Kasheli Metro Depot Reaches 23 Per Cent Progress
RAILWAYS & METRO RAIL

Kasheli Metro Depot Reaches 23 Per Cent Progress

The Mumbai Metropolitan Region Development Authority (MMRDA) has reported completion of 23 per cent of construction work on the Kasheli Metro depot as of June 2026. The depot will serve as the operations, maintenance and stabling facility for Metro Line 5 that connects Thane, Bhiwandi, Kalyan and Ulhasnagar. The authority said the progress reflects ongoing site works and preliminary civil structures being established to receive rail systems and depot equipment in later phases.

Spread across nearly 27 hectares near the Kasheli Toll Plaza, the depot site secured statutory environmental clearances in August 2025. The facility is being developed to support the rolling stock fleet and long-term operations of the nearly 32 km Metro Line 5 corridor, including workshops, stabling yards and administrative areas. Land assembly and access arrangements have been completed for primary construction, enabling contractors to advance earthworks, foundations and service corridors.

MMRDA is implementing a phased construction strategy intended to make key depot facilities operational at the earliest feasible stages, allowing selective commissioning of systems ahead of full depot completion. Early operational areas will permit progressive testing, train stabling and routine maintenance activities while other sections continue under construction. The approach is designed to align depot delivery with train procurement and depot commissioning schedules to reduce operational bottlenecks once the corridor is ready for service.

The authority reported ongoing coordination with contractors and utility agencies to manage timelines, safety and environmental compliances during construction. Continued progress at the Kasheli depot is integral to the wider Metro Line 5 project and its objective of improving regional transit capacity. MMRDA will monitor works and report milestones as construction advances towards full completion.

The Mumbai Metropolitan Region Development Authority (MMRDA) has reported completion of 23 per cent of construction work on the Kasheli Metro depot as of June 2026. The depot will serve as the operations, maintenance and stabling facility for Metro Line 5 that connects Thane, Bhiwandi, Kalyan and Ulhasnagar. The authority said the progress reflects ongoing site works and preliminary civil structures being established to receive rail systems and depot equipment in later phases. Spread across nearly 27 hectares near the Kasheli Toll Plaza, the depot site secured statutory environmental clearances in August 2025. The facility is being developed to support the rolling stock fleet and long-term operations of the nearly 32 km Metro Line 5 corridor, including workshops, stabling yards and administrative areas. Land assembly and access arrangements have been completed for primary construction, enabling contractors to advance earthworks, foundations and service corridors. MMRDA is implementing a phased construction strategy intended to make key depot facilities operational at the earliest feasible stages, allowing selective commissioning of systems ahead of full depot completion. Early operational areas will permit progressive testing, train stabling and routine maintenance activities while other sections continue under construction. The approach is designed to align depot delivery with train procurement and depot commissioning schedules to reduce operational bottlenecks once the corridor is ready for service. The authority reported ongoing coordination with contractors and utility agencies to manage timelines, safety and environmental compliances during construction. Continued progress at the Kasheli depot is integral to the wider Metro Line 5 project and its objective of improving regional transit capacity. MMRDA will monitor works and report milestones as construction advances towards full completion.

Related Stories

Gold Stories

Next Story
Infrastructure Transport

MMRDA Targets Completion of Projects by December 2028

The Mumbai Metropolitan Region Development Authority (MMRDA) is targeting the completion of all its ongoing infrastructure projects by December 2028, a year ahead of its December 2029 deadline, Metropolitan Commissioner Dr Sanjay Mukherjee has said.Speaking at the sixth edition of the Real Estate & Infrastructure Investors' Summit (REIIS) 2026 in Mumbai, Mukherjee said the authority was developing an integrated network of roads, tunnels, sea links and Metro corridors under its broader vision of “Mumbai in 59 Minutes”.The objective is to improve east-west and north-south connectivity an..

Next Story
Building Material

High-Performance Façades Gain Ground in Indian Buildings

High-performance façades are gaining greater importance in Indian architecture as developers and architects increasingly focus on energy efficiency, thermal comfort and building performance, according to Shankar Fenestrations & Glasses.The company said modern façade systems are increasingly being considered as part of a building's overall performance strategy rather than being used primarily as aesthetic elements.High-performance glass, curtain wall systems and structural glazing can contribute to thermal regulation, solar control, daylight management and indoor comfort. Their growing ad..

Next Story
Technology

SPML Infra's 104.4 kWh BESS Battery Pack Clears Global Tests

SPML Infra has announced that its proprietary 104.4 kWh Battery Energy Storage System (BESS) battery pack has completed key international safety, performance and transportation testing and certification requirements, marking a step towards its commercial deployment.Developed under the company's own intellectual property, the battery pack has completed requirements under UL9540A, IEC 62619, IEC 63056, IEC 60730, IEC 61000-6-2, IEC 61000-6-4 and UN38.3 standards.The testing covers areas including thermal runaway safety, battery performance, system functional safety, electromagnetic compatibility..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

SPECIAL OFFER
QR Code