Andhra Pradesh Sets Strict Timelines for Mining Land NOCs
COAL & MINING

Andhra Pradesh Sets Strict Timelines for Mining Land NOCs

Andhra Pradesh Mines and Geology Principal Secretary Mukesh Kumar Meena has directed officials to adhere strictly to prescribed timelines for processing land no-objection certificates for mining applications and take steps to eliminate pending cases.

Meena conducted a videoconference review meeting with officials from the Mines Directorate, Joint Collectors, District Forest Offices and District Mines and Geology Offices. The meeting reviewed the time-bound NOC mechanism under OMEPS 2.0, with instructions that every application be processed within the specified period and delays escalated through the online system.

Under the revised procedure, a Tahsildar has 14 days from the date of intimation to issue or reject an NOC on the portal. If no action is taken within that period, the application is escalated to the Joint Collector, who has seven days to process it. Continued delays move the application to the District Collector for another seven days, while the Director of Mines and Geology receives an alert at each stage.

Meena asked Joint Collectors and field-level Revenue officials to monitor pending applications closely and comply with the timelines. District Collectors have been instructed to ensure that Tahsildars follow the process, and responsibility will be fixed on officers found guilty of wilful delays or negligence.

He also directed Mines and Geology officials to scrutinise applications properly before forwarding NOC requests to Revenue authorities. Area plans must be submitted through the portal with existing leases clearly demarcated, while proposals involving land within 500 metres of a Reserved Forest must be sent to the concerned District Forest Officer.

The department has been asked to use OMEPS 2.0’s digital monitoring and escalation features effectively. The portal records remarks, document uploads and application forwarding at every stage, while automatically compiling pending cases to support monitoring and timely disposal.

Andhra Pradesh Mines and Geology Principal Secretary Mukesh Kumar Meena has directed officials to adhere strictly to prescribed timelines for processing land no-objection certificates for mining applications and take steps to eliminate pending cases. Meena conducted a videoconference review meeting with officials from the Mines Directorate, Joint Collectors, District Forest Offices and District Mines and Geology Offices. The meeting reviewed the time-bound NOC mechanism under OMEPS 2.0, with instructions that every application be processed within the specified period and delays escalated through the online system. Under the revised procedure, a Tahsildar has 14 days from the date of intimation to issue or reject an NOC on the portal. If no action is taken within that period, the application is escalated to the Joint Collector, who has seven days to process it. Continued delays move the application to the District Collector for another seven days, while the Director of Mines and Geology receives an alert at each stage. Meena asked Joint Collectors and field-level Revenue officials to monitor pending applications closely and comply with the timelines. District Collectors have been instructed to ensure that Tahsildars follow the process, and responsibility will be fixed on officers found guilty of wilful delays or negligence. He also directed Mines and Geology officials to scrutinise applications properly before forwarding NOC requests to Revenue authorities. Area plans must be submitted through the portal with existing leases clearly demarcated, while proposals involving land within 500 metres of a Reserved Forest must be sent to the concerned District Forest Officer. The department has been asked to use OMEPS 2.0’s digital monitoring and escalation features effectively. The portal records remarks, document uploads and application forwarding at every stage, while automatically compiling pending cases to support monitoring and timely disposal.

Related Stories

Gold Stories

Next Story
Infrastructure Urban

VECV Sales Rise 49.6% to 11,396 Units in September

VE Commercial Vehicles Ltd (VECV), a joint venture between Volvo Group and Eicher Motors, recorded sales of 11,396 units in September 2026, up 49.6 per cent from 7,619 units in September 2025.The total included 11,146 units under the Eicher brand and 250 units under the Volvo brand.Eicher-branded trucks and buses recorded sales of 11,146 units during the month, compared with 7,352 units in September 2025, registering growth of 51.6 per cent.In the domestic commercial vehicle market, Eicher trucks and buses reported sales of 10,479 units, up 57.5 per cent from 6,652 units in the corresponding p..

Next Story
Infrastructure Urban

"Agentic AI set to transform supply chain decision-making."

Interview with: Lalit Das, Founder & CEO, Agentra AIWhy the next phase of supply chain technology will be about AI that acts, not just advises?Supply chains no longer have a visibility problem. They have a decision-latency problem. It takes about 8.7 hours to detect a disruption and more than 40 more to understand its impact, all before anyone acts. Meanwhile, disruption costs the global economy an estimated $184 billion a year.Enterprises already own excellent systems of record. What they lack is a system of action. Copilots don't fix that, they just give faster answers about a broken pro..

Next Story
Real Estate

BNW Developments Opens Sydney Office to Target UAE Investors

BNW Developments has expanded its international presence with the opening of a new office in Sydney, Australia, aimed at strengthening engagement with Australian investors interested in the UAE residential property market.The Sydney office will serve as a local platform for investors, wealth advisers, brokerage firms and real estate professionals exploring opportunities in Dubai and Ras Al Khaimah.Headquartered in Dubai, BNW Developments has launched 13 projects and has another 16 projects in its pipeline, representing a combined gross development value of around AED 32 billion (USD 8.7 billio..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

SPECIAL OFFER
QR Code