs 4.11 billion.The company said it began its cement operations in 2014 with a 2.3 MMT per annum (MMTPA) operation at Nimbol. It now aims to reach 35 MMTPA of cement capacity by FY28, nearly 15 times its initial capacity. Its portfolio spans cement, ready-mix concrete and modern building materials.On sustainability and cost efficiency, Nuvoco partnered with CleanMax for a 46.4 MW wind-solar hybrid re..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

SPECIAL OFFER
QR Code