+
Adani’s Godda Power Plant to Join Indian Grid by December 2025
POWER & RENEWABLE ENERGY

Adani’s Godda Power Plant to Join Indian Grid by December 2025

Adani Power Limited’s ultra-supercritical 1,600 MW Godda Thermal Power Plant in Jharkhand—currently exporting all its electricity to Bangladesh—is expected to be connected to India’s national power grid by December 2025, enabling participation in the domestic electricity market under specific conditions.

“We are expecting that the Godda power plant will be connected by December 2025. If there is persistent non-scheduling from Bangladesh due to lack of demand, or if there is a payment default under the Power Purchase Agreement (PPA), we have been permitted to sell power to the Indian grid,” said S. B. Khyalia, CEO of Adani Power Limited, during an earnings call on Thursday.

Commissioned as India’s first private thermal plant dedicated to cross-border power export, the first 800 MW unit of the Godda plant began operations on 6 April 2023, followed by the second 800 MW unit on 26 June 2023. Under a 25-year PPA with Bangladesh, the project initially faced payment arrears exceeding USD 500 million from the Bangladeshi power utility. However, following an amendment to Indian regulations in August 2024, Adani Power was allowed to supply power from Godda to the Indian grid under certain conditions.

Adani Power stated that most of the dues have now been cleared by Bangladesh, with only half a month’s payment outstanding. The company also highlighted the strong operational performance of the plant, reporting a Plant Load Factor (PLF) of 72 per cent during the second quarter of FY2025, significantly higher than the national average of 60–65 per cent for thermal power stations.

“The PLF at Godda is much better than the Indian grid average,” Khyalia said, noting that the plant’s performance demonstrates its efficiency and reliability.

Adani Power is currently involved in bidding processes for 22,000 MW of thermal capacity across India. The company has emerged as the lowest bidder (L1) for a 3,200 MW project in Assam, which has already received regulatory approval, and expects formal communication of the award soon.

Khyalia added that Adani Power has also submitted bids for new thermal projects in Rajasthan (3,200 MW), Uttarakhand (1,320 MW), Maharashtra (1,600 MW), Uttar Pradesh (4,000 MW), West Bengal (2,260 MW), Karnataka (1,600 MW), and Gujarat (4,000 MW).

The company currently has four brownfield thermal projects under construction, with a combined capacity of 6,020 MW, for which major equipment orders have been placed with L&T and BHEL. These projects are scheduled for completion between FY2026 and FY2029.

“We have fully de-risked our project pipeline with 100 per cent advance ordering for boilers, turbines, and generators,” Khyalia said. “All projects are brownfield, and 100 per cent of the required land is already available.”

The integration of the Godda plant into India’s national grid represents a strategic milestone for Adani Power, enhancing its operational flexibility and reinforcing its leadership in India’s thermal power sector.

Adani Power Limited’s ultra-supercritical 1,600 MW Godda Thermal Power Plant in Jharkhand—currently exporting all its electricity to Bangladesh—is expected to be connected to India’s national power grid by December 2025, enabling participation in the domestic electricity market under specific conditions. “We are expecting that the Godda power plant will be connected by December 2025. If there is persistent non-scheduling from Bangladesh due to lack of demand, or if there is a payment default under the Power Purchase Agreement (PPA), we have been permitted to sell power to the Indian grid,” said S. B. Khyalia, CEO of Adani Power Limited, during an earnings call on Thursday. Commissioned as India’s first private thermal plant dedicated to cross-border power export, the first 800 MW unit of the Godda plant began operations on 6 April 2023, followed by the second 800 MW unit on 26 June 2023. Under a 25-year PPA with Bangladesh, the project initially faced payment arrears exceeding USD 500 million from the Bangladeshi power utility. However, following an amendment to Indian regulations in August 2024, Adani Power was allowed to supply power from Godda to the Indian grid under certain conditions. Adani Power stated that most of the dues have now been cleared by Bangladesh, with only half a month’s payment outstanding. The company also highlighted the strong operational performance of the plant, reporting a Plant Load Factor (PLF) of 72 per cent during the second quarter of FY2025, significantly higher than the national average of 60–65 per cent for thermal power stations. “The PLF at Godda is much better than the Indian grid average,” Khyalia said, noting that the plant’s performance demonstrates its efficiency and reliability. Adani Power is currently involved in bidding processes for 22,000 MW of thermal capacity across India. The company has emerged as the lowest bidder (L1) for a 3,200 MW project in Assam, which has already received regulatory approval, and expects formal communication of the award soon. Khyalia added that Adani Power has also submitted bids for new thermal projects in Rajasthan (3,200 MW), Uttarakhand (1,320 MW), Maharashtra (1,600 MW), Uttar Pradesh (4,000 MW), West Bengal (2,260 MW), Karnataka (1,600 MW), and Gujarat (4,000 MW). The company currently has four brownfield thermal projects under construction, with a combined capacity of 6,020 MW, for which major equipment orders have been placed with L&T and BHEL. These projects are scheduled for completion between FY2026 and FY2029. “We have fully de-risked our project pipeline with 100 per cent advance ordering for boilers, turbines, and generators,” Khyalia said. “All projects are brownfield, and 100 per cent of the required land is already available.” The integration of the Godda plant into India’s national grid represents a strategic milestone for Adani Power, enhancing its operational flexibility and reinforcing its leadership in India’s thermal power sector.

Next Story
Infrastructure Transport

MMRDA Installs 325-Tonne Steel Spans on Mumbai Metro Line 4

The Mumbai Metropolitan Region Development Authority (MMRDA) has achieved a key construction milestone on Metro Line 4 with the successful installation of three large steel spans at Bhandup West during overnight operations.The spans, together weighing 325 metric tonnes, were launched using eight heavy-duty cranes and 12 multi-axle vehicles. The operation required precise engineering and meticulous planning to minimise disruption in the densely populated suburban area.Due to effective inter-agency coordination, the work—originally scheduled across four nights—was completed within just two n..

Next Story
Infrastructure Transport

CMRL Targets March 2027 Opening for Vadapalani–Panagal Park

Chennai Metro Rail Limited (CMRL) is progressing as scheduled to open the Vadapalani–Panagal Park section of Phase II’s Corridor 4 by March 2027. The 3.5 km underground stretch is part of the 26.1 km Corridor 4 connecting Lighthouse with Poonamallee Bypass.Construction activities are advancing steadily, with tunnelling works between Vadapalani and Panagal Park already completed. Track-laying operations are expected to commence shortly. At Panagal Park station, structural works have reached the concourse and platform levels, while excavation continues at the lowest level.CMRL is also consid..

Next Story
Infrastructure Transport

Maha-Metro Invites Pune Metro Civil Maintenance Bids

Maharashtra Metro Rail Corporation Limited (Maha-Metro) has invited bids for the annual civil maintenance contract of the Pune Metro Rail Project. The tender, bearing ID and number P1-O&M-20/2025, is scheduled to close on 23 February 2026, with a pre-bid meeting slated for 10 February 2026. The earnest money deposit (EMD) for the contract is Rs 3,50,500, and the duration of the contract is one year.The scope of work includes annual civil maintenance of 28 elevated and underground stations, 28.079 km of elevated viaduct including steel bridges, 12.15 km of tunnels, and two depots under the ..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Open In App