E-way underpasses back on track
Contact:Delhi Integrated
Multi-Modal Transit System Ltd.
Tel: 011-4309 0100.
Fax: 011-2 386 0966.
E-mail: info@dimts.in
Website: www.dimts.in
The detailed project report (DPR) to build three underpasses at IFFCO Chowk, the Signature Tower intersection and Rajiv Chowk on the Delhi-Gurgaon expressway has been submitted to the MCG, for approval. The delay in the project has seen its cost rise by about Rs 19 crore against the original estimate of Rs 760 core by Delhi Integrated Multi-Modal Transit System Ltd (DIMTS). Funds of Rs 110 crore for traffic signage and route diversions, along with Rs 120 crore for tunnelling work will be requested. Contact:Delhi Integrated Multi-Modal Transit System Ltd. Tel: 011-4309 0100. Fax: 011-2 386 0966. E-mail: info@dimts.in Website: www.dimts.in