Adani’s Godda Power Plant to Join Indian Grid by December 2025
POWER & RENEWABLE ENERGY

Adani’s Godda Power Plant to Join Indian Grid by December 2025

Adani Power Limited’s ultra-supercritical 1,600 MW Godda Thermal Power Plant in Jharkhand—currently exporting all its electricity to Bangladesh—is expected to be connected to India’s national power grid by December 2025, enabling participation in the domestic electricity market under specific conditions.

“We are expecting that the Godda power plant will be connected by December 2025. If there is persistent non-scheduling from Bangladesh due to lack of demand, or if there is a payment default under the Power Purchase Agreement (PPA), we have been permitted to sell power to the Indian grid,” said S. B. Khyalia, CEO of Adani Power Limited, during an earnings call on Thursday.

Commissioned as India’s first private thermal plant dedicated to cross-border power export, the first 800 MW unit of the Godda plant began operations on 6 April 2023, followed by the second 800 MW unit on 26 June 2023. Under a 25-year PPA with Bangladesh, the project initially faced payment arrears exceeding USD 500 million from the Bangladeshi power utility. However, following an amendment to Indian regulations in August 2024, Adani Power was allowed to supply power from Godda to the Indian grid under certain conditions.

Adani Power stated that most of the dues have now been cleared by Bangladesh, with only half a month’s payment outstanding. The company also highlighted the strong operational performance of the plant, reporting a Plant Load Factor (PLF) of 72 per cent during the second quarter of FY2025, significantly higher than the national average of 60–65 per cent for thermal power stations.

“The PLF at Godda is much better than the Indian grid average,” Khyalia said, noting that the plant’s performance demonstrates its efficiency and reliability.

Adani Power is currently involved in bidding processes for 22,000 MW of thermal capacity across India. The company has emerged as the lowest bidder (L1) for a 3,200 MW project in Assam, which has already received regulatory approval, and expects formal communication of the award soon.

Khyalia added that Adani Power has also submitted bids for new thermal projects in Rajasthan (3,200 MW), Uttarakhand (1,320 MW), Maharashtra (1,600 MW), Uttar Pradesh (4,000 MW), West Bengal (2,260 MW), Karnataka (1,600 MW), and Gujarat (4,000 MW).

The company currently has four brownfield thermal projects under construction, with a combined capacity of 6,020 MW, for which major equipment orders have been placed with L&T and BHEL. These projects are scheduled for completion between FY2026 and FY2029.

“We have fully de-risked our project pipeline with 100 per cent advance ordering for boilers, turbines, and generators,” Khyalia said. “All projects are brownfield, and 100 per cent of the required land is already available.”

The integration of the Godda plant into India’s national grid represents a strategic milestone for Adani Power, enhancing its operational flexibility and reinforcing its leadership in India’s thermal power sector.

Adani Power Limited’s ultra-supercritical 1,600 MW Godda Thermal Power Plant in Jharkhand—currently exporting all its electricity to Bangladesh—is expected to be connected to India’s national power grid by December 2025, enabling participation in the domestic electricity market under specific conditions. “We are expecting that the Godda power plant will be connected by December 2025. If there is persistent non-scheduling from Bangladesh due to lack of demand, or if there is a payment default under the Power Purchase Agreement (PPA), we have been permitted to sell power to the Indian grid,” said S. B. Khyalia, CEO of Adani Power Limited, during an earnings call on Thursday. Commissioned as India’s first private thermal plant dedicated to cross-border power export, the first 800 MW unit of the Godda plant began operations on 6 April 2023, followed by the second 800 MW unit on 26 June 2023. Under a 25-year PPA with Bangladesh, the project initially faced payment arrears exceeding USD 500 million from the Bangladeshi power utility. However, following an amendment to Indian regulations in August 2024, Adani Power was allowed to supply power from Godda to the Indian grid under certain conditions. Adani Power stated that most of the dues have now been cleared by Bangladesh, with only half a month’s payment outstanding. The company also highlighted the strong operational performance of the plant, reporting a Plant Load Factor (PLF) of 72 per cent during the second quarter of FY2025, significantly higher than the national average of 60–65 per cent for thermal power stations. “The PLF at Godda is much better than the Indian grid average,” Khyalia said, noting that the plant’s performance demonstrates its efficiency and reliability. Adani Power is currently involved in bidding processes for 22,000 MW of thermal capacity across India. The company has emerged as the lowest bidder (L1) for a 3,200 MW project in Assam, which has already received regulatory approval, and expects formal communication of the award soon. Khyalia added that Adani Power has also submitted bids for new thermal projects in Rajasthan (3,200 MW), Uttarakhand (1,320 MW), Maharashtra (1,600 MW), Uttar Pradesh (4,000 MW), West Bengal (2,260 MW), Karnataka (1,600 MW), and Gujarat (4,000 MW). The company currently has four brownfield thermal projects under construction, with a combined capacity of 6,020 MW, for which major equipment orders have been placed with L&T and BHEL. These projects are scheduled for completion between FY2026 and FY2029. “We have fully de-risked our project pipeline with 100 per cent advance ordering for boilers, turbines, and generators,” Khyalia said. “All projects are brownfield, and 100 per cent of the required land is already available.” The integration of the Godda plant into India’s national grid represents a strategic milestone for Adani Power, enhancing its operational flexibility and reinforcing its leadership in India’s thermal power sector.

Next Story
Infrastructure Urban

Jyoti Structures FY26 profit rises 56.5%

Jyoti Structures (JSL) recently reported strong financial results for the quarter and year ended 31 March 2026, driven by disciplined execution, cost management and steady progress across its order book.For Q4 FY2025-26, total income rose 44.2 per cent to Rs 2.41 billion from Rs 1.67 billion in Q4 FY2024-25. EBITDA increased 58.6 per cent to Rs 237 million, while EBITDA margin improved by 89 basis points to 9.84 per cent. Profit before tax grew 53.3 per cent to Rs 188.5 million, and net profit rose 51.9 per cent to Rs 181.4 million.For FY2025-26, total income grew 53.1 per cent to Rs 7.72 bill..

Next Story
Infrastructure Energy

Cat BEPU to Power Doppstadt Separator at IFAT 2026

Caterpillar’s Cat Battery Electric Power Unit (BEPU) has been selected by Doppstadt to power its SWS 6 Spiral Shaft Separator, which will be showcased for the first time at IFAT 2026 in Munich, Germany, from 4–7 May.The compact plug-and-play BEPU is designed to replace a diesel engine within the same space, using the same mounting locations and relative machine position. It integrates the battery, motor, inverter, onboard charging, cooling and controls, enabling OEMs to electrify existing chassis platforms without extensive redesign.Caterpillar and Cat dealer Zeppelin Power Systems have be..

Next Story
Infrastructure Urban

VECV sales rise 6.9% in April 2026

VE Commercial Vehicles, a joint venture between Volvo Group and Eicher Motors, recorded sales of 7,318 units in April 2026, compared to 6,846 units in April 2025, registering 6.9 per cent growth. The total included 7,159 units under the Eicher brand and 159 units under the Volvo brand.Eicher branded trucks and buses reported sales of 7,159 units during the month, up 6.6 per cent from 6,717 units in April 2025. In the domestic commercial vehicle market, Eicher sales rose 8.6 per cent to 6,797 units from 6,257 units a year earlier.Exports declined 21.3 per cent, with VECV recording 362 units in ..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement