132 kV Ramban-Khellani power line upgraded to 220 MW capacity
POWER & RENEWABLE ENERGY

132 kV Ramban-Khellani power line upgraded to 220 MW capacity

In a significant step towards strengthening the power infrastructure in the twin Districts of Doda and Kishtwar, the Power Development Department (PDD) has achieved a historic milestone by inaugurating the first-ever double-circuit transmission line after a long period of 75 years.

The transformative project has established a critical link between the 220 kV Grid Station in Ramban and the 132 kV Grid Station at Khellani in Doda district, heralding a new era of connectivity and reliability for the regions.

The newly commissioned 132 kV double-circuit transmission line, which became operational on February 1, 2024, with a power transmission capacity of 150 MW (approximately 75 MW for each circuit), will ensure a threefold increase in the overall power transmission capacity for the hilly districts of Doda and Kishtwar.

This development comes as a timely solution to the challenges faced by the aging 132 kV single-circuit Udhampur-Dul Hasti Line (UDH Tx Line). Despite its commendable service over three decades, the line struggled to meet the escalating power demand, especially during harsh winters.

A senior PDD official mentioned, "The UDH Tx Line, with a rated transmission capacity of nearly 75 MW, had been catering to the power requirements of the twin districts since its inception. However, with the load demand surging to 200 MW and weather-induced wear and tear taking a toll, the line faced limitations, leading to curtailments and impacting the reliability of power supply."

He added that the radial configuration and the absence of an alternate transmission system exacerbated these challenges, leaving Doda and Kishtwar vulnerable to frequent blackouts.

According to him, the newly operational transmission line will not only address these issues but also ensure an alternative power source, complementing the existing UDH Tx Line.

"With a combined capacity of over 220 MW, the existing and the new double-circuit transmission lines will now create a resilient network ensuring uninterrupted power supply, even in the event of failures or breakdowns," said the official.

The construction of the 132 kV double-circuit Ramban to Khellani Transmission Line started some years back. Due to various technical delays, the project couldn?t progress, and the works remained held up.

Overcoming these bottlenecks, the Government awarded the project afresh to Power Grid Corporation of India (PGCIL), a key player in the country?s power sector.

The swift and efficient execution by PGCIL allowed the transmission line to be commissioned well ahead of schedule, providing much-needed relief to the public of Doda and Kishtwar.

The PDD official added that the feeding grid Khellani (20+50 MVA) is also being augmented to 100 MVA (50+50 MVA), the contract of which stands awarded while the other grid, Katersamna (2?20 MVA), is shortly being augmented to 70 MVA (20+50 MVA), thereby making Doda and Kishtwar Districts self-sufficient concerning power.

"These upgrades, coupled with the newly commissioned transmission line, are part of a broader strategy aimed at fortifying the power infrastructure in the region," he said.

Furthermore, the Government has also given approval for a Rs 10 bn investment in the upcoming Financial Year for the construction of three major 400 kV Grid Stations in Akhnoor, Rajouri, and Katra in the Jammu region and two 220 kV level Grid Stations at Wahipora and Sallar in the Kashmir Region.

In a significant step towards strengthening the power infrastructure in the twin Districts of Doda and Kishtwar, the Power Development Department (PDD) has achieved a historic milestone by inaugurating the first-ever double-circuit transmission line after a long period of 75 years. The transformative project has established a critical link between the 220 kV Grid Station in Ramban and the 132 kV Grid Station at Khellani in Doda district, heralding a new era of connectivity and reliability for the regions. The newly commissioned 132 kV double-circuit transmission line, which became operational on February 1, 2024, with a power transmission capacity of 150 MW (approximately 75 MW for each circuit), will ensure a threefold increase in the overall power transmission capacity for the hilly districts of Doda and Kishtwar. This development comes as a timely solution to the challenges faced by the aging 132 kV single-circuit Udhampur-Dul Hasti Line (UDH Tx Line). Despite its commendable service over three decades, the line struggled to meet the escalating power demand, especially during harsh winters. A senior PDD official mentioned, The UDH Tx Line, with a rated transmission capacity of nearly 75 MW, had been catering to the power requirements of the twin districts since its inception. However, with the load demand surging to 200 MW and weather-induced wear and tear taking a toll, the line faced limitations, leading to curtailments and impacting the reliability of power supply. He added that the radial configuration and the absence of an alternate transmission system exacerbated these challenges, leaving Doda and Kishtwar vulnerable to frequent blackouts. According to him, the newly operational transmission line will not only address these issues but also ensure an alternative power source, complementing the existing UDH Tx Line. With a combined capacity of over 220 MW, the existing and the new double-circuit transmission lines will now create a resilient network ensuring uninterrupted power supply, even in the event of failures or breakdowns, said the official. The construction of the 132 kV double-circuit Ramban to Khellani Transmission Line started some years back. Due to various technical delays, the project couldn?t progress, and the works remained held up. Overcoming these bottlenecks, the Government awarded the project afresh to Power Grid Corporation of India (PGCIL), a key player in the country?s power sector. The swift and efficient execution by PGCIL allowed the transmission line to be commissioned well ahead of schedule, providing much-needed relief to the public of Doda and Kishtwar. The PDD official added that the feeding grid Khellani (20+50 MVA) is also being augmented to 100 MVA (50+50 MVA), the contract of which stands awarded while the other grid, Katersamna (2?20 MVA), is shortly being augmented to 70 MVA (20+50 MVA), thereby making Doda and Kishtwar Districts self-sufficient concerning power. These upgrades, coupled with the newly commissioned transmission line, are part of a broader strategy aimed at fortifying the power infrastructure in the region, he said. Furthermore, the Government has also given approval for a Rs 10 bn investment in the upcoming Financial Year for the construction of three major 400 kV Grid Stations in Akhnoor, Rajouri, and Katra in the Jammu region and two 220 kV level Grid Stations at Wahipora and Sallar in the Kashmir Region.

Next Story
Infrastructure Transport

Shivraj Chouhan Launches PMGSY IV and Announces Package for Madhya Pradesh

Union Minister Shivraj Singh Chouhan launched the Pradhan Mantri Gram Sadak Yojana (PMGSY) IV at Bhairunda in Sehore district during the 25 year celebrations and announced a development package for Madhya Pradesh. The programme was organised by the Union Ministry of Rural Development and attended by Chief Minister Dr Mohan Yadav, ministers of state, state ministers, legislators and senior officials from the centre and the state. The minister said the central government under the Prime Minister is committed to strengthening rural livelihoods through improved connectivity, housing and women's in..

Next Story
Infrastructure Urban

DMR Engineering Reports FY 25-26 Financial Results

DMR Engineering reported its half year results for the financial year ended 31 March 2026 and published full year figures on a standalone basis. Standalone revenue from operations decreased by 2.01 per cent year-over-year to Rs 102.58 million (mn), while profit after tax declined by 43.94 per cent to nine point five six mn, leaving a profit after tax margin of nine point zero five per cent. Earnings per share stood at Rs zero point nine two, a fall of 44.71 per cent year-over-year. The company attributed part of the decline to one-off provisioning for bad debts and additional financing charges..

Next Story
Infrastructure Urban

Atlanta Electricals Posts Strong FY26 Growth And Debt Free Finish

Atlanta Electricals reported audited consolidated results for the quarter and year ended 31 March 2026. The company recorded significant year-on-year revenue growth driven by capacity ramp-up at new facilities and higher utilisation at legacy plants. The announcement summarised operating improvements and strategic milestones achieved during the year. For Q4 the company reported revenue of Rs 7.48 bn and for FY26 revenue of Rs 18.52 bn, representing robust growth versus the prior year. EBITDA in Q4 was Rs. 1.49 bn and Rs. 3.44 bn for the full year, with margins expanding to 20 per cent in the q..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

-->