Renewable Energy Projects Face up to 12-month Delay in PPA Signing
POWER & RENEWABLE ENERGY

Renewable Energy Projects Face up to 12-month Delay in PPA Signing

India’s renewable energy sector is facing significant delays in the signing of power purchase agreements (PPAs), with around 80-90 GW of projects in the pipeline, of which 40-45 GW are experiencing delays, as reported by industry experts.

Kannan Krishnan, the Joint Managing Director of Jakson Green, stated that these delays affect all renewable energy projects, including FDRE and RTC tenders. He mentioned that discoms are now more inclined to engage with projects that have higher capacity utilization factors. Krishnan added that there is a considerable lag in the signing of PPAs, with over 40 to 45 GW of renewable energy projects being impacted, including REIPs and discoms.

Vikram V, Vice-President and Co-Group Head of Corporate Ratings at ICRA, explained that there is an 8-9 month gap between the award of projects and the signing of PPAs or PSAs by the bidding agencies. This delay in signing causes the deferral of project execution since the timeline for execution starts only after the PPA is signed. He further noted that the renewable project pipeline remains large at 80-90 GW, but a substantial portion of this is waiting for PPAs or PSAs to be signed. While bidding activity remains robust and contributes to building the project pipeline for future capacity, Vikram stressed the importance of timely PPA or PSA signing to begin execution.

The delays are attributed to several factors, including regulatory uncertainties, financial challenges faced by discoms, mismatches between state and central policies, grid infrastructure limitations, and tariff rate disputes. Ravi Shekhar, Managing Director of Eninrac Consulting, highlighted that these delays, arising from structural and operational challenges, are affecting project timelines, causing cost overruns, lowering investor confidence, and increasing risk perception.

In 2022, while the planned RE capacity was 15 GW, PPAs were signed for only 9.5 GW, with delays of 6-12 months in PPA signing. In 2023, 12 GW of PPAs were signed for the 18 GW planned capacity, with delays of 8-10 months. In 2024, PPA signing is expected to experience a delay of 4-8 months.

Regarding states with the most significant delays, Renew’s 500 MW solar project in Gujarat faced a 12-month delay, while Adani Green’s 400 MW wind-solar hybrid project in Andhra Pradesh was delayed by 10 months. Tata Power’s 350 MW hybrid project in Karnataka was delayed by 9 months, as per data shared by the research consultancy up to November 2024.

Krishnan from Jakson Green explained that the government has a clear bidding trajectory for public sector undertakings such as NHPC, NTPC, SECI, and SJVN. Consequently, tenders are being auctioned without offtake agreements in place to meet the bidding calendar. He noted that previously, tenders were only auctioned when there was certainty about the PSA, ensuring an offtake agreement in a short duration. He suggested that the government should also establish a similar offtake calendar for discoms to align PPAs and PSAs.

Shekhar further identified the primary causes of delay, including the financial struggles of discoms, tariff disputes, policy misalignment, and grid infrastructure limitations. Many state-owned discoms face substantial debt, hindering their ability to commit to long-term PPAs. Delayed payments for existing renewable projects have further increased the reluctance to sign new agreements. He also mentioned that tariff disagreements between state and central governments often prolong negotiations, with developers seeking higher tariffs to cover inflation and costs, while discoms push for lower rates. Additionally, grid infrastructure limitations constrain the integration of large-scale renewable energy projects, leading discoms to be cautious about committing to new capacity.

Vikram from ICRA emphasized that the enforcement of Renewable Purchase Obligation (RPO) norms would be critical in prompting discoms to sign PPAs and PSAs. Another industry expert suggested that stronger penalties should be implemented on discoms for failing to meet RPO obligations quarterly.

"Join industry leaders at RAHSTA Expo, India's premier platform for roads, highways and traffic infrastructure. Register now to explore innovations, network with experts and shape the future of mobility."

