WOLFF cranes constructing high bridge over Neckar Valley
Equipment

WOLFF cranes constructing high bridge over Neckar Valley

When completed, this impressive 667-m-long and up to 90-m-high bridge will span the Neckar Valley near the small town of Horb in Baden-W'rttemberg. Thanks to this new bypass, traffic in the centre of Horb will be alleviated and the region's transport infrastructure will be upgraded. But until then, there will be plenty to do for the Porr GmbH & Co. KGaA construction company and the five WOLFF cranes that are in use at the enormous construction site. Their figures are also impressive: Two freestanding WOLFF cranes are operating on 96.4- and 100.9-m-high towers " a structural challenge for the Wolffkran team.

At present, the two WOLFF 7534.16 Clear cranes are drawing a lot of attention in the Neckar Valley: Both are around 100 m high and tower over the first 70-m elements of the new viaduct. Since the fall of 2023, they have been moving heavy freestanding steel components, formwork, reinforcements, and concrete buckets. With their 75-m jibs, they can lift a maximum of 16.5 tonne and 3.4 tonne at the top (4-strand operation). "This is normally not possible with a freestanding crane," explains Wolfgang Kavelius, Sales Manager at Wolffkran GmbH. "But the special design of the bridge piers meant that no tie-ins could be used, or they would have been disproportion-ately complex and expensive."

The technical WOLFF team makes it possible For this reason, Porr turned to the technical support team at Wolffkran, which not only developed a suitable crane concept but also a special structural solution for the two Porr-owned WOLFF cranes. "To ensure the necessary stability, the towers were assembled using three different tower elements," explains Peter Hegen-bart, Head of Sales Project Engineering at Wolffkran GmbH. The lower third of the towers is formed by the TV 33 tower element with a side length of 3.3 meters. Above this is a transition area composed of tower sections with a side length of 2.5 meters, which leads into the upper half of the tower made of 2x2-meter tower sections (TV 20). ?This specialized structure makes it possible to limit the maximum tower deformation to well under two meters, thus allowing the cranes to be operated safely as freestanding units," says Hegenbart.

?Thanks to Wolffkran's experience and technical expertise, we can use our own WOLFF 7534 Clear cranes as planned. This also allowed us to simply rent the additional 3.3-meter tower elements we needed for the project. We appreciate this flexibility, which goes above and beyond the normal standard, from our long-standing part-ner Wolffkran," says Markus Jahn, Project Manager at Porr.

Two-stage assembly in the narrow Neckar Valley In the inaccessible terrain of the Neckar Valley, which is also trav-ersed by an ICE railway line and a cycle path, the available space is very limited, which makes the construction site logistics particularly challenging. Because it was not possible to use a sufficiently large mobile crane to erect the two WOLFF 7534.16 Clear cranes to their ultimate heights, the assembly was carried out in two stages. After the mobile crane had assembled the tower to a height of around 60 meters, the cranes climbed the remaining 40 meters to the top using an external climbing mechanism. For space reasons, both cranes were placed on foundation anchors. As construction progresses, the complex assembly process, which takes two days per crane, will have to be repeated, as one of the two cranes will be moved to follow the progress of the expanding bridge.

The WOLFF 7534.16 Clear are currently being supported by a WOLFF 6031.12 Clear with a 65-meter jib and a 47.3-meter hook height. As the construction process moves forward, a WOLFF 7534.16 Clear and a WOLFF 6031.12 Clear from the Porr crane fleet will support the pack.

When completed, this impressive 667-m-long and up to 90-m-high bridge will span the Neckar Valley near the small town of Horb in Baden-W'rttemberg. Thanks to this new bypass, traffic in the centre of Horb will be alleviated and the region's transport infrastructure will be upgraded. But until then, there will be plenty to do for the Porr GmbH & Co. KGaA construction company and the five WOLFF cranes that are in use at the enormous construction site. Their figures are also impressive: Two freestanding WOLFF cranes are operating on 96.4- and 100.9-m-high towers a structural challenge for the Wolffkran team. At present, the two WOLFF 7534.16 Clear cranes are drawing a lot of attention in the Neckar Valley: Both are around 100 m high and tower over the first 70-m elements of the new viaduct. Since the fall of 2023, they have been moving heavy freestanding steel components, formwork, reinforcements, and concrete buckets. With their 75-m jibs, they can lift a maximum of 16.5 tonne and 3.4 tonne at the top (4-strand operation). This is normally not possible with a freestanding crane, explains Wolfgang Kavelius, Sales Manager at Wolffkran GmbH. But the special design of the bridge piers meant that no tie-ins could be used, or they would have been disproportion-ately complex and expensive. The technical WOLFF team makes it possible For this reason, Porr turned to the technical support team at Wolffkran, which not only developed a suitable crane concept but also a special structural solution for the two Porr-owned WOLFF cranes. To ensure the necessary stability, the towers were assembled using three different tower elements, explains Peter Hegen-bart, Head of Sales Project Engineering at Wolffkran GmbH. The lower third of the towers is formed by the TV 33 tower element with a side length of 3.3 meters. Above this is a transition area composed of tower sections with a side length of 2.5 meters, which leads into the upper half of the tower made of 2x2-meter tower sections (TV 20). ?This specialized structure makes it possible to limit the maximum tower deformation to well under two meters, thus allowing the cranes to be operated safely as freestanding units, says Hegenbart. ?Thanks to Wolffkran's experience and technical expertise, we can use our own WOLFF 7534 Clear cranes as planned. This also allowed us to simply rent the additional 3.3-meter tower elements we needed for the project. We appreciate this flexibility, which goes above and beyond the normal standard, from our long-standing part-ner Wolffkran, says Markus Jahn, Project Manager at Porr. Two-stage assembly in the narrow Neckar Valley In the inaccessible terrain of the Neckar Valley, which is also trav-ersed by an ICE railway line and a cycle path, the available space is very limited, which makes the construction site logistics particularly challenging. Because it was not possible to use a sufficiently large mobile crane to erect the two WOLFF 7534.16 Clear cranes to their ultimate heights, the assembly was carried out in two stages. After the mobile crane had assembled the tower to a height of around 60 meters, the cranes climbed the remaining 40 meters to the top using an external climbing mechanism. For space reasons, both cranes were placed on foundation anchors. As construction progresses, the complex assembly process, which takes two days per crane, will have to be repeated, as one of the two cranes will be moved to follow the progress of the expanding bridge. The WOLFF 7534.16 Clear are currently being supported by a WOLFF 6031.12 Clear with a 65-meter jib and a 47.3-meter hook height. As the construction process moves forward, a WOLFF 7534.16 Clear and a WOLFF 6031.12 Clear from the Porr crane fleet will support the pack.

Next Story
Infrastructure Urban

India To Invest $37 Billion To Boost Petrochemical Capacity

India is set to become a major global player in the petrochemicals industry, driven by a planned capital expenditure of $37 billion (Rs 3.1 trillion) aimed at reducing import dependency and enhancing self-sufficiency, according to S&P Global Ratings.In its latest report titled “First China, Now India: Self-Sufficiency Goals Will Add To Petrochemicals Supply”, S&P said India’s large-scale capacity expansion—mirroring China’s earlier push—will likely intensify oversupply pressures in Asia’s petrochemical markets.Currently the world’s third-largest petrochemical consumer a..

Next Story
Infrastructure Transport

Indian Railways Expands Global Exports Of Rail Equipment

Indian Railways has announced that it is rapidly emerging as a global exporter of railway equipment, including bogies, coaches, locomotives, and propulsion systems, under the government’s ‘Make in India, Make for the World’ initiative.According to an official statement, India’s railway products are now reaching over 16 international markets, reflecting the country’s growing capacity to design, develop, and deliver world-class rail solutions.Metro coaches have been exported to Australia and Canada; bogies to the United Kingdom, Saudi Arabia, France, and Australia; propulsion systems t..

Next Story
Infrastructure Transport

RailTel Awards Rs 163 Million Contract To RTNS Technology

RailTel Corporation of India Limited (RailTel), a Mini Ratna Public Sector Undertaking, has awarded a domestic work order worth Rs 163 million to RTNS Technology Private Limited.The contract, issued on 30 September 2025, involves the supply and installation of equipment and related services for one of RailTel’s key customers. The project underscores RailTel’s commitment to advancing technology and communication infrastructure through collaboration with domestic system integrators.RTNS Technology Private Limited, an ISO-certified system integrator, provides comprehensive solutions for perim..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Talk to us?