Grid India proposes new rules to improve temporary grid access
POWER & RENEWABLE ENERGY

Grid India proposes new rules to improve temporary grid access

Grid India has submitted proposals to amend the Central Electricity Regulatory Commission’s (CERC) draft procedure for granting Temporary General Network Access (T-GNA) to the interstate transmission system. The move aims to allow power projects to schedule up to their full T-GNA capacity, ensuring efficient grid utilisation, fair access, and stable power distribution across regions.

Under the proposal, entities registered with the National Open Access Registry (NOAR) for short-term access approvals would also need to register with their respective Regional Load Dispatch Centres (RLDCs) for T-GNA approvals. This dual registration is expected to improve coordination and streamline approvals for temporary network access.

Bi-monthly clearance for deemed T-GNA

For generating stations whose General Network Access (GNA) is yet to become effective, RLDCs will identify projects seeking deemed T-GNA and issue standing clearances every two months. This measure will help projects operate within their sanctioned capacity while awaiting full GNA activation, preventing underutilisation of transmission infrastructure.

T-GNA clearance will be granted based on the available margin in the transmission network. This ensures grid stability and prevents over-scheduling, keeping total power flows within system limits while allowing optimal capacity use.

Equal treatment for renewable projects

Renewable energy projects linked to a pooling station via deemed T-GNA will be treated on par with those holding or awaiting GNA. This ensures equitable access for clean energy developers and supports greater integration of renewables into the national grid.

Under the proposed system, applications for deemed T-GNA between the 1st and 15th of a month must be submitted within 24 hours of the 25th of the previous month. Permissions will be allocated pro-rata based on available transmission capacity, ensuring fair and transparent scheduling.

Applications submitted after the 25th will be considered on a first-come, first-served basis, maintaining openness and consistency in granting approvals.

Flexibility for hybrid power projects

Hybrid power generators — with or without energy storage — may receive standing clearance up to their installed capacity, provided scheduling remains within the approved connectivity quantum. This helps maintain safe and reliable operation of the transmission system.

Entities granted T-GNA for renewable energy projects (T-GNARE) can convert them into regular T-GNA by applying to the nodal RLDC. Power delivery can start four months after application, giving time for system integration and network coordination.

These proposed amendments are expected to enhance grid efficiency, promote renewable integration, and ensure fairness in allocating transmission capacity across India’s growing power sector.

Grid India has submitted proposals to amend the Central Electricity Regulatory Commission’s (CERC) draft procedure for granting Temporary General Network Access (T-GNA) to the interstate transmission system. The move aims to allow power projects to schedule up to their full T-GNA capacity, ensuring efficient grid utilisation, fair access, and stable power distribution across regions. Under the proposal, entities registered with the National Open Access Registry (NOAR) for short-term access approvals would also need to register with their respective Regional Load Dispatch Centres (RLDCs) for T-GNA approvals. This dual registration is expected to improve coordination and streamline approvals for temporary network access. Bi-monthly clearance for deemed T-GNA For generating stations whose General Network Access (GNA) is yet to become effective, RLDCs will identify projects seeking deemed T-GNA and issue standing clearances every two months. This measure will help projects operate within their sanctioned capacity while awaiting full GNA activation, preventing underutilisation of transmission infrastructure. T-GNA clearance will be granted based on the available margin in the transmission network. This ensures grid stability and prevents over-scheduling, keeping total power flows within system limits while allowing optimal capacity use. Equal treatment for renewable projects Renewable energy projects linked to a pooling station via deemed T-GNA will be treated on par with those holding or awaiting GNA. This ensures equitable access for clean energy developers and supports greater integration of renewables into the national grid. Under the proposed system, applications for deemed T-GNA between the 1st and 15th of a month must be submitted within 24 hours of the 25th of the previous month. Permissions will be allocated pro-rata based on available transmission capacity, ensuring fair and transparent scheduling. Applications submitted after the 25th will be considered on a first-come, first-served basis, maintaining openness and consistency in granting approvals. Flexibility for hybrid power projects Hybrid power generators — with or without energy storage — may receive standing clearance up to their installed capacity, provided scheduling remains within the approved connectivity quantum. This helps maintain safe and reliable operation of the transmission system. Entities granted T-GNA for renewable energy projects (T-GNARE) can convert them into regular T-GNA by applying to the nodal RLDC. Power delivery can start four months after application, giving time for system integration and network coordination. These proposed amendments are expected to enhance grid efficiency, promote renewable integration, and ensure fairness in allocating transmission capacity across India’s growing power sector.

Related Stories

Gold Stories

Next Story
Infrastructure Transport

Mumbai-Ahmedabad Bullet Train’s Surat-Vapi Section Set for 2027

The first section of the Mumbai-Ahmedabad Bullet Train corridor, linking Surat and Vapi, is targeted to begin services in 2027. Construction is expected to be completed by December 2026, while Railway Minister Ashwini Vaishnaw has indicated that an inauguration could take place around the middle of 2027. The National High Speed Rail Corporation (NHSRCL) said the train being manufactured in India is expected to reach the tracks around April or May 2027. The train will undergo extensive testing before the section is opened for passenger services. The project began construction in 2021 and includ..

Next Story
Infrastructure Transport

Indian Railways Approves Four Projects Worth Rs. 7.36 bn Across Four States

Indian Railways has approved four projects with a combined value of Rs. 7.36 bn across Uttar Pradesh, Maharashtra, Andhra Pradesh and Gujarat. The programme covers train protection, signalling, electric traction supply and a road overbridge, with each project assigned to a different railway zone. In Uttar Pradesh, Rs. 2.52 bn has been approved to extend the Kavach 4.0 automatic train protection system across 607.7 km in the Lucknow Division of North Eastern Railway. The system monitors train movements and can apply the brakes if a driver fails to observe a signal or exceeds a safe speed. The w..

Next Story
Infrastructure Urban

Chandru Raheja Sells 1.49% Stake in Mindspace REIT for Rs. 5 bn

Billionaire Chandru Lachmandas Raheja has sold a 1.49 per cent holding in Mindspace Business Parks REIT for Rs. 5 bn through a bulk deal on the BSE. The transaction involved 9.9 mn units and was executed at an average price of Rs. 505 per unit, according to exchange data. Following the sale, units of Mindspace Business Parks REIT were trading 0.18 per cent lower at Rs. 504.05 on Tuesday. Exchange data did not identify the buyers involved in the transaction. Raheja is the chairman of real estate company K Raheja Corp. The sale involved 99,00,990 units, representing 1.49 per cent of the Mumbai-b..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

SPECIAL OFFER
QR Code