India’s renewable energy sector is facing significant delays in the signing of power purchase agreements (PPAs), with around 80-90 GW of projects in the pipeline, of which 40-45 GW are experiencing delays, as reported by industry experts. Kannan Krishnan, the Joint Managing Director of Jakson Green, stated that these delays affect all renewable energy projects, including FDRE and RTC tenders. He mentioned that discoms are now more inclined to engage with projects that have higher capacity utilization factors. Krishnan added that there is a considerable lag in the signing of PPAs, with over 40 to 45 GW of renewable energy projects being impacted, including REIPs and discoms. Vikram V, Vice-President and Co-Group Head of Corporate Ratings at ICRA, explained that there is an 8-9 month gap between the award of projects and the signing of PPAs or PSAs by the bidding agencies. This delay in signing causes the deferral of project execution since the timeline for execution starts only after the PPA is signed. He further noted that the renewable project pipeline remains large at 80-90 GW, but a substantial portion of this is waiting for PPAs or PSAs to be signed. While bidding activity remains robust and contributes to building the project pipeline for future capacity, Vikram stressed the importance of timely PPA or PSA signing to begin execution. The delays are attributed to several factors, including regulatory uncertainties, financial challenges faced by discoms, mismatches between state and central policies, grid infrastructure limitations, and tariff rate disputes. Ravi Shekhar, Managing Director of Eninrac Consulting, highlighted that these delays, arising from structural and operational challenges, are affecting project timelines, causing cost overruns, lowering investor confidence, and increasing risk perception. In 2022, while the planned RE capacity was 15 GW, PPAs were signed for only 9.5 GW, with delays of 6-12 months in PPA signing. In 2023, 12 GW of PPAs were signed for the 18 GW planned capacity, with delays of 8-10 months. In 2024, PPA signing is expected to experience a delay of 4-8 months. Regarding states with the most significant delays, Renew’s 500 MW solar project in Gujarat faced a 12-month delay, while Adani Green’s 400 MW wind-solar hybrid project in Andhra Pradesh was delayed by 10 months. Tata Power’s 350 MW hybrid project in Karnataka was delayed by 9 months, as per data shared by the research consultancy up to November 2024. Krishnan from Jakson Green explained that the government has a clear bidding trajectory for public sector undertakings such as NHPC, NTPC, SECI, and SJVN. Consequently, tenders are being auctioned without offtake agreements in place to meet the bidding calendar. He noted that previously, tenders were only auctioned when there was certainty about the PSA, ensuring an offtake agreement in a short duration. He suggested that the government should also establish a similar offtake calendar for discoms to align PPAs and PSAs. Shekhar further identified the primary causes of delay, including the financial struggles of discoms, tariff disputes, policy misalignment, and grid infrastructure limitations. Many state-owned discoms face substantial debt, hindering their ability to commit to long-term PPAs. Delayed payments for existing renewable projects have further increased the reluctance to sign new agreements. He also mentioned that tariff disagreements between state and central governments often prolong negotiations, with developers seeking higher tariffs to cover inflation and costs, while discoms push for lower rates. Additionally, grid infrastructure limitations constrain the integration of large-scale renewable energy projects, leading discoms to be cautious about committing to new capacity. Vikram from ICRA emphasized that the enforcement of Renewable Purchase Obligation (RPO) norms would be critical in prompting discoms to sign PPAs and PSAs. Another industry expert suggested that stronger penalties should be implemented on discoms for failing to meet RPO obligations quarterly.

Next Story
Infrastructure Urban

IHC and Adani to Invest US$11.5 bn in Odisha Aluminium Project

Abu Dhabi's International Holding Company (IHC) will invest US$11.5 bn in an integrated aluminium project in the eastern Indian state of Odisha in a joint venture with the Adani Group, a state official said. The official said the announcement represented the country's largest foreign investment in mining and metallurgy. Officials said the venture would span both mining and metallurgical activities across several facilities in the state. The project has been described as integrated, encompassing upstream bauxite extraction and downstream smelting and metallurgy, and is intended to develop a com..

Next Story
Infrastructure Transport

Air India and SIAEC to Explore MRO Joint Venture in India

Air India and SIA Engineering Company (SIAEC) have signed a memorandum of understanding (MoU) to explore the formation of a maintenance, repair and overhaul joint venture in India. The MoU, signed on Friday, will examine collaboration to develop India as a global aviation MRO hub and to serve growing needs across the Indian and regional markets. SIA Engineering Company, part of the Singapore Airlines Group which holds a 25.1 per cent stake in Air India, will bring technical expertise alongside Air India's established airline operations network. The partnership builds on existing cooperation be..

Next Story
Infrastructure Transport

Assam and Centre Review Aviation Projects Push Silchar Airport Approval

Assam and the Centre on Thursday, July two reviewed a series of aviation infrastructure projects aimed at strengthening air connectivity across the state, with the proposed greenfield airport at Silchar emerging as a key priority. The review formed part of broader efforts to position Assam as a major aviation and logistics hub for the north east. Officials outlined timelines and preparatory work that they said would guide the next stages of project approvals. The Chief Minister met the Union Civil Aviation Minister at Rajiv Gandhi Bhavan in New Delhi and described the meeting as very productiv..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement