Around 14 km of city roads under TRDC to get facelift soon
SMART CITIES

Around 14 km of city roads under TRDC to get facelift soon

Around 14 kilometres of city roads under the Thiruvananthapuram Road Development Company (TRDC) will get a facelift soon.

The company, a concessionaire of the City Roads Improvement Project (CRIP), has begun removing the top layer of the rubberised road to resurface it as part of maintenance. The Kerala Road Fund Board (KRFB) of the state public works department (PWD) is overseeing the resurfacing.

Though the summer rain has halted work in many areas, TRDC is confident about finishing the renovation by July-end. But the removal of the top layer has made commuting challenging through several stretches, mainly for two-wheelers.

As several roads were dug up for the Smart Roads project, people had to bear with travelling on bumpy roads. The 14 km of stretches under maintenance are Manmohan Bungalow-Kowdiar, LMS-Vellayambalam, Asan Square-Panchapura Junction, and LMS-Ayyankali Hall Junction, Enchakkal-Sreekanteswaram, Kerala University-Chackai, Vanross-Press Club Road, and the road around the Secretariat. A new culvert around Poonthi road is also part of the project.

A senior officer with TRDC told the media that efforts are being made to finish the renovation of all these roads by July-end.

The rain has disrupted, and postponed, the work. If the rain stays away, the renovation work can finish within 15 days, the officer said.

RFB general manager K J Satheesh Kumar told the media that the company failed to complete the work when TRDC was assigned for resurfacing roads in 2019. The TRDC has agreed to renovate the roads this time before August.

According to the bump integrator (BI) tests conducted in December 2016 and June 2017, under the supervision of an independent engineer, most corridors did not fall within the defined quality. However, TRDC had claimed that the tested portions lacked quality due to utility works.

At the same time, the PWD urged TRDC to take up the relaying work. Till the completion of work the PWD also withheld annuity payment.

TRDC gets a half-yearly annuity payment of Rs 17.74 crore as per the contract. If the concessionaire fails to take up maintenance work, KRFB can undertake repairs, and the company would be responsible to reimburse one-and-a-half times the expense to KRFB.

Under the build-operate-transfer (BOT) model, CRIP was implemented for the improvement of 42.067 km of roads in 17 corridors. The project was to be finished within 32 months, with TRDC supposed to maintain it for 15 years. The project, though stalled, was finished in four phases.

Image Source

Also read: 11 roads in Vypeen region to be renovated soon

Around 14 kilometres of city roads under the Thiruvananthapuram Road Development Company (TRDC) will get a facelift soon. The company, a concessionaire of the City Roads Improvement Project (CRIP), has begun removing the top layer of the rubberised road to resurface it as part of maintenance. The Kerala Road Fund Board (KRFB) of the state public works department (PWD) is overseeing the resurfacing. Though the summer rain has halted work in many areas, TRDC is confident about finishing the renovation by July-end. But the removal of the top layer has made commuting challenging through several stretches, mainly for two-wheelers. As several roads were dug up for the Smart Roads project, people had to bear with travelling on bumpy roads. The 14 km of stretches under maintenance are Manmohan Bungalow-Kowdiar, LMS-Vellayambalam, Asan Square-Panchapura Junction, and LMS-Ayyankali Hall Junction, Enchakkal-Sreekanteswaram, Kerala University-Chackai, Vanross-Press Club Road, and the road around the Secretariat. A new culvert around Poonthi road is also part of the project. A senior officer with TRDC told the media that efforts are being made to finish the renovation of all these roads by July-end. The rain has disrupted, and postponed, the work. If the rain stays away, the renovation work can finish within 15 days, the officer said. RFB general manager K J Satheesh Kumar told the media that the company failed to complete the work when TRDC was assigned for resurfacing roads in 2019. The TRDC has agreed to renovate the roads this time before August. According to the bump integrator (BI) tests conducted in December 2016 and June 2017, under the supervision of an independent engineer, most corridors did not fall within the defined quality. However, TRDC had claimed that the tested portions lacked quality due to utility works. At the same time, the PWD urged TRDC to take up the relaying work. Till the completion of work the PWD also withheld annuity payment. TRDC gets a half-yearly annuity payment of Rs 17.74 crore as per the contract. If the concessionaire fails to take up maintenance work, KRFB can undertake repairs, and the company would be responsible to reimburse one-and-a-half times the expense to KRFB. Under the build-operate-transfer (BOT) model, CRIP was implemented for the improvement of 42.067 km of roads in 17 corridors. The project was to be finished within 32 months, with TRDC supposed to maintain it for 15 years. The project, though stalled, was finished in four phases. Image Source Also read: 11 roads in Vypeen region to be renovated soon

Next Story
Products

Koemmerling opens Navi Mumbai experience centre

Koemmerling, a brand of the profine Group, has expanded its presence in the Mumbai metropolitan region with the opening of a new experience centre in Navi Mumbai and launched its Allure S46 minimal sliding door system for the Indian market.Located in CBD Belapur, the facility was inaugurated by Peter Mrosik, Owner and CEO, profine Group, along with Farid Khan, Chairman and Managing Director, profine India, and Kamal Bajaj, CEO, profine India.The company said the new centre will showcase its portfolio of uPVC and aluminium window and door systems to architects, developers and homeowners.The ina..

Next Story
Products

India's waterproofing market nears Rs 150 bn milestone

India's waterproofing industry is approaching a market size of Rs 150 billion and is expected to surpass the $2 billion milestone, according to speakers at the 2nd India International Waterproofers Conference & Expo 2026 organised by the Waterproofers Association of India (WAI) in New Delhi.The two-day event brought together more than 20 speakers, 55 international delegates and 53 exhibition booths, with discussions focusing on climate-resilient construction, advanced waterproofing technologies and international collaboration.Inaugurating the event, Durga Shanker Mishra, former Secretary, ..

Next Story
Real Estate

Dilip Buildcon Q1 FY27 Revenue at Rs 23.78 billion

Dilip Buildcon Limited reported consolidated revenue from operations of Rs 2,378 crore in Q1 FY27, along with EBITDA of Rs 429 crore and profit after tax of Rs 128 crore.Consolidated EBITDA margin stood at 18.1%, improving from 17.1% in Q4 FY26. On a standalone basis, revenue from operations was Rs 1,930 crore, EBITDA stood at Rs 199 crore and PAT was Rs 39 crore, with an EBITDA margin of 10.3%.The company’s order book stood at Rs 27,691 crore as of 30 June 2026, compared with Rs 28,830 crore as of 31 March 2026. Roads and highways accounted for 17.1% of the order book, irrigation and water ..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement