132 kV Ramban-Khellani power line upgraded to 220 MW capacity
POWER & RENEWABLE ENERGY

132 kV Ramban-Khellani power line upgraded to 220 MW capacity

In a significant step towards strengthening the power infrastructure in the twin Districts of Doda and Kishtwar, the Power Development Department (PDD) has achieved a historic milestone by inaugurating the first-ever double-circuit transmission line after a long period of 75 years.

The transformative project has established a critical link between the 220 kV Grid Station in Ramban and the 132 kV Grid Station at Khellani in Doda district, heralding a new era of connectivity and reliability for the regions.

The newly commissioned 132 kV double-circuit transmission line, which became operational on February 1, 2024, with a power transmission capacity of 150 MW (approximately 75 MW for each circuit), will ensure a threefold increase in the overall power transmission capacity for the hilly districts of Doda and Kishtwar.

This development comes as a timely solution to the challenges faced by the aging 132 kV single-circuit Udhampur-Dul Hasti Line (UDH Tx Line). Despite its commendable service over three decades, the line struggled to meet the escalating power demand, especially during harsh winters.

A senior PDD official mentioned, "The UDH Tx Line, with a rated transmission capacity of nearly 75 MW, had been catering to the power requirements of the twin districts since its inception. However, with the load demand surging to 200 MW and weather-induced wear and tear taking a toll, the line faced limitations, leading to curtailments and impacting the reliability of power supply."

He added that the radial configuration and the absence of an alternate transmission system exacerbated these challenges, leaving Doda and Kishtwar vulnerable to frequent blackouts.

According to him, the newly operational transmission line will not only address these issues but also ensure an alternative power source, complementing the existing UDH Tx Line.

"With a combined capacity of over 220 MW, the existing and the new double-circuit transmission lines will now create a resilient network ensuring uninterrupted power supply, even in the event of failures or breakdowns," said the official.

The construction of the 132 kV double-circuit Ramban to Khellani Transmission Line started some years back. Due to various technical delays, the project couldn?t progress, and the works remained held up.

Overcoming these bottlenecks, the Government awarded the project afresh to Power Grid Corporation of India (PGCIL), a key player in the country?s power sector.

The swift and efficient execution by PGCIL allowed the transmission line to be commissioned well ahead of schedule, providing much-needed relief to the public of Doda and Kishtwar.

The PDD official added that the feeding grid Khellani (20+50 MVA) is also being augmented to 100 MVA (50+50 MVA), the contract of which stands awarded while the other grid, Katersamna (2?20 MVA), is shortly being augmented to 70 MVA (20+50 MVA), thereby making Doda and Kishtwar Districts self-sufficient concerning power.

"These upgrades, coupled with the newly commissioned transmission line, are part of a broader strategy aimed at fortifying the power infrastructure in the region," he said.

Furthermore, the Government has also given approval for a Rs 10 bn investment in the upcoming Financial Year for the construction of three major 400 kV Grid Stations in Akhnoor, Rajouri, and Katra in the Jammu region and two 220 kV level Grid Stations at Wahipora and Sallar in the Kashmir Region.

In a significant step towards strengthening the power infrastructure in the twin Districts of Doda and Kishtwar, the Power Development Department (PDD) has achieved a historic milestone by inaugurating the first-ever double-circuit transmission line after a long period of 75 years. The transformative project has established a critical link between the 220 kV Grid Station in Ramban and the 132 kV Grid Station at Khellani in Doda district, heralding a new era of connectivity and reliability for the regions. The newly commissioned 132 kV double-circuit transmission line, which became operational on February 1, 2024, with a power transmission capacity of 150 MW (approximately 75 MW for each circuit), will ensure a threefold increase in the overall power transmission capacity for the hilly districts of Doda and Kishtwar. This development comes as a timely solution to the challenges faced by the aging 132 kV single-circuit Udhampur-Dul Hasti Line (UDH Tx Line). Despite its commendable service over three decades, the line struggled to meet the escalating power demand, especially during harsh winters. A senior PDD official mentioned, The UDH Tx Line, with a rated transmission capacity of nearly 75 MW, had been catering to the power requirements of the twin districts since its inception. However, with the load demand surging to 200 MW and weather-induced wear and tear taking a toll, the line faced limitations, leading to curtailments and impacting the reliability of power supply. He added that the radial configuration and the absence of an alternate transmission system exacerbated these challenges, leaving Doda and Kishtwar vulnerable to frequent blackouts. According to him, the newly operational transmission line will not only address these issues but also ensure an alternative power source, complementing the existing UDH Tx Line. With a combined capacity of over 220 MW, the existing and the new double-circuit transmission lines will now create a resilient network ensuring uninterrupted power supply, even in the event of failures or breakdowns, said the official. The construction of the 132 kV double-circuit Ramban to Khellani Transmission Line started some years back. Due to various technical delays, the project couldn?t progress, and the works remained held up. Overcoming these bottlenecks, the Government awarded the project afresh to Power Grid Corporation of India (PGCIL), a key player in the country?s power sector. The swift and efficient execution by PGCIL allowed the transmission line to be commissioned well ahead of schedule, providing much-needed relief to the public of Doda and Kishtwar. The PDD official added that the feeding grid Khellani (20+50 MVA) is also being augmented to 100 MVA (50+50 MVA), the contract of which stands awarded while the other grid, Katersamna (2?20 MVA), is shortly being augmented to 70 MVA (20+50 MVA), thereby making Doda and Kishtwar Districts self-sufficient concerning power. These upgrades, coupled with the newly commissioned transmission line, are part of a broader strategy aimed at fortifying the power infrastructure in the region, he said. Furthermore, the Government has also given approval for a Rs 10 bn investment in the upcoming Financial Year for the construction of three major 400 kV Grid Stations in Akhnoor, Rajouri, and Katra in the Jammu region and two 220 kV level Grid Stations at Wahipora and Sallar in the Kashmir Region.

Next Story
Real Estate

Indian REITs Offer 6-7.5 per cent Yield, Surpassing Many Global Markets

Indian Real Estate Investment Trusts (REITs) are delivering average yields of 6–7.5 per cent for unitholders, outperforming many mature markets, including the US, according to a report by Credai and Anarock.Credai, the apex body of Indian real estate developers, and property consultant Anarock released the report Indian REITs – A Gateway to Institutional Real Estate at an event in India.Currently, India has five listed REITs – Brookfield India Real Estate Trust, Embassy Office Parks REIT, Mindspace Business Parks REIT, Nexus Select Trust, and Knowledge Realty Trust. Nexus Select Trust pr..

Next Story
Infrastructure Energy

Insolation Energy Wins 226 MW Solar Projects Under PM-KUSUM

Insolation Energy on Monday announced securing multiple solar projects totalling 226.45 MW, with an investment of Rs 7.5 billion, under the PM-KUSUM scheme. The orders were awarded to its wholly-owned subsidiary, Insolation Green Energy Pvt Ltd, by Jaipur Vidyut Vitran Nigam Limited for 20 sites and Ajmer Vidyut Vitran Nigam Limited for 115 sites, the company informed the exchanges.“The combined SPV solar power plants will total 226.45 MW under PM-KUSUM Component A, with the final levelised tariff at Rs 3.04 per unit for 16 sites, Rs 2.82 per unit for 5 sites, Rs 2.75 per unit for 53 sites, ..

Next Story
Infrastructure Energy

Numaligarh Refinery Awards EPC Contract for Rooftop Solar Projects

State-owned Numaligarh Refinery Ltd. (NRL) has awarded a Letter of Award to Solarium Green Energy Ltd. for the rate contract covering the Engineering, Procurement, and Construction (EPC) of grid-connected rooftop solar PV projects at various locations. The projects fall within the categories of 51–200 kW and 201–1000 kW. Notable projects include a 140 kW rooftop solar plant at NRL Assam, a 760 kW plant at NRL Assam, and a 280 kW plant at NRL West Bengal.The supply order covers ex-manufacturing works and the dispatch price for plant and equipment for the 140 kW, 760 kW, and 280 kW rooftop s..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Talk to us?