Case Studies of Indian companies following Lean Construction
ROADS & HIGHWAYS

Case Studies of Indian companies following Lean Construction

When HCC was constructing the two-tier Bogibeel Bridge—the country’s longest rail-cum-road bridge—placing the 125-m long fully-welded steel spans, each weighing 1,700 tonne, on the pillars embedded in the riverbed was a challenge. “On-site engineers had two choices for a more practical and economical method, either lifting the spans with floating cranes or erecting them with a launching truss,” shares Amit Uplenchwar, CEO, HCC E&C. “After weighing the pros and cons, the team came up with a third solution of pulling the steel trusses with a set of jacks and winches on the pillars. This eliminated the need to enter the river. Besides, it also ensured safer working conditions, precluded the mobilisation of a giant setup on either side of the river and accelerated the project’s pace. The strategy proved testament to the global practice of Lean construction, which is changing the way projects are executed from design to construction.”

Shapoorji Pallonji Engineering & Construction has implemented Lean for an IT park spread over 40 acre with a built-up area of 3.5 m sq ft. It required coordination among 46 contractors having more than 2,000 workers at a time. “The project was struggling with coordination issues within and among teams, and wastage of material and labour at the same time,” says SC Dixit, Executive Director, Shapoorji Pallonji Engineering & Construction. “The implementation of Lean tools such as Last Planner System (LPS) helped in coordination and streamlining communication, while Value Stream Mapping (VSM) practices helped in reducing man days and improving productivity. Further, pull-based planning ensured optimistic targets, which is further reinforced by the rest of the tools, resulting in improved productivity; and a sense of waste reduction is nurtured in the team, which resulted in improved coordination and higher percentage plan completion.”

At one of Tata Realty and Infrastructure’s recent projects in Gurugram, a large SEZ project of about 5 million sq ft, “we have implemented Lean and created a Big Room,” says Prakash Patil, Secretary General, The Institute for Lean Construction Excellence, and Vice President-Projects, Tata Realty and Infrastructure. “We are using the Last Planner (r) System (LPS), Pull Planning, BIM etc, extensively here.”

- SERAPHINA D’SOUZA

When HCC was constructing the two-tier Bogibeel Bridge—the country’s longest rail-cum-road bridge—placing the 125-m long fully-welded steel spans, each weighing 1,700 tonne, on the pillars embedded in the riverbed was a challenge. “On-site engineers had two choices for a more practical and economical method, either lifting the spans with floating cranes or erecting them with a launching truss,” shares Amit Uplenchwar, CEO, HCC E&C. “After weighing the pros and cons, the team came up with a third solution of pulling the steel trusses with a set of jacks and winches on the pillars. This eliminated the need to enter the river. Besides, it also ensured safer working conditions, precluded the mobilisation of a giant setup on either side of the river and accelerated the project’s pace. The strategy proved testament to the global practice of Lean construction, which is changing the way projects are executed from design to construction.”Shapoorji Pallonji Engineering & Construction has implemented Lean for an IT park spread over 40 acre with a built-up area of 3.5 m sq ft. It required coordination among 46 contractors having more than 2,000 workers at a time. “The project was struggling with coordination issues within and among teams, and wastage of material and labour at the same time,” says SC Dixit, Executive Director, Shapoorji Pallonji Engineering & Construction. “The implementation of Lean tools such as Last Planner System (LPS) helped in coordination and streamlining communication, while Value Stream Mapping (VSM) practices helped in reducing man days and improving productivity. Further, pull-based planning ensured optimistic targets, which is further reinforced by the rest of the tools, resulting in improved productivity; and a sense of waste reduction is nurtured in the team, which resulted in improved coordination and higher percentage plan completion.”At one of Tata Realty and Infrastructure’s recent projects in Gurugram, a large SEZ project of about 5 million sq ft, “we have implemented Lean and created a Big Room,” says Prakash Patil, Secretary General, The Institute for Lean Construction Excellence, and Vice President-Projects, Tata Realty and Infrastructure. “We are using the Last Planner (r) System (LPS), Pull Planning, BIM etc, extensively here.”- SERAPHINA D’SOUZA

Next Story
Infrastructure Transport

PM to Inaugurate Indore Metro Phase 1 and Datia Satna Airports on May 31

Prime Minister Narendra Modi is scheduled to inaugurate the first phase of the Indore Metro Rail project, along with the Datia and Satna airports, via video conferencing during his visit to Bhopal on May 31, according to a senior Madhya Pradesh cabinet official.During his day-long visit to Bhopal, the Prime Minister will also participate in a conference organized to commemorate the 300th birth anniversary of Devi Ahilyabai Holkar, the historic queen of the Malwa kingdom, now part of Madhya Pradesh, as stated by the Parliamentary Affairs Minister and Cabinet spokesperson Kailash Vijayvargiya.It..

Next Story
Infrastructure Transport

Kochi Metro Holds Talks with BPCL to Restore Greenery on Medians

Kochi Metro Rail (KMRL), facing increasing criticism for not maintaining the green spaces along the medians in the metro corridor, has initiated discussions with Bharat Petroleum Corporation (BPCL) and the Ernakulam District Horticulture Society to revive the project.Sources reveal that KMRL is also making fresh efforts to find sponsors to care for and maintain the gardens located between the metro pillars. Previously, several sponsors had withdrawn, which led to the neglect of these green areas.There are 989 medians along the 28-km Kochi Metro stretch. Of these, 465 are under the National Hig..

Next Story
Infrastructure Transport

Rajasthan CM Approves DPR for Jaipur Metro Phase-2 Expansion

Rajasthan Chief Minister Bhajanlal Sharma approved the detailed project report (DPR) of Jaipur Metro Phase-2 and forwarded it to the Central Government.The construction work for the project is set to begin once the Union Ministry of Housing and Urban Affairs grants approval to the DPR.Phase 2 of Jaipur Metro had been announced in the state budget for 2025-26.The project, covering a 42.80-km stretch from Todi Mode to Prahladpura, will be implemented by the Rajasthan Metro Rail Corporation—a newly formed 50:50 joint venture between the state and Central governments. The corporation will be res..

Advertisement

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Advertisement

Talk to us?