Right-of-Way Issues Delay 14 Interstate Transmission Projects
POWER & RENEWABLE ENERGY

Right-of-Way Issues Delay 14 Interstate Transmission Projects

Fourteen interstate transmission system (ISTS) projects are facing delays due to prolonged right-of-way (RoW) issues, primarily driven by demands for higher compensation than state-approved rates. Additional challenges, including delays in forest clearances, have further stalled progress, according to Minister of State for Power Shripad Naik. Of the 14 affected projects, eight are being executed by POWERGRID, while six are handled by private companies, including Adani, Sterlite, Tata Power, and ReNew. These projects span multiple states. To address compensation concerns, the Ministry of Power revised RoW payment guidelines in June 2024, linking land rates to market values. Compensation for tower base areas was increased to 200% of land value, while the RoW corridor compensation was raised to 30%. The revised guidelines apply to transmission lines of 66 kV and above, excluding sub-transmission and distribution lines below this voltage. Despite these delays, the government ensures renewable energy evacuation by utilising margins in existing transmission networks wherever feasible. To mitigate RoW challenges, project route alignments are now validated through the PM Gati Shakti portal, optimising corridor planning in urban and forested areas. Additionally, the Ministry of Power is leveraging the Project Monitoring Group under the Department for Promotion of Industry and Internal Trade to coordinate with state governments, Union ministries, and transmission service providers to fast-track issue resolution. Transmission infrastructure remains a critical bottleneck in India's renewable energy expansion, with ongoing issues such as landholder opposition, litigation, and delays in environmental approvals further impacting project timelines. (mercom)

Fourteen interstate transmission system (ISTS) projects are facing delays due to prolonged right-of-way (RoW) issues, primarily driven by demands for higher compensation than state-approved rates. Additional challenges, including delays in forest clearances, have further stalled progress, according to Minister of State for Power Shripad Naik. Of the 14 affected projects, eight are being executed by POWERGRID, while six are handled by private companies, including Adani, Sterlite, Tata Power, and ReNew. These projects span multiple states. To address compensation concerns, the Ministry of Power revised RoW payment guidelines in June 2024, linking land rates to market values. Compensation for tower base areas was increased to 200% of land value, while the RoW corridor compensation was raised to 30%. The revised guidelines apply to transmission lines of 66 kV and above, excluding sub-transmission and distribution lines below this voltage. Despite these delays, the government ensures renewable energy evacuation by utilising margins in existing transmission networks wherever feasible. To mitigate RoW challenges, project route alignments are now validated through the PM Gati Shakti portal, optimising corridor planning in urban and forested areas. Additionally, the Ministry of Power is leveraging the Project Monitoring Group under the Department for Promotion of Industry and Internal Trade to coordinate with state governments, Union ministries, and transmission service providers to fast-track issue resolution. Transmission infrastructure remains a critical bottleneck in India's renewable energy expansion, with ongoing issues such as landholder opposition, litigation, and delays in environmental approvals further impacting project timelines. (mercom)

Next Story
Real Estate

Integrated Waterproofing Strategies

Waterproofing buildings used to be an annual pre-monsoon affair but the evolution of real-estate development has changed that approach. In new developments, developers are weaving waterproofing solutions into both the design and construction phases, an approach that Nikhil Madan, Managing Director, Mahima Group, says, “is all about ensuring lasting durability [of the building] and keeping lifecycle risks including water seepage and extensive maintenance to a minimum.”Watertight by designAluminium formwork systems aren’t commonly thought of as a waterproofing tool but at the Mahima Group,..

Next Story
Infrastructure Urban

GROHE Showcases Water-Led Design At Milan

GROHE unveiled its GROHE SPA Aqua Sanctuary at Milan Design Week 2026, transforming Piccolo Teatro Studio Melato into an immersive showcase of water, design and wellbeing. Built on the philosophy of ‘Wellbeing Through Water’, the installation reimagined bathrooms as holistic spaces for relaxation, rejuvenation and self-care.The Aqua Sanctuary was presented through three interconnected sanctums. The first showcased the 3D-printed GROHE SPA AquaTree shower and faucet, highlighting bespoke innovation and biophilic design. The second featured the Atrio Private Collection and GROHE SPA x Buster..

Next Story
Infrastructure Transport

Rahee Group Expands Rail Manufacturing Capacity

Rahee Group has outlined a multi-year investment roadmap to expand its operational footprint and strengthen manufacturing capabilities for India’s growing railway and urban transit sector. The Group is expanding in Odisha with a new Track Component Casting Unit, for which the groundbreaking ceremony was held on 8 April 2026 in the presence of Odisha Chief Minister Mohan Charan Majhi.The Group’s flagship EPC arm, Rahee Infratech Ltd, continues to focus on complex rail infrastructure projects, including track systems, bridges, viaducts and ballastless infrastructure. Its wholly owned subsidi..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement