132 kV Ramban-Khellani power line upgraded to 220 MW capacity
POWER & RENEWABLE ENERGY

132 kV Ramban-Khellani power line upgraded to 220 MW capacity

In a significant step towards strengthening the power infrastructure in the twin Districts of Doda and Kishtwar, the Power Development Department (PDD) has achieved a historic milestone by inaugurating the first-ever double-circuit transmission line after a long period of 75 years.

The transformative project has established a critical link between the 220 kV Grid Station in Ramban and the 132 kV Grid Station at Khellani in Doda district, heralding a new era of connectivity and reliability for the regions.

The newly commissioned 132 kV double-circuit transmission line, which became operational on February 1, 2024, with a power transmission capacity of 150 MW (approximately 75 MW for each circuit), will ensure a threefold increase in the overall power transmission capacity for the hilly districts of Doda and Kishtwar.

This development comes as a timely solution to the challenges faced by the aging 132 kV single-circuit Udhampur-Dul Hasti Line (UDH Tx Line). Despite its commendable service over three decades, the line struggled to meet the escalating power demand, especially during harsh winters.

A senior PDD official mentioned, "The UDH Tx Line, with a rated transmission capacity of nearly 75 MW, had been catering to the power requirements of the twin districts since its inception. However, with the load demand surging to 200 MW and weather-induced wear and tear taking a toll, the line faced limitations, leading to curtailments and impacting the reliability of power supply."

He added that the radial configuration and the absence of an alternate transmission system exacerbated these challenges, leaving Doda and Kishtwar vulnerable to frequent blackouts.

According to him, the newly operational transmission line will not only address these issues but also ensure an alternative power source, complementing the existing UDH Tx Line.

"With a combined capacity of over 220 MW, the existing and the new double-circuit transmission lines will now create a resilient network ensuring uninterrupted power supply, even in the event of failures or breakdowns," said the official.

The construction of the 132 kV double-circuit Ramban to Khellani Transmission Line started some years back. Due to various technical delays, the project couldn?t progress, and the works remained held up.

Overcoming these bottlenecks, the Government awarded the project afresh to Power Grid Corporation of India (PGCIL), a key player in the country?s power sector.

The swift and efficient execution by PGCIL allowed the transmission line to be commissioned well ahead of schedule, providing much-needed relief to the public of Doda and Kishtwar.

The PDD official added that the feeding grid Khellani (20+50 MVA) is also being augmented to 100 MVA (50+50 MVA), the contract of which stands awarded while the other grid, Katersamna (2?20 MVA), is shortly being augmented to 70 MVA (20+50 MVA), thereby making Doda and Kishtwar Districts self-sufficient concerning power.

"These upgrades, coupled with the newly commissioned transmission line, are part of a broader strategy aimed at fortifying the power infrastructure in the region," he said.

Furthermore, the Government has also given approval for a Rs 10 bn investment in the upcoming Financial Year for the construction of three major 400 kV Grid Stations in Akhnoor, Rajouri, and Katra in the Jammu region and two 220 kV level Grid Stations at Wahipora and Sallar in the Kashmir Region.

In a significant step towards strengthening the power infrastructure in the twin Districts of Doda and Kishtwar, the Power Development Department (PDD) has achieved a historic milestone by inaugurating the first-ever double-circuit transmission line after a long period of 75 years. The transformative project has established a critical link between the 220 kV Grid Station in Ramban and the 132 kV Grid Station at Khellani in Doda district, heralding a new era of connectivity and reliability for the regions. The newly commissioned 132 kV double-circuit transmission line, which became operational on February 1, 2024, with a power transmission capacity of 150 MW (approximately 75 MW for each circuit), will ensure a threefold increase in the overall power transmission capacity for the hilly districts of Doda and Kishtwar. This development comes as a timely solution to the challenges faced by the aging 132 kV single-circuit Udhampur-Dul Hasti Line (UDH Tx Line). Despite its commendable service over three decades, the line struggled to meet the escalating power demand, especially during harsh winters. A senior PDD official mentioned, The UDH Tx Line, with a rated transmission capacity of nearly 75 MW, had been catering to the power requirements of the twin districts since its inception. However, with the load demand surging to 200 MW and weather-induced wear and tear taking a toll, the line faced limitations, leading to curtailments and impacting the reliability of power supply. He added that the radial configuration and the absence of an alternate transmission system exacerbated these challenges, leaving Doda and Kishtwar vulnerable to frequent blackouts. According to him, the newly operational transmission line will not only address these issues but also ensure an alternative power source, complementing the existing UDH Tx Line. With a combined capacity of over 220 MW, the existing and the new double-circuit transmission lines will now create a resilient network ensuring uninterrupted power supply, even in the event of failures or breakdowns, said the official. The construction of the 132 kV double-circuit Ramban to Khellani Transmission Line started some years back. Due to various technical delays, the project couldn?t progress, and the works remained held up. Overcoming these bottlenecks, the Government awarded the project afresh to Power Grid Corporation of India (PGCIL), a key player in the country?s power sector. The swift and efficient execution by PGCIL allowed the transmission line to be commissioned well ahead of schedule, providing much-needed relief to the public of Doda and Kishtwar. The PDD official added that the feeding grid Khellani (20+50 MVA) is also being augmented to 100 MVA (50+50 MVA), the contract of which stands awarded while the other grid, Katersamna (2?20 MVA), is shortly being augmented to 70 MVA (20+50 MVA), thereby making Doda and Kishtwar Districts self-sufficient concerning power. These upgrades, coupled with the newly commissioned transmission line, are part of a broader strategy aimed at fortifying the power infrastructure in the region, he said. Furthermore, the Government has also given approval for a Rs 10 bn investment in the upcoming Financial Year for the construction of three major 400 kV Grid Stations in Akhnoor, Rajouri, and Katra in the Jammu region and two 220 kV level Grid Stations at Wahipora and Sallar in the Kashmir Region.

Next Story
Infrastructure Urban

India To Invest $37 Billion To Boost Petrochemical Capacity

India is set to become a major global player in the petrochemicals industry, driven by a planned capital expenditure of $37 billion (Rs 3.1 trillion) aimed at reducing import dependency and enhancing self-sufficiency, according to S&P Global Ratings.In its latest report titled “First China, Now India: Self-Sufficiency Goals Will Add To Petrochemicals Supply”, S&P said India’s large-scale capacity expansion—mirroring China’s earlier push—will likely intensify oversupply pressures in Asia’s petrochemical markets.Currently the world’s third-largest petrochemical consumer a..

Next Story
Infrastructure Transport

Indian Railways Expands Global Exports Of Rail Equipment

Indian Railways has announced that it is rapidly emerging as a global exporter of railway equipment, including bogies, coaches, locomotives, and propulsion systems, under the government’s ‘Make in India, Make for the World’ initiative.According to an official statement, India’s railway products are now reaching over 16 international markets, reflecting the country’s growing capacity to design, develop, and deliver world-class rail solutions.Metro coaches have been exported to Australia and Canada; bogies to the United Kingdom, Saudi Arabia, France, and Australia; propulsion systems t..

Next Story
Infrastructure Transport

RailTel Awards Rs 163 Million Contract To RTNS Technology

RailTel Corporation of India Limited (RailTel), a Mini Ratna Public Sector Undertaking, has awarded a domestic work order worth Rs 163 million to RTNS Technology Private Limited.The contract, issued on 30 September 2025, involves the supply and installation of equipment and related services for one of RailTel’s key customers. The project underscores RailTel’s commitment to advancing technology and communication infrastructure through collaboration with domestic system integrators.RTNS Technology Private Limited, an ISO-certified system integrator, provides comprehensive solutions for perim..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Talk to us?