Grid India proposes new rules to improve temporary grid access
POWER & RENEWABLE ENERGY

Grid India proposes new rules to improve temporary grid access

Grid India has submitted proposals to amend the Central Electricity Regulatory Commission’s (CERC) draft procedure for granting Temporary General Network Access (T-GNA) to the interstate transmission system. The move aims to allow power projects to schedule up to their full T-GNA capacity, ensuring efficient grid utilisation, fair access, and stable power distribution across regions.

Under the proposal, entities registered with the National Open Access Registry (NOAR) for short-term access approvals would also need to register with their respective Regional Load Dispatch Centres (RLDCs) for T-GNA approvals. This dual registration is expected to improve coordination and streamline approvals for temporary network access.

Bi-monthly clearance for deemed T-GNA

For generating stations whose General Network Access (GNA) is yet to become effective, RLDCs will identify projects seeking deemed T-GNA and issue standing clearances every two months. This measure will help projects operate within their sanctioned capacity while awaiting full GNA activation, preventing underutilisation of transmission infrastructure.

T-GNA clearance will be granted based on the available margin in the transmission network. This ensures grid stability and prevents over-scheduling, keeping total power flows within system limits while allowing optimal capacity use.

Equal treatment for renewable projects

Renewable energy projects linked to a pooling station via deemed T-GNA will be treated on par with those holding or awaiting GNA. This ensures equitable access for clean energy developers and supports greater integration of renewables into the national grid.

Under the proposed system, applications for deemed T-GNA between the 1st and 15th of a month must be submitted within 24 hours of the 25th of the previous month. Permissions will be allocated pro-rata based on available transmission capacity, ensuring fair and transparent scheduling.

Applications submitted after the 25th will be considered on a first-come, first-served basis, maintaining openness and consistency in granting approvals.

Flexibility for hybrid power projects

Hybrid power generators — with or without energy storage — may receive standing clearance up to their installed capacity, provided scheduling remains within the approved connectivity quantum. This helps maintain safe and reliable operation of the transmission system.

Entities granted T-GNA for renewable energy projects (T-GNARE) can convert them into regular T-GNA by applying to the nodal RLDC. Power delivery can start four months after application, giving time for system integration and network coordination.

These proposed amendments are expected to enhance grid efficiency, promote renewable integration, and ensure fairness in allocating transmission capacity across India’s growing power sector.

Grid India has submitted proposals to amend the Central Electricity Regulatory Commission’s (CERC) draft procedure for granting Temporary General Network Access (T-GNA) to the interstate transmission system. The move aims to allow power projects to schedule up to their full T-GNA capacity, ensuring efficient grid utilisation, fair access, and stable power distribution across regions. Under the proposal, entities registered with the National Open Access Registry (NOAR) for short-term access approvals would also need to register with their respective Regional Load Dispatch Centres (RLDCs) for T-GNA approvals. This dual registration is expected to improve coordination and streamline approvals for temporary network access. Bi-monthly clearance for deemed T-GNA For generating stations whose General Network Access (GNA) is yet to become effective, RLDCs will identify projects seeking deemed T-GNA and issue standing clearances every two months. This measure will help projects operate within their sanctioned capacity while awaiting full GNA activation, preventing underutilisation of transmission infrastructure. T-GNA clearance will be granted based on the available margin in the transmission network. This ensures grid stability and prevents over-scheduling, keeping total power flows within system limits while allowing optimal capacity use. Equal treatment for renewable projects Renewable energy projects linked to a pooling station via deemed T-GNA will be treated on par with those holding or awaiting GNA. This ensures equitable access for clean energy developers and supports greater integration of renewables into the national grid. Under the proposed system, applications for deemed T-GNA between the 1st and 15th of a month must be submitted within 24 hours of the 25th of the previous month. Permissions will be allocated pro-rata based on available transmission capacity, ensuring fair and transparent scheduling. Applications submitted after the 25th will be considered on a first-come, first-served basis, maintaining openness and consistency in granting approvals. Flexibility for hybrid power projects Hybrid power generators — with or without energy storage — may receive standing clearance up to their installed capacity, provided scheduling remains within the approved connectivity quantum. This helps maintain safe and reliable operation of the transmission system. Entities granted T-GNA for renewable energy projects (T-GNARE) can convert them into regular T-GNA by applying to the nodal RLDC. Power delivery can start four months after application, giving time for system integration and network coordination. These proposed amendments are expected to enhance grid efficiency, promote renewable integration, and ensure fairness in allocating transmission capacity across India’s growing power sector.

Next Story
Infrastructure Transport

Lucknow Metro East-West Corridor Consultancy Contract Awarded

The Uttar Pradesh Metro Rail Corporation has awarded the first construction-related consultancy contract for the Lucknow Metro East West Corridor to a joint venture of AYESA Ingenieria Arquitectura SAU and AYESA India Pvt Ltd. The firm was declared the lowest bidder for the Detailed Design Consultant contract for Lucknow Metro Line-2 under Phase 1B and the contract was recommended following the financial bid. The contract is valued at Rs 159.0 million (mn), covering design services for the corridor. Lucknow Metro Line-2 envisages the construction of an 11.165 kilometre corridor connecting Cha..

Next Story
Infrastructure Urban

Div Com Kashmir Urges Fast Tracking Of Jhelum Water Transport Project

The Divisional Commissioner of Kashmir has called for the fast-tracking of the Jhelum water transport project, urging district administrations and relevant agencies to accelerate planning and clearances. In a meeting convened at the divisional headquarters, the commissioner instructed officials from irrigation, public health engineering and municipal departments to prioritise the project and coordinate survey and design work. The directive emphasised removal of administrative bottlenecks and close monitoring to ensure timely mobilisation of resources and contractors. Officials were told to in..

Next Story
Infrastructure Urban

Interarch Reports Strong Q3 And Nine Month Results

Interarch Building Solutions Limited reported unaudited results for the third quarter and nine months ended 31 December 2025, recording strong revenue growth driven by execution and a robust order book. Net revenue for the third quarter rose by 43.7 per cent to Rs 5.225 billion (bn), compared with Rs 3.636 bn a year earlier, reflecting heightened demand in pre-engineered building projects. The company’s total order book as at 31 January 2026 stood at Rs 16.85 bn, supporting near-term visibility. EBITDA excluding other income for the quarter increased by 43.2 per cent to Rs 503 million (mn),..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Open In App