Solar Growth May Slow Beyond FY28 on Awards, Grid Constraints
POWER & RENEWABLE ENERGY

Solar Growth May Slow Beyond FY28 on Awards, Grid Constraints

India’s solar capacity growth could face headwinds beyond FY28 as slower renewable energy project awards, delays in signing power agreements and transmission constraints threaten expansion, according to a report by Yes Securities. Near-term additions remain supported by a construction pipeline exceeding 150 GW and rising rooftop installations, but weaker award activity could affect capacity additions and industry volumes in FY29 and FY30.

Solar capacity additions nearly doubled to 44.61 GW in FY26 from 23.83 GW in FY25. Installations remained strong in the first half of FY27, when 21 GW of solar alternating current capacity was added. However, fresh renewable energy awards fell to 14.7 GW in FY26 from 40.6 GW in FY25, while only 4.7 GW had been awarded in FY27 up to August 10, 2026.

The slowdown has coincided with delays in securing power purchase agreements (PPAs) and power sale agreements (PSAs). About 40 to 45 GW of awarded renewable energy capacity was yet to secure these agreements, creating uncertainty over project execution. Yes Securities said the construction pipeline should support demand for solar modules through FY28, although weaker awards could affect volumes in the following two financial years.

Transmission bottlenecks and rising grid curtailment are adding to sector challenges. Solar power curtailment reached 8,133 gigawatt-hours (GWh) during April-June 2026, with Rajasthan and Gujarat among the states facing difficulties in evacuating renewable power. Curtailment occurs when available electricity cannot be transmitted or absorbed by the grid, limiting delivered power.

Rooftop and agricultural solar programmes continue to support installations and demand for domestic modules. The PM Surya Ghar scheme added 2.4 mn rooftop systems in the first half of FY27, compared with 1.7 mn during the whole of FY26. The PM-Kusum programme is also supporting domestically manufactured modules, while storage-linked tenders are emerging as another demand source, though they could direct more investment towards battery storage.

India’s solar capacity growth could face headwinds beyond FY28 as slower renewable energy project awards, delays in signing power agreements and transmission constraints threaten expansion, according to a report by Yes Securities. Near-term additions remain supported by a construction pipeline exceeding 150 GW and rising rooftop installations, but weaker award activity could affect capacity additions and industry volumes in FY29 and FY30. Solar capacity additions nearly doubled to 44.61 GW in FY26 from 23.83 GW in FY25. Installations remained strong in the first half of FY27, when 21 GW of solar alternating current capacity was added. However, fresh renewable energy awards fell to 14.7 GW in FY26 from 40.6 GW in FY25, while only 4.7 GW had been awarded in FY27 up to August 10, 2026. The slowdown has coincided with delays in securing power purchase agreements (PPAs) and power sale agreements (PSAs). About 40 to 45 GW of awarded renewable energy capacity was yet to secure these agreements, creating uncertainty over project execution. Yes Securities said the construction pipeline should support demand for solar modules through FY28, although weaker awards could affect volumes in the following two financial years. Transmission bottlenecks and rising grid curtailment are adding to sector challenges. Solar power curtailment reached 8,133 gigawatt-hours (GWh) during April-June 2026, with Rajasthan and Gujarat among the states facing difficulties in evacuating renewable power. Curtailment occurs when available electricity cannot be transmitted or absorbed by the grid, limiting delivered power. Rooftop and agricultural solar programmes continue to support installations and demand for domestic modules. The PM Surya Ghar scheme added 2.4 mn rooftop systems in the first half of FY27, compared with 1.7 mn during the whole of FY26. The PM-Kusum programme is also supporting domestically manufactured modules, while storage-linked tenders are emerging as another demand source, though they could direct more investment towards battery storage.

Related Stories

Gold Stories

Next Story
Technology

ABB Unveils Intelligent Motor to Accelerate Industrial AI Adoption

ABB recently launched Intelleqt, which it describes as the world’s first low-voltage motor with factory-integrated intelligence, at the SPS trade fair in Germany. Designed to deliver real-time operational insights from its first rotation, the motor enables industrial operators to integrate equipment-level data into existing digital platforms while retaining full ownership of their data.The launch addresses growing challenges in scaling artificial intelligence (AI) across industrial operations, particularly data quality and availability. According to Deloitte, while 84 per cent of manufacture..

Next Story
Real Estate

Hiranandani’s Centaurus Becomes India’s First SmartScore Platinum Tower

House of Hiranandani’s Centaurus, a Grade A commercial tower at Hiranandani Estate, Thane, recently became India’s first building to achieve SmartScore Platinum certification, the highest rating under the globally recognised smart building certification framework. The development is also the country’s first building to hold both SmartScore and WiredScore certifications at the Platinum level.SmartScore certification evaluates a building’s smart capabilities, digital infrastructure, intelligent building systems and technology-led solutions that enhance occupier experience, operational ef..

Next Story
Infrastructure Transport

PM Modi May Lay Foundation Stone for Mamnoor Airport in December

Prime Minister Narendra Modi is expected to lay the foundation stone for Mamnoor Airport in Warangal during a proposed visit to Telangana in December, according to a tentative schedule. A public meeting is also being planned, with the event likely to form a central part of the Bharatiya Janata Party’s campaign ahead of Legislative Council and civic elections. The BJP is preparing to present the proposed airport, highway construction, railway modernisation, the Kazipet coach factory and improved urban connectivity as evidence of the Union government’s infrastructure focus in Telangana. The ..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

SPECIAL OFFER
QR Code