Andhra Pradesh Sets Strict Timelines for Mining Land NOCs
COAL & MINING

Andhra Pradesh Sets Strict Timelines for Mining Land NOCs

Andhra Pradesh Mines and Geology Principal Secretary Mukesh Kumar Meena has directed officials to adhere strictly to prescribed timelines for processing land no-objection certificates for mining applications and take steps to eliminate pending cases.

Meena conducted a videoconference review meeting with officials from the Mines Directorate, Joint Collectors, District Forest Offices and District Mines and Geology Offices. The meeting reviewed the time-bound NOC mechanism under OMEPS 2.0, with instructions that every application be processed within the specified period and delays escalated through the online system.

Under the revised procedure, a Tahsildar has 14 days from the date of intimation to issue or reject an NOC on the portal. If no action is taken within that period, the application is escalated to the Joint Collector, who has seven days to process it. Continued delays move the application to the District Collector for another seven days, while the Director of Mines and Geology receives an alert at each stage.

Meena asked Joint Collectors and field-level Revenue officials to monitor pending applications closely and comply with the timelines. District Collectors have been instructed to ensure that Tahsildars follow the process, and responsibility will be fixed on officers found guilty of wilful delays or negligence.

He also directed Mines and Geology officials to scrutinise applications properly before forwarding NOC requests to Revenue authorities. Area plans must be submitted through the portal with existing leases clearly demarcated, while proposals involving land within 500 metres of a Reserved Forest must be sent to the concerned District Forest Officer.

The department has been asked to use OMEPS 2.0’s digital monitoring and escalation features effectively. The portal records remarks, document uploads and application forwarding at every stage, while automatically compiling pending cases to support monitoring and timely disposal.

Andhra Pradesh Mines and Geology Principal Secretary Mukesh Kumar Meena has directed officials to adhere strictly to prescribed timelines for processing land no-objection certificates for mining applications and take steps to eliminate pending cases. Meena conducted a videoconference review meeting with officials from the Mines Directorate, Joint Collectors, District Forest Offices and District Mines and Geology Offices. The meeting reviewed the time-bound NOC mechanism under OMEPS 2.0, with instructions that every application be processed within the specified period and delays escalated through the online system. Under the revised procedure, a Tahsildar has 14 days from the date of intimation to issue or reject an NOC on the portal. If no action is taken within that period, the application is escalated to the Joint Collector, who has seven days to process it. Continued delays move the application to the District Collector for another seven days, while the Director of Mines and Geology receives an alert at each stage. Meena asked Joint Collectors and field-level Revenue officials to monitor pending applications closely and comply with the timelines. District Collectors have been instructed to ensure that Tahsildars follow the process, and responsibility will be fixed on officers found guilty of wilful delays or negligence. He also directed Mines and Geology officials to scrutinise applications properly before forwarding NOC requests to Revenue authorities. Area plans must be submitted through the portal with existing leases clearly demarcated, while proposals involving land within 500 metres of a Reserved Forest must be sent to the concerned District Forest Officer. The department has been asked to use OMEPS 2.0’s digital monitoring and escalation features effectively. The portal records remarks, document uploads and application forwarding at every stage, while automatically compiling pending cases to support monitoring and timely disposal.

Related Stories

Gold Stories

Next Story
Infrastructure Urban

Welspun One unveils Diwali campaign for World Trade Center Thane

Welspun One has unveiled A Dream Diwali, a festive brand film promoting World Trade Center Thane, its proposed mixed-use development in the Mumbai Metropolitan Region (MMR). The campaign uses individual interpretations of an ideal Diwali to introduce the experiences and offerings planned at the development.The film follows different characters as they share their festive wishes and go about activities such as shopping, meeting friends, playing games and spending time with family. Through these everyday moments, the campaign presents the idea that celebrations are personal and that different ge..

Next Story
Equipment

BorgWarner secures three turbocharger contracts with global powertrain leader

BorgWarner has secured three new turbocharger contracts with a global powertrain technology company. The wins comprise one contract for its variable turbine geometry (VTG) turbocharger and two for its wastegate turbocharger. The technologies will be deployed in the customer's light-vehicle gasoline platforms in South America and Europe, with production scheduled to begin in 2027.The VTG turbochargers are designed for gasoline engines operating under demanding conditions and high-boost pressure requirements. They are engineered to support Miller-cycle engines and withstand exhaust temperatures ..

Next Story
Infrastructure Transport

International Digi Yatra Trials Begin at Seven Airports

India has begun trials of Digi Yatra for international passengers at seven airports, allowing eligible Indian passport holders to use facial recognition at selected airport checkpoints. The facility is currently limited to Indian nationals with e-passports travelling on selected international flights operated by Air India and IndiGo. The Civil Aviation Ministry announced the trials on 1 November, with testing scheduled through December 2026. A wider rollout is expected in 2027 after the ministry assesses passenger feedback gathered during the trial period, according to PTI. The system is inten..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

SPECIAL OFFER
QR Code