Tata Power Commissions Second Element Of Jalpura-Khurja Project
POWER & RENEWABLE ENERGY

Tata Power Commissions Second Element Of Jalpura-Khurja Project

Tata Power has commissioned the second element of the Jalpura-Khurja transmission project in Uttar Pradesh, strengthening the state's power transmission infrastructure and improving connectivity to growing electricity demand centres across the National Capital Region and western Uttar Pradesh. The work was executed by TP Jalpura Khurja Power Transmission, a wholly owned subsidiary of Tata Power. The commissioning follows the company's ongoing efforts to expand high-voltage transmission capacity in the region.

The second element comprises a 400 kilovolt (kV) double-circuit transmission line between Khurja and Jalpura spanning 162 circuit kilometres (CKM) and a 400/220 kilovolt (kV) gas insulated switchgear (GIS) substation at Jalpura with 1,000 megavolt ampere (MVA) transformation capacity. The 162 CKM corridor consists of two circuits of approximately 81 kilometre each and establishes a critical high-voltage link between Khurja and Jalpura. Khurja functions as an important power node in western Uttar Pradesh and plays a strategic role in enabling efficient transmission towards the National Capital Region and Noida.

The newly commissioned 400/220 kV GIS substation at Jalpura will act as a major power gateway, enabling transfer of power from the 400 kV grid to the 220 kV network and supporting the region's rising electricity needs. The substation is expected to improve reliability, resilience and efficiency of the transmission network while facilitating load management across connected centres. The arrangement will reduce bottlenecks and support distribution planning as demand grows.

Tata Power's transmission portfolio now totals 7,900 circuit kilometres of lines operational and under execution across India, reinforcing the company's role in strengthening the nation's electricity transmission network. The commissioning forms part of a broader strategy to expand transmission capacity to meet projected demand in key load centres. The company will continue to pursue projects that enhance grid stability and interregional connectivity.

Tata Power has commissioned the second element of the Jalpura-Khurja transmission project in Uttar Pradesh, strengthening the state's power transmission infrastructure and improving connectivity to growing electricity demand centres across the National Capital Region and western Uttar Pradesh. The work was executed by TP Jalpura Khurja Power Transmission, a wholly owned subsidiary of Tata Power. The commissioning follows the company's ongoing efforts to expand high-voltage transmission capacity in the region. The second element comprises a 400 kilovolt (kV) double-circuit transmission line between Khurja and Jalpura spanning 162 circuit kilometres (CKM) and a 400/220 kilovolt (kV) gas insulated switchgear (GIS) substation at Jalpura with 1,000 megavolt ampere (MVA) transformation capacity. The 162 CKM corridor consists of two circuits of approximately 81 kilometre each and establishes a critical high-voltage link between Khurja and Jalpura. Khurja functions as an important power node in western Uttar Pradesh and plays a strategic role in enabling efficient transmission towards the National Capital Region and Noida. The newly commissioned 400/220 kV GIS substation at Jalpura will act as a major power gateway, enabling transfer of power from the 400 kV grid to the 220 kV network and supporting the region's rising electricity needs. The substation is expected to improve reliability, resilience and efficiency of the transmission network while facilitating load management across connected centres. The arrangement will reduce bottlenecks and support distribution planning as demand grows. Tata Power's transmission portfolio now totals 7,900 circuit kilometres of lines operational and under execution across India, reinforcing the company's role in strengthening the nation's electricity transmission network. The commissioning forms part of a broader strategy to expand transmission capacity to meet projected demand in key load centres. The company will continue to pursue projects that enhance grid stability and interregional connectivity.

Related Stories

Gold Stories

Next Story
Real Estate

WSB Real Estate Partners Exits Six Housing Investments

WSB Real Estate Partners recently announced the successful exit of six residential investments across Bengaluru, Mumbai Metropolitan Region (MMR) and National Capital Region (NCR), delivering an average internal rate of return (IRR) of 19–21 per cent and an overall investment return of 1.4 times.The real estate-focused investment firm invested approximately Rs 7 billion across six mid-affordable housing projects over the past four years. All six investments were fully repaid between April and November 2026, several months ahead of their original investment tenures.WSB collaborated with sever..

Next Story
Infrastructure Transport

Aluminium Industry Seeks Policy Support for Rs 4 Trillion Investment

The Aluminium Association of India (AAI) has recently urged the government to introduce supportive policy measures to safeguard the sector’s proposed Rs 4 trillion investment pipeline. The association highlighted the need for a predictable policy framework to strengthen domestic manufacturing, expand production capacity and reduce import dependence.AAI submitted its recommendations for the Union Budget 2027-28 to the Ministries of Finance, Commerce and Industry, and Mines, along with the Department for Promotion of Industry and Internal Trade (DPIIT).India’s aluminium demand is projected t..

Next Story
Technology

ABB Unveils Intelligent Motor to Accelerate Industrial AI Adoption

ABB recently launched Intelleqt, which it describes as the world’s first low-voltage motor with factory-integrated intelligence, at the SPS trade fair in Germany. Designed to deliver real-time operational insights from its first rotation, the motor enables industrial operators to integrate equipment-level data into existing digital platforms while retaining full ownership of their data.The launch addresses growing challenges in scaling artificial intelligence (AI) across industrial operations, particularly data quality and availability. According to Deloitte, while 84 per cent of manufacture..

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

SPECIAL OFFER
QR Code