Adani’s Godda Power Plant to Join Indian Grid by December 2025
POWER & RENEWABLE ENERGY

Adani’s Godda Power Plant to Join Indian Grid by December 2025

Adani Power Limited’s ultra-supercritical 1,600 MW Godda Thermal Power Plant in Jharkhand—currently exporting all its electricity to Bangladesh—is expected to be connected to India’s national power grid by December 2025, enabling participation in the domestic electricity market under specific conditions.

“We are expecting that the Godda power plant will be connected by December 2025. If there is persistent non-scheduling from Bangladesh due to lack of demand, or if there is a payment default under the Power Purchase Agreement (PPA), we have been permitted to sell power to the Indian grid,” said S. B. Khyalia, CEO of Adani Power Limited, during an earnings call on Thursday.

Commissioned as India’s first private thermal plant dedicated to cross-border power export, the first 800 MW unit of the Godda plant began operations on 6 April 2023, followed by the second 800 MW unit on 26 June 2023. Under a 25-year PPA with Bangladesh, the project initially faced payment arrears exceeding USD 500 million from the Bangladeshi power utility. However, following an amendment to Indian regulations in August 2024, Adani Power was allowed to supply power from Godda to the Indian grid under certain conditions.

Adani Power stated that most of the dues have now been cleared by Bangladesh, with only half a month’s payment outstanding. The company also highlighted the strong operational performance of the plant, reporting a Plant Load Factor (PLF) of 72 per cent during the second quarter of FY2025, significantly higher than the national average of 60–65 per cent for thermal power stations.

“The PLF at Godda is much better than the Indian grid average,” Khyalia said, noting that the plant’s performance demonstrates its efficiency and reliability.

Adani Power is currently involved in bidding processes for 22,000 MW of thermal capacity across India. The company has emerged as the lowest bidder (L1) for a 3,200 MW project in Assam, which has already received regulatory approval, and expects formal communication of the award soon.

Khyalia added that Adani Power has also submitted bids for new thermal projects in Rajasthan (3,200 MW), Uttarakhand (1,320 MW), Maharashtra (1,600 MW), Uttar Pradesh (4,000 MW), West Bengal (2,260 MW), Karnataka (1,600 MW), and Gujarat (4,000 MW).

The company currently has four brownfield thermal projects under construction, with a combined capacity of 6,020 MW, for which major equipment orders have been placed with L&T and BHEL. These projects are scheduled for completion between FY2026 and FY2029.

“We have fully de-risked our project pipeline with 100 per cent advance ordering for boilers, turbines, and generators,” Khyalia said. “All projects are brownfield, and 100 per cent of the required land is already available.”

The integration of the Godda plant into India’s national grid represents a strategic milestone for Adani Power, enhancing its operational flexibility and reinforcing its leadership in India’s thermal power sector.

Adani Power Limited’s ultra-supercritical 1,600 MW Godda Thermal Power Plant in Jharkhand—currently exporting all its electricity to Bangladesh—is expected to be connected to India’s national power grid by December 2025, enabling participation in the domestic electricity market under specific conditions. “We are expecting that the Godda power plant will be connected by December 2025. If there is persistent non-scheduling from Bangladesh due to lack of demand, or if there is a payment default under the Power Purchase Agreement (PPA), we have been permitted to sell power to the Indian grid,” said S. B. Khyalia, CEO of Adani Power Limited, during an earnings call on Thursday. Commissioned as India’s first private thermal plant dedicated to cross-border power export, the first 800 MW unit of the Godda plant began operations on 6 April 2023, followed by the second 800 MW unit on 26 June 2023. Under a 25-year PPA with Bangladesh, the project initially faced payment arrears exceeding USD 500 million from the Bangladeshi power utility. However, following an amendment to Indian regulations in August 2024, Adani Power was allowed to supply power from Godda to the Indian grid under certain conditions. Adani Power stated that most of the dues have now been cleared by Bangladesh, with only half a month’s payment outstanding. The company also highlighted the strong operational performance of the plant, reporting a Plant Load Factor (PLF) of 72 per cent during the second quarter of FY2025, significantly higher than the national average of 60–65 per cent for thermal power stations. “The PLF at Godda is much better than the Indian grid average,” Khyalia said, noting that the plant’s performance demonstrates its efficiency and reliability. Adani Power is currently involved in bidding processes for 22,000 MW of thermal capacity across India. The company has emerged as the lowest bidder (L1) for a 3,200 MW project in Assam, which has already received regulatory approval, and expects formal communication of the award soon. Khyalia added that Adani Power has also submitted bids for new thermal projects in Rajasthan (3,200 MW), Uttarakhand (1,320 MW), Maharashtra (1,600 MW), Uttar Pradesh (4,000 MW), West Bengal (2,260 MW), Karnataka (1,600 MW), and Gujarat (4,000 MW). The company currently has four brownfield thermal projects under construction, with a combined capacity of 6,020 MW, for which major equipment orders have been placed with L&T and BHEL. These projects are scheduled for completion between FY2026 and FY2029. “We have fully de-risked our project pipeline with 100 per cent advance ordering for boilers, turbines, and generators,” Khyalia said. “All projects are brownfield, and 100 per cent of the required land is already available.” The integration of the Godda plant into India’s national grid represents a strategic milestone for Adani Power, enhancing its operational flexibility and reinforcing its leadership in India’s thermal power sector.

Next Story
Infrastructure Urban

Vice-President Backs Global Unity at IN-STEP 2025

Vice-President of India, Shri C. P. Radhakrishnan, addressed delegates at the 3rd edition of the International Strategic Engagement Programme (IN-STEP) held at the Vice-President’s Enclave in New Delhi. IN-STEP serves as a key dialogue platform for senior national security officers from India and friendly foreign nations. The current edition hosts 44 delegates, including 32 international participants representing 24 Global South countries. Commending the joint efforts of the National Defence College, National Security Council Secretariat, Ministry of External Affairs, and Ministry of Defen..

Next Story
Infrastructure Urban

India to Host Global Maritime Events in Visakhapatnam

India will host three major international maritime events in February 2026 at Visakhapatnam — the International Fleet Review (IFR) 2026, Exercise MILAN 2026, and the Indian Ocean Naval Symposium (IONS) Conclave of Chiefs. Scheduled from 15 to 25 February 2026, this marks the first time India will conduct all three significant maritime gatherings simultaneously. The events embody Prime Minister Shri Narendra Modi’s MAHASAGAR vision — Mutual and Holistic Advancement for Security and Growth Across Regions — announced in 2025. The MAHASAGAR framework extends India’s SAGAR (Security and ..

Next Story
Infrastructure Urban

Heavy Industries Ministry Frees 4.4 Million Sq Ft Under SCDPM 5.0

Inspired by the Prime Minister’s vision to institutionalise Swachhata and clear long-pending matters, the Ministry of Heavy Industries (MHI), along with its Central Public Sector Enterprises (CPSEs) and Autonomous Bodies (ABs), actively participated in the fifth consecutive year of the Special Campaign for Disposal of Pending Matters (SCDPM) 5.0, held from 2 to 31 October 2025. Throughout the campaign, MHI worked closely with the Department of Administrative Reforms and Public Grievances, reporting daily progress on a dedicated monitoring portal. Shri Bhupathi Raju Srinivasa Varma, Minister..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Talk to us?