+
WOLFF cranes constructing high bridge over Neckar Valley
Equipment

WOLFF cranes constructing high bridge over Neckar Valley

When completed, this impressive 667-m-long and up to 90-m-high bridge will span the Neckar Valley near the small town of Horb in Baden-W'rttemberg. Thanks to this new bypass, traffic in the centre of Horb will be alleviated and the region's transport infrastructure will be upgraded. But until then, there will be plenty to do for the Porr GmbH & Co. KGaA construction company and the five WOLFF cranes that are in use at the enormous construction site. Their figures are also impressive: Two freestanding WOLFF cranes are operating on 96.4- and 100.9-m-high towers " a structural challenge for the Wolffkran team.

At present, the two WOLFF 7534.16 Clear cranes are drawing a lot of attention in the Neckar Valley: Both are around 100 m high and tower over the first 70-m elements of the new viaduct. Since the fall of 2023, they have been moving heavy freestanding steel components, formwork, reinforcements, and concrete buckets. With their 75-m jibs, they can lift a maximum of 16.5 tonne and 3.4 tonne at the top (4-strand operation). "This is normally not possible with a freestanding crane," explains Wolfgang Kavelius, Sales Manager at Wolffkran GmbH. "But the special design of the bridge piers meant that no tie-ins could be used, or they would have been disproportion-ately complex and expensive."

The technical WOLFF team makes it possible For this reason, Porr turned to the technical support team at Wolffkran, which not only developed a suitable crane concept but also a special structural solution for the two Porr-owned WOLFF cranes. "To ensure the necessary stability, the towers were assembled using three different tower elements," explains Peter Hegen-bart, Head of Sales Project Engineering at Wolffkran GmbH. The lower third of the towers is formed by the TV 33 tower element with a side length of 3.3 meters. Above this is a transition area composed of tower sections with a side length of 2.5 meters, which leads into the upper half of the tower made of 2x2-meter tower sections (TV 20). ?This specialized structure makes it possible to limit the maximum tower deformation to well under two meters, thus allowing the cranes to be operated safely as freestanding units," says Hegenbart.

?Thanks to Wolffkran's experience and technical expertise, we can use our own WOLFF 7534 Clear cranes as planned. This also allowed us to simply rent the additional 3.3-meter tower elements we needed for the project. We appreciate this flexibility, which goes above and beyond the normal standard, from our long-standing part-ner Wolffkran," says Markus Jahn, Project Manager at Porr.

Two-stage assembly in the narrow Neckar Valley In the inaccessible terrain of the Neckar Valley, which is also trav-ersed by an ICE railway line and a cycle path, the available space is very limited, which makes the construction site logistics particularly challenging. Because it was not possible to use a sufficiently large mobile crane to erect the two WOLFF 7534.16 Clear cranes to their ultimate heights, the assembly was carried out in two stages. After the mobile crane had assembled the tower to a height of around 60 meters, the cranes climbed the remaining 40 meters to the top using an external climbing mechanism. For space reasons, both cranes were placed on foundation anchors. As construction progresses, the complex assembly process, which takes two days per crane, will have to be repeated, as one of the two cranes will be moved to follow the progress of the expanding bridge.

The WOLFF 7534.16 Clear are currently being supported by a WOLFF 6031.12 Clear with a 65-meter jib and a 47.3-meter hook height. As the construction process moves forward, a WOLFF 7534.16 Clear and a WOLFF 6031.12 Clear from the Porr crane fleet will support the pack.

When completed, this impressive 667-m-long and up to 90-m-high bridge will span the Neckar Valley near the small town of Horb in Baden-W'rttemberg. Thanks to this new bypass, traffic in the centre of Horb will be alleviated and the region's transport infrastructure will be upgraded. But until then, there will be plenty to do for the Porr GmbH & Co. KGaA construction company and the five WOLFF cranes that are in use at the enormous construction site. Their figures are also impressive: Two freestanding WOLFF cranes are operating on 96.4- and 100.9-m-high towers a structural challenge for the Wolffkran team. At present, the two WOLFF 7534.16 Clear cranes are drawing a lot of attention in the Neckar Valley: Both are around 100 m high and tower over the first 70-m elements of the new viaduct. Since the fall of 2023, they have been moving heavy freestanding steel components, formwork, reinforcements, and concrete buckets. With their 75-m jibs, they can lift a maximum of 16.5 tonne and 3.4 tonne at the top (4-strand operation). This is normally not possible with a freestanding crane, explains Wolfgang Kavelius, Sales Manager at Wolffkran GmbH. But the special design of the bridge piers meant that no tie-ins could be used, or they would have been disproportion-ately complex and expensive. The technical WOLFF team makes it possible For this reason, Porr turned to the technical support team at Wolffkran, which not only developed a suitable crane concept but also a special structural solution for the two Porr-owned WOLFF cranes. To ensure the necessary stability, the towers were assembled using three different tower elements, explains Peter Hegen-bart, Head of Sales Project Engineering at Wolffkran GmbH. The lower third of the towers is formed by the TV 33 tower element with a side length of 3.3 meters. Above this is a transition area composed of tower sections with a side length of 2.5 meters, which leads into the upper half of the tower made of 2x2-meter tower sections (TV 20). ?This specialized structure makes it possible to limit the maximum tower deformation to well under two meters, thus allowing the cranes to be operated safely as freestanding units, says Hegenbart. ?Thanks to Wolffkran's experience and technical expertise, we can use our own WOLFF 7534 Clear cranes as planned. This also allowed us to simply rent the additional 3.3-meter tower elements we needed for the project. We appreciate this flexibility, which goes above and beyond the normal standard, from our long-standing part-ner Wolffkran, says Markus Jahn, Project Manager at Porr. Two-stage assembly in the narrow Neckar Valley In the inaccessible terrain of the Neckar Valley, which is also trav-ersed by an ICE railway line and a cycle path, the available space is very limited, which makes the construction site logistics particularly challenging. Because it was not possible to use a sufficiently large mobile crane to erect the two WOLFF 7534.16 Clear cranes to their ultimate heights, the assembly was carried out in two stages. After the mobile crane had assembled the tower to a height of around 60 meters, the cranes climbed the remaining 40 meters to the top using an external climbing mechanism. For space reasons, both cranes were placed on foundation anchors. As construction progresses, the complex assembly process, which takes two days per crane, will have to be repeated, as one of the two cranes will be moved to follow the progress of the expanding bridge. The WOLFF 7534.16 Clear are currently being supported by a WOLFF 6031.12 Clear with a 65-meter jib and a 47.3-meter hook height. As the construction process moves forward, a WOLFF 7534.16 Clear and a WOLFF 6031.12 Clear from the Porr crane fleet will support the pack.

Next Story
Real Estate

MoHUA Sanctions 1.47 Lakh Additional Houses Under PMAY-U 2.0

In a major push towards the Government’s Housing for All mission, the Ministry of Housing and Urban Affairs (MoHUA) has approved 1,46,582 additional pucca houses under Pradhan Mantri Awas Yojana – Urban 2.0 (PMAY-U 2.0) for 14 States/UTs, bringing total sanctions under the revamped scheme to 8.56 lakh.The decision came during the fourth meeting of the Central Sanctioning and Monitoring Committee (CSMC), chaired by Srinivas Katikithala, Secretary, MoHUA, at the Ministry’s Kasturba Gandhi Marg office. Senior officials, State Principal Secretaries, and PMAY-U Mission Directors participated ..

Next Story
Real Estate

Piyush Goyal Inaugurates Expanded ISA Building at Intellectual Property Office

Union Minister of Commerce and Industry, Piyush Goyal, today inaugurated the newly expanded International Searching Authority (ISA) building at the Intellectual Property Office (IPO) in Dwarka, New Delhi, marking a major step forward in India’s intellectual property ecosystem.Addressing the gathering, Goyal highlighted that innovation has been central to India’s heritage for centuries, citing the engineering brilliance of the Konark Temple as a historic example. He emphasised that innovation is not just intellectual property but a symbol of sovereignty, and a key driver in India’s journe..

Next Story
Real Estate

SIEGER Boosts Automation in Mumbai Realty

SIEGER, a leading automation solutions provider, is expanding its advanced manufacturing capabilities to meet the surging demand for precision, high-speed automation in Mumbai’s rapidly growing real estate sector.Operating from a 21,000 m² advanced production hub in Coimbatore—part of a 40,000 m² integrated campus—SIEGER offers complete solutions from design and prototyping to manufacturing and deployment. The fully digitalised facility features CNC machining, QR-coded component tracking, conveyorized powder coating, and a Government of India–certified R&D centre, ensuring unmatc