+
Right-of-Way Issues Delay 14 Interstate Transmission Projects
POWER & RENEWABLE ENERGY

Right-of-Way Issues Delay 14 Interstate Transmission Projects

Fourteen interstate transmission system (ISTS) projects are facing delays due to prolonged right-of-way (RoW) issues, primarily driven by demands for higher compensation than state-approved rates. Additional challenges, including delays in forest clearances, have further stalled progress, according to Minister of State for Power Shripad Naik. Of the 14 affected projects, eight are being executed by POWERGRID, while six are handled by private companies, including Adani, Sterlite, Tata Power, and ReNew. These projects span multiple states. To address compensation concerns, the Ministry of Power revised RoW payment guidelines in June 2024, linking land rates to market values. Compensation for tower base areas was increased to 200% of land value, while the RoW corridor compensation was raised to 30%. The revised guidelines apply to transmission lines of 66 kV and above, excluding sub-transmission and distribution lines below this voltage. Despite these delays, the government ensures renewable energy evacuation by utilising margins in existing transmission networks wherever feasible. To mitigate RoW challenges, project route alignments are now validated through the PM Gati Shakti portal, optimising corridor planning in urban and forested areas. Additionally, the Ministry of Power is leveraging the Project Monitoring Group under the Department for Promotion of Industry and Internal Trade to coordinate with state governments, Union ministries, and transmission service providers to fast-track issue resolution. Transmission infrastructure remains a critical bottleneck in India's renewable energy expansion, with ongoing issues such as landholder opposition, litigation, and delays in environmental approvals further impacting project timelines. (mercom)

Fourteen interstate transmission system (ISTS) projects are facing delays due to prolonged right-of-way (RoW) issues, primarily driven by demands for higher compensation than state-approved rates. Additional challenges, including delays in forest clearances, have further stalled progress, according to Minister of State for Power Shripad Naik. Of the 14 affected projects, eight are being executed by POWERGRID, while six are handled by private companies, including Adani, Sterlite, Tata Power, and ReNew. These projects span multiple states. To address compensation concerns, the Ministry of Power revised RoW payment guidelines in June 2024, linking land rates to market values. Compensation for tower base areas was increased to 200% of land value, while the RoW corridor compensation was raised to 30%. The revised guidelines apply to transmission lines of 66 kV and above, excluding sub-transmission and distribution lines below this voltage. Despite these delays, the government ensures renewable energy evacuation by utilising margins in existing transmission networks wherever feasible. To mitigate RoW challenges, project route alignments are now validated through the PM Gati Shakti portal, optimising corridor planning in urban and forested areas. Additionally, the Ministry of Power is leveraging the Project Monitoring Group under the Department for Promotion of Industry and Internal Trade to coordinate with state governments, Union ministries, and transmission service providers to fast-track issue resolution. Transmission infrastructure remains a critical bottleneck in India's renewable energy expansion, with ongoing issues such as landholder opposition, litigation, and delays in environmental approvals further impacting project timelines. (mercom)

Related Stories

Gold Stories

Next Story
Infrastructure Transport

97 Per Cent Of Rongjeng-Mangsang-Adokgre Road Nears Completion

Deputy Chief Minister in-charge of public works Prestone Tynsong said in Shillong on 26 August that 97 per cent physical progress had been achieved on the ongoing Rongjeng-Mangsang-Adokgre road being constructed under the Non-Lapsable Central Pool of Resources (NLCPR). He noted the project was sanctioned in 2017 and that the stipulated time for completion had been 24 months from issue of the final work order. The deputy chief minister informed the assembly that the government had decided to include the remaining work under a World Bank project. In reply to a query from Rongjeng MLA Jim M Sangm..

Next Story
Infrastructure Transport

First TBM Starts Digging Five Point Three Kilometre Tunnel Under SGNP

The Goregaon-Mulund Link Road (GMLR) Phase three (B) project has reached a key milestone as the first tunnel boring machine (TBM) began excavation of the first of two tunnels beneath the Sanjay Gandhi National Park (SGNP). The machine, named Tulsi, started cutting a five point three kilometre bore that will link Dadasaheb Phalke Chitranagari in Goregaon East with Amar Nagar in Mulund West. Officials issued a statement noting the commencement of tunnelling work under the protected green belt. The twin tunnels are being constructed using mechanised tunnelling methods that aim to limit surface di..

Next Story
Infrastructure Transport

UP Approves Two Expressways And Rs 240 bn Infrastructure Push

The Uttar Pradesh Cabinet approved a series of infrastructure and industrial investment proposals totalling Rs 240 billion (Rs 240 bn), including two major expressway projects, a manufacturing and logistics cluster in Sultanpur and incentives for 11 industrial projects across the state. The decisions, taken at a meeting chaired by Chief Minister Yogi Adityanath, underline the state government’s focus on expanding road connectivity around emerging industrial hubs while attracting manufacturing investment to districts beyond major urban centres. The approvals cover both greenfield expressway c..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

SPECIAL OFFER
QR Code