NTPC Issues 400 MWh BESS Tender After GR Infraprojects Termination
POWER & RENEWABLE ENERGY

NTPC Issues 400 MWh BESS Tender After GR Infraprojects Termination

NTPC has issued a tender to develop a 400 MWh Battery Energy Storage System (BESS) at NTPC Mouda Super Thermal Power Station in Maharashtra. Bids are scheduled to be submitted by October 22, 2026. The tender follows the termination of an earlier contract awarded to GR Infraprojects for the same project.

NTPC terminated the contract after GR Infraprojects failed to meet its contractual obligations, take immediate corrective measures and achieve the required progress. The original contract was awarded in March 2026 at a cost of Rs. 4.13 bn, with completion scheduled within 15 months. NTPC has now initiated a re-tendering process to facilitate the early re-award and timely execution of the project.

The re-tender is being undertaken at the risk and cost of GR Infraprojects, in line with the applicable contractual provisions. The project forms part of NTPC’s wider programme to deploy battery storage alongside its conventional power generation assets. The company is developing storage projects at multiple locations as renewable generation increases the need for grid balancing and flexibility.

The scope covers the battery system, Battery Management System, Energy Management System, supervisory control and data acquisition system, Power Conversion System, protection and communication systems, and high-tension and low-tension infrastructure. It also includes auxiliary power, fire detection and protection, remote control and monitoring facilities, and other materials and accessories required for the reliable operation and maintenance of the BESS.

The successful bidder will also be responsible for interconnecting the storage system with the existing thermal power station facilities. In addition, the contract includes a Comprehensive Annual Maintenance Contract for 11 years from the successful completion of the Performance Guarantee Test. The arrangement is intended to support sustained operation of the storage facility after commissioning.

NTPC has issued a tender to develop a 400 MWh Battery Energy Storage System (BESS) at NTPC Mouda Super Thermal Power Station in Maharashtra. Bids are scheduled to be submitted by October 22, 2026. The tender follows the termination of an earlier contract awarded to GR Infraprojects for the same project. NTPC terminated the contract after GR Infraprojects failed to meet its contractual obligations, take immediate corrective measures and achieve the required progress. The original contract was awarded in March 2026 at a cost of Rs. 4.13 bn, with completion scheduled within 15 months. NTPC has now initiated a re-tendering process to facilitate the early re-award and timely execution of the project. The re-tender is being undertaken at the risk and cost of GR Infraprojects, in line with the applicable contractual provisions. The project forms part of NTPC’s wider programme to deploy battery storage alongside its conventional power generation assets. The company is developing storage projects at multiple locations as renewable generation increases the need for grid balancing and flexibility. The scope covers the battery system, Battery Management System, Energy Management System, supervisory control and data acquisition system, Power Conversion System, protection and communication systems, and high-tension and low-tension infrastructure. It also includes auxiliary power, fire detection and protection, remote control and monitoring facilities, and other materials and accessories required for the reliable operation and maintenance of the BESS. The successful bidder will also be responsible for interconnecting the storage system with the existing thermal power station facilities. In addition, the contract includes a Comprehensive Annual Maintenance Contract for 11 years from the successful completion of the Performance Guarantee Test. The arrangement is intended to support sustained operation of the storage facility after commissioning.

Related Stories

Gold Stories

Next Story
Infrastructure Transport

Mumbai-Ahmedabad Bullet Train’s Surat-Vapi Section Set for 2027

The first section of the Mumbai-Ahmedabad Bullet Train corridor, linking Surat and Vapi, is targeted to begin services in 2027. Construction is expected to be completed by December 2026, while Railway Minister Ashwini Vaishnaw has indicated that an inauguration could take place around the middle of 2027. The National High Speed Rail Corporation (NHSRCL) said the train being manufactured in India is expected to reach the tracks around April or May 2027. The train will undergo extensive testing before the section is opened for passenger services. The project began construction in 2021 and includ..

Next Story
Infrastructure Transport

Indian Railways Approves Four Projects Worth Rs. 7.36 bn Across Four States

Indian Railways has approved four projects with a combined value of Rs. 7.36 bn across Uttar Pradesh, Maharashtra, Andhra Pradesh and Gujarat. The programme covers train protection, signalling, electric traction supply and a road overbridge, with each project assigned to a different railway zone. In Uttar Pradesh, Rs. 2.52 bn has been approved to extend the Kavach 4.0 automatic train protection system across 607.7 km in the Lucknow Division of North Eastern Railway. The system monitors train movements and can apply the brakes if a driver fails to observe a signal or exceeds a safe speed. The w..

Next Story
Infrastructure Urban

Chandru Raheja Sells 1.49% Stake in Mindspace REIT for Rs. 5 bn

Billionaire Chandru Lachmandas Raheja has sold a 1.49 per cent holding in Mindspace Business Parks REIT for Rs. 5 bn through a bulk deal on the BSE. The transaction involved 9.9 mn units and was executed at an average price of Rs. 505 per unit, according to exchange data. Following the sale, units of Mindspace Business Parks REIT were trading 0.18 per cent lower at Rs. 504.05 on Tuesday. Exchange data did not identify the buyers involved in the transaction. Raheja is the chairman of real estate company K Raheja Corp. The sale involved 99,00,990 units, representing 1.49 per cent of the Mumbai-b..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

SPECIAL OFFER
QR Code