Kasheli Metro Depot Reaches 23 Per Cent Progress
RAILWAYS & METRO RAIL

Kasheli Metro Depot Reaches 23 Per Cent Progress

The Mumbai Metropolitan Region Development Authority (MMRDA) has reported completion of 23 per cent of construction work on the Kasheli Metro depot as of June 2026. The depot will serve as the operations, maintenance and stabling facility for Metro Line 5 that connects Thane, Bhiwandi, Kalyan and Ulhasnagar. The authority said the progress reflects ongoing site works and preliminary civil structures being established to receive rail systems and depot equipment in later phases.

Spread across nearly 27 hectares near the Kasheli Toll Plaza, the depot site secured statutory environmental clearances in August 2025. The facility is being developed to support the rolling stock fleet and long-term operations of the nearly 32 km Metro Line 5 corridor, including workshops, stabling yards and administrative areas. Land assembly and access arrangements have been completed for primary construction, enabling contractors to advance earthworks, foundations and service corridors.

MMRDA is implementing a phased construction strategy intended to make key depot facilities operational at the earliest feasible stages, allowing selective commissioning of systems ahead of full depot completion. Early operational areas will permit progressive testing, train stabling and routine maintenance activities while other sections continue under construction. The approach is designed to align depot delivery with train procurement and depot commissioning schedules to reduce operational bottlenecks once the corridor is ready for service.

The authority reported ongoing coordination with contractors and utility agencies to manage timelines, safety and environmental compliances during construction. Continued progress at the Kasheli depot is integral to the wider Metro Line 5 project and its objective of improving regional transit capacity. MMRDA will monitor works and report milestones as construction advances towards full completion.

"Join industry leaders at RAHSTA Expo, India's premier platform for roads, highways and traffic infrastructure. Register now to explore innovations, network with experts and shape the future of mobility."

The Mumbai Metropolitan Region Development Authority (MMRDA) has reported completion of 23 per cent of construction work on the Kasheli Metro depot as of June 2026. The depot will serve as the operations, maintenance and stabling facility for Metro Line 5 that connects Thane, Bhiwandi, Kalyan and Ulhasnagar. The authority said the progress reflects ongoing site works and preliminary civil structures being established to receive rail systems and depot equipment in later phases. Spread across nearly 27 hectares near the Kasheli Toll Plaza, the depot site secured statutory environmental clearances in August 2025. The facility is being developed to support the rolling stock fleet and long-term operations of the nearly 32 km Metro Line 5 corridor, including workshops, stabling yards and administrative areas. Land assembly and access arrangements have been completed for primary construction, enabling contractors to advance earthworks, foundations and service corridors. MMRDA is implementing a phased construction strategy intended to make key depot facilities operational at the earliest feasible stages, allowing selective commissioning of systems ahead of full depot completion. Early operational areas will permit progressive testing, train stabling and routine maintenance activities while other sections continue under construction. The approach is designed to align depot delivery with train procurement and depot commissioning schedules to reduce operational bottlenecks once the corridor is ready for service. The authority reported ongoing coordination with contractors and utility agencies to manage timelines, safety and environmental compliances during construction. Continued progress at the Kasheli depot is integral to the wider Metro Line 5 project and its objective of improving regional transit capacity. MMRDA will monitor works and report milestones as construction advances towards full completion.

Next Story
Infrastructure Transport

Uttar Pradesh Accelerates National Highway Projects

Uttar Pradesh Chief Minister Yogi Adityanath met Union Road Transport and Highways Minister Nitin Gadkari to review National Highway and road infrastructure projects. Officials from the National Highways Authority of India presented progress updates and proposals. Ministers directed acceleration of land acquisition, forest clearances, utility shifting and other formalities to expedite delivery. Officials said that since 2014 about 10,204 kilometres of National Highway projects have been awarded and nearly 9,329 kilometres completed, with 606 kilometres approved and 1,010 kilometres completed b..

Next Story
Infrastructure Transport

NHAI Completes Repairs at 33 of 40 Spots Along Gurugram NH-48

The National Highways Authority of India has rectified 33 of 40 deficient locations along an 11km stretch of the Delhi–Gurugram NH-48 corridor, following a joint inspection by the authority, the Municipal Corporation of Gurugram and the Gurugram Metropolitan Development Authority. The audit identified damaged footpaths, crash barriers, inadequate lane markings and poor sanitation at multiple points between Rajiv Chowk and Signature Towers. Repairs and maintenance works have been carried out over May and June as part of the exercise. The report noted broken crash barriers and roadside litteri..

Next Story
Infrastructure Urban

Mankhurd Maharashtra Nagar Flyover To Open By August 2027

The Brihanmumbai Municipal Corporation has said the Mankhurd-Maharashtra Nagar flyover will be operational by August 2027, as part of measures to ease congestion in the eastern suburbs. The structure will provide a direct link from the T Junction on the Sion-Panvel highway to the existing Ghatkopar-Mankhurd Link Road. The T Junction is one of the major traffic choke points in the eastern suburbs and records heavy flows of vehicles travelling to and from Navi Mumbai and Pune. Motorists currently spend more than 15 minutes at the signal during peak periods, according to civic data, prompting the..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement