More than 80 per cent of issues pertained to the state governments
ROADS & HIGHWAYS

More than 80 per cent of issues pertained to the state governments

Arun Goyal, Former Secretary to Government of India and Ex-Head of the Project Monitoring Group (PMG), had a long stint in the Group from October 2015 to February 2019.The group was tasked with fast-tracking, setting up and implementing large public, private and public-private partnership (PPP) projects by resolving a variety of issues. The group mainly dealt with projects with anticipated investment above Rs 10 billion (Rs 5 billion in case of projects with FDI). “The issues uploaded by project proponents on PMG’s portal were resolved through regular review,” says Goyal. “The review was carried through inter-ministerial subgroups and state-level meetings with respective chief secretaries or senior level-officers at state capitals or through video conference.Project proponents were also invited for these review meetings. During my three-and-a-half-year stint at PMG, more than 3,400 issues pertaining to over 720 projects were resolved under the mechanism.” Goyal shares more on solutions to avoid time and cost overruns, in conversation with SERAPHINA D’SOUZA...

  • “I observed that issues leading to time or cost overruns pertained to both the Centre and state governments. Central Government issues included environment, forest and wildlife clearances; eco-sensitive zone clearances; sanction of debt funds and working capital by banks or financial institutions; approval for private railways siding construction; and permission for road crossing of pipelines, transmission lines, railway lines and shifting of utilities. State government issues included land acquisition issues such as government notifications or disbursement of compensation and mutation; removalof encroachments and handing over possession of land; formulation of relief and rehabilitation plans; issue of certificate under the Forest Rights Act; tree-cutting permissions; grant of right of way (RoW) permissions; consent to establish and operate from the State Pollution Control Board; and transfer of government land.
  • I found that most of the issues on our portal pertained to the Central Government’s linear projects such as highways and rail lines, transmission lines and pipelines. Very few issues pertaining to the Central Government were pending on PMG’s portal at a particular time. In the Central Government, rigorous and digital monitoring mechanisms ensured issues were addressed quickly. More than 80 per cent of issues pertained to the state governments. As projects are executed on ground in different states, response varied from state to state. Some states were also slow in responding to issues owing to political reasons.
  • I have observed that once there is cost and time overrun in a public project, project execution tends to get further delayed. In a delayed project, decision-making involves deviations from the terms and conditions of the tender and, at times, the financial implications may be huge. In such circumstances, public-sector executives and civil servants tend be cautious and sometimes the procedures involved are also lengthy.
  • There is another important difference in project execution between the private sector and public sector. A public-sector employee has to follow all procedures of tendering, etc, without consideration of the time and amount already invested into the project. On the other hand, a private-sector executive is able to factor in opportunity and the cost involved because of the amount and time already invested and need not follow all procedures.
  • Overall, I feel there has to be a sense of urgency amongstate-level officials, particularly at the district level, to proactively resolve and expedite local-level issues. This is particularly important for linear projects because, sometimes, a long, linear project with huge investment may get stalled because of issues involved in a small patch of land.”
  • Arun Goyal, Former Secretary to Government of India and Ex-Head of the Project Monitoring Group (PMG), had a long stint in the Group from October 2015 to February 2019.The group was tasked with fast-tracking, setting up and implementing large public, private and public-private partnership (PPP) projects by resolving a variety of issues. The group mainly dealt with projects with anticipated investment above Rs 10 billion (Rs 5 billion in case of projects with FDI). “The issues uploaded by project proponents on PMG’s portal were resolved through regular review,” says Goyal. “The review was carried through inter-ministerial subgroups and state-level meetings with respective chief secretaries or senior level-officers at state capitals or through video conference.Project proponents were also invited for these review meetings. During my three-and-a-half-year stint at PMG, more than 3,400 issues pertaining to over 720 projects were resolved under the mechanism.” Goyal shares more on solutions to avoid time and cost overruns, in conversation with SERAPHINA D’SOUZA... “I observed that issues leading to time or cost overruns pertained to both the Centre and state governments. Central Government issues included environment, forest and wildlife clearances; eco-sensitive zone clearances; sanction of debt funds and working capital by banks or financial institutions; approval for private railways siding construction; and permission for road crossing of pipelines, transmission lines, railway lines and shifting of utilities. State government issues included land acquisition issues such as government notifications or disbursement of compensation and mutation; removalof encroachments and handing over possession of land; formulation of relief and rehabilitation plans; issue of certificate under the Forest Rights Act; tree-cutting permissions; grant of right of way (RoW) permissions; consent to establish and operate from the State Pollution Control Board; and transfer of government land. I found that most of the issues on our portal pertained to the Central Government’s linear projects such as highways and rail lines, transmission lines and pipelines. Very few issues pertaining to the Central Government were pending on PMG’s portal at a particular time. In the Central Government, rigorous and digital monitoring mechanisms ensured issues were addressed quickly. More than 80 per cent of issues pertained to the state governments. As projects are executed on ground in different states, response varied from state to state. Some states were also slow in responding to issues owing to political reasons. I have observed that once there is cost and time overrun in a public project, project execution tends to get further delayed. In a delayed project, decision-making involves deviations from the terms and conditions of the tender and, at times, the financial implications may be huge. In such circumstances, public-sector executives and civil servants tend be cautious and sometimes the procedures involved are also lengthy. There is another important difference in project execution between the private sector and public sector. A public-sector employee has to follow all procedures of tendering, etc, without consideration of the time and amount already invested into the project. On the other hand, a private-sector executive is able to factor in opportunity and the cost involved because of the amount and time already invested and need not follow all procedures. Overall, I feel there has to be a sense of urgency amongstate-level officials, particularly at the district level, to proactively resolve and expedite local-level issues. This is particularly important for linear projects because, sometimes, a long, linear project with huge investment may get stalled because of issues involved in a small patch of land.”

    Next Story
    Infrastructure Transport

    JNPA Becomes First Indian Port to Cross 10 Million TEU Capacity

    The Jawaharlal Nehru Port Authority (JNPA), located at Uran in Navi Mumbai, has become the first port in India to achieve over 10 million TEUs (twenty-foot equivalent units) in container handling capacity.With the recent expansion, the port now operates five container terminals with a combined capacity of 10.4 million TEUs, alongside two liquid and two general cargo terminals.Handling more than half of India’s container traffic, JNPA processed 7.05 million TEUs in 2024 and has moved 15.39 million tonnes of containers and 16.64 million tonnes of total cargo in the first two months of FY 2025..

    Next Story
    Infrastructure Transport

    Nod for Rs. 36.26 billion Expansion of Pune Metro Line 2

    The Union Cabinet has approved the Rs.36.26 billion expansion of Pune Metro Line 2, adding 12.75 km of track and 13 new stations to improve east–west connectivity across the city.The project aims to link Pune’s urban core with rapidly growing suburbs, supporting the city’s rising demand for efficient and sustainable transport solutions. This expansion is part of Corridor 2 of the Pune Metro and includes two key routes: Vanaz to Chandani Chowk (Corridor 2A) and Ramwadi to Wagholi/Vitthalwadi (Corridor 2B).It will connect residential, IT, and educational hubs in areas such as Bavdhan, Koth..

    Next Story
    Infrastructure Transport

    Assembly begins for ‘Nayak’ TBM on Thane– Borivali Twin Tunnel Project

    The assembly of ‘Nayak’, the first of four Tunnel Boring Machines (TBMs) for the Thane–Borivali Twin Tube Tunnel Project, has commenced at the Thane site. Built by German firm Herrenknecht AG and deployed by Megha Engineering & Infrastructure (MEIL), the TBM marks a key milestone in Mumbai’s ambitious 11.8-km underground road corridor beneath Sanjay Gandhi National Park.The twin tunnels will reduce the Thane–Borivali travel distance by 12 km and decongest Thane Ghodbunder Road. ‘Nayak’, with a 13.2-metre diameter, is designed to bore through challenging geological conditions ..

    Advertisement

    Advertisement

    Subscribe to Our Newsletter

    Get daily newsletters around different themes from Construction world.

    STAY CONNECTED

    Advertisement

    Advertisement

    Advertisement

    Advertisement

    Talk to us?