Chennai Metro Completes Ullagaram-Sholinganallur Precast Work
RAILWAYS & METRO RAIL

Chennai Metro Completes Ullagaram-Sholinganallur Precast Work

Chennai Metro Rail (CMRL) has completed casting all precast elements, including the final U-girder, for the Ullagaram-Sholinganallur stretch of Phase II Corridor 5. The completion marks a significant construction milestone for the elevated metro section and concludes the precast scope of the ECV-03 package.

The package involved casting 3,126 precast elements. These comprised 1,041 I-girders, 892 U-girders, 871 pier arm segments, 303 pier caps and 19 portal shells, according to information issued by CMRL on Tuesday.

With 892 U-girders cast, ECV-03 recorded the highest U-girder production among the packages being implemented under the Phase II project. The construction activity used 98,052 cubic metres of concrete, 18,550 t of reinforcement steel and 3,010 t of high-tensile strands.

The work was completed through coordinated efforts by CMRL, its general consultant AEON Consortium and the contractor HCC-KEC Consortium. The milestone was marked in the presence of CMRL Director (Projects) T. Archunan and officials representing the metro operator, consultant and contractor.

Following completion of the final U-girder, the project will proceed with erecting the remaining U-girders and constructing the entry and exit structures. CMRL said these activities are progressing as part of the wider effort to complete Chennai Metro Phase II on schedule. The latest milestone enables the project team to focus on the remaining structural and access-related works along the corridor.

The Ullagaram-Sholinganallur section is being developed as part of Corridor 5 in the second phase of the Chennai Metro expansion. The completion of casting provides the project with the full set of precast components required for the remaining erection activities in the ECV-03 package.

Chennai Metro Rail (CMRL) has completed casting all precast elements, including the final U-girder, for the Ullagaram-Sholinganallur stretch of Phase II Corridor 5. The completion marks a significant construction milestone for the elevated metro section and concludes the precast scope of the ECV-03 package. The package involved casting 3,126 precast elements. These comprised 1,041 I-girders, 892 U-girders, 871 pier arm segments, 303 pier caps and 19 portal shells, according to information issued by CMRL on Tuesday. With 892 U-girders cast, ECV-03 recorded the highest U-girder production among the packages being implemented under the Phase II project. The construction activity used 98,052 cubic metres of concrete, 18,550 t of reinforcement steel and 3,010 t of high-tensile strands. The work was completed through coordinated efforts by CMRL, its general consultant AEON Consortium and the contractor HCC-KEC Consortium. The milestone was marked in the presence of CMRL Director (Projects) T. Archunan and officials representing the metro operator, consultant and contractor. Following completion of the final U-girder, the project will proceed with erecting the remaining U-girders and constructing the entry and exit structures. CMRL said these activities are progressing as part of the wider effort to complete Chennai Metro Phase II on schedule. The latest milestone enables the project team to focus on the remaining structural and access-related works along the corridor. The Ullagaram-Sholinganallur section is being developed as part of Corridor 5 in the second phase of the Chennai Metro expansion. The completion of casting provides the project with the full set of precast components required for the remaining erection activities in the ECV-03 package.

Related Stories

Gold Stories

Next Story
Real Estate

IGBC Green Building Congress 2026 advances India’s net-zero agenda

The Indian Green Building Council (IGBC), part of the Confederation of Indian Industry (CII), opened the 24th edition of the Green Building Congress 2026 at the Jio World Convention Centre, Mumbai, with a focus on accelerating India's green and net-zero building movement. The three-day event, being held from 26 to 28 November, brought together policymakers, industry leaders and sustainability experts to discuss green buildings, climate-resilient infrastructure and sustainable communities.A key highlight of the inaugural session was the launch of five pilot rating systems: Green Retail, DigiBui..

Next Story
Real Estate

Maharashtra CM inaugurates fifth Model Sub-Registrar Office in Mumbai

Maharashtra Chief Minister Devendra Fadnavis has inaugurated a Model Sub-Registrar Office (SRO) in Lower Parel, Mumbai, taking the number of such centres launched in the state to five. The initiative aims to modernise property registration services through technology-enabled infrastructure and citizen-centric processes.Developed by the Government of Maharashtra in association with VFS Global and WE Excel Software, the Lower Parel centre follows the launch of Model SROs in Pune, Bandra Kurla Complex in Mumbai, Navi Mumbai and Nagpur.The centres provide facilities for registering property-relate..

Next Story
Infrastructure Transport

NHBF hails Indian Army aircraft operations on Amritsar–Jamnagar corridor

The National Highways Builders Federation (NHBF) has welcomed the successful landing and take-off of four Indian Army microlight aircraft on the Amritsar–Jamnagar Economic Corridor (NH-754K) in Gujarat. The exercise demonstrated the potential of highway infrastructure to support defence operations and emergency response. The expressway was developed by CDS Infra Projects, an NHBF member company.Developed under the Bharatmala Pariyojana, the six-lane greenfield corridor is described as India's second-longest expressway. The operation was conducted by the Indian Army's Team Mountain Eagles as ..

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

SPECIAL OFFER
QR Code