Sridhar Babu Sets September 30 Deadline for Road Widening
ROADS & HIGHWAYS

Sridhar Babu Sets September 30 Deadline for Road Widening

Information Technology and Industries Minister D Sridhar Babu (the minister) inspected the Bahadurpally–Kompally road widening project at Dulapally and instructed officials to complete the works within the stipulated timelines. During the inspection he reviewed the project progress and ordered the removal of bottlenecks that were delaying operations along the corridor. The minister called for a focused effort to expedite pending activities and to ensure contractor mobilisation and resource allocation proceed without further hindrance.

He directed the authorities to complete the shifting of electrical poles along the forest stretch by August 15 and to finish the road widening works by September 30. The minister also instructed the Hyderabad Metropolitan Development Authority (HMDA) to prepare and submit detailed proposals for stormwater drains to the City Municipal Corporation (CMC) for examination and necessary action. The objective was to ensure adequate drainage along the corridor and to prevent waterlogging once the carriageway widening is complete.

He asked officials to prioritise land acquisition processes in Dulapally and Bahadurpally and to resolve title and compensation issues expeditiously. The minister expected close coordination between revenue, public works and utility departments to accelerate clearances and to enable uninterrupted construction. Officials were urged to monitor contractor progress and to report bottlenecks promptly so that remedial measures could be implemented. The aim was to adhere to the deadline and to minimise time overruns that increase costs.

The minister instructed officials to furnish regular progress updates and to submit timelines for pending subactivities to his office for periodic review. He recommended proactive management of environmental and safety clearances and the deployment of traffic management plans during construction to reduce inconvenience to commuters. Completion of the widened corridor will improve connectivity between residential and industrial zones and support smoother movement of goods and people along the route.

Information Technology and Industries Minister D Sridhar Babu (the minister) inspected the Bahadurpally–Kompally road widening project at Dulapally and instructed officials to complete the works within the stipulated timelines. During the inspection he reviewed the project progress and ordered the removal of bottlenecks that were delaying operations along the corridor. The minister called for a focused effort to expedite pending activities and to ensure contractor mobilisation and resource allocation proceed without further hindrance. He directed the authorities to complete the shifting of electrical poles along the forest stretch by August 15 and to finish the road widening works by September 30. The minister also instructed the Hyderabad Metropolitan Development Authority (HMDA) to prepare and submit detailed proposals for stormwater drains to the City Municipal Corporation (CMC) for examination and necessary action. The objective was to ensure adequate drainage along the corridor and to prevent waterlogging once the carriageway widening is complete. He asked officials to prioritise land acquisition processes in Dulapally and Bahadurpally and to resolve title and compensation issues expeditiously. The minister expected close coordination between revenue, public works and utility departments to accelerate clearances and to enable uninterrupted construction. Officials were urged to monitor contractor progress and to report bottlenecks promptly so that remedial measures could be implemented. The aim was to adhere to the deadline and to minimise time overruns that increase costs. The minister instructed officials to furnish regular progress updates and to submit timelines for pending subactivities to his office for periodic review. He recommended proactive management of environmental and safety clearances and the deployment of traffic management plans during construction to reduce inconvenience to commuters. Completion of the widened corridor will improve connectivity between residential and industrial zones and support smoother movement of goods and people along the route.

Next Story
Infrastructure Urban

SCLR Extension Nears Completion Linking BKC With Signal-Free Route

The Santacruz-Chembur Link Road (SCLR) extension towards Bandra-Kurla Complex (BKC) via the Mumbai University campus has entered its final stage, bringing motorists closer to a direct, signal-free connection between the Western Express Highway and the city’s commercial district. The elevated connector is being built as an arm from the SCLR alignment and will link the western suburbs with BKC without surface signals. The link is designed to reduce journey times for commuters travelling from the western suburbs to BKC and to improve access to eastern Mumbai. By carrying through traffic above s..

Next Story
Infrastructure Transport

Raiganj MP Seeks Bengal Only Highway Link To Siliguri

Raiganj Member of Parliament Kartik Chandra Paul met Union Minister for Road Transport and Highways Nitin Gadkari in New Delhi to press for a new stretch of national highway in North Dinajpur district. He urged approval for a Bengal-to-Bengal link that would connect National Highways 12 and 27 to allow vehicles bound for Siliguri to avoid the current route through Kishanganj in neighbouring Bihar. He also submitted a proposed alignment of the new road to the ministry for consideration. At present vehicles from Raiganj travel along NH-12 and join NH-27 at Purnia More in Dalkhola, a route that p..

Next Story
Infrastructure Transport

Airport Kilambakkam Metro Line To Be Extended To Chengalpattu

Chennai Metro Rail (CMRL) has invited tenders for two detailed project reports that would extend its rail network to Chengalpattu in the south and extend Corridor-5 to Wimco Nagar in the north as part of a second wave of expansion beyond the operator's corridors under construction. The move signals an acceleration of planning for suburban links and interchange nodes. The larger of the two studies covers a roughly 27km extension from the planned Kilambakkam metro station to Chengalpattu under Corridor-1, Phase I. CMRL floated the tender at an estimated cost of Rs 21.6 mn. The proposed line woul..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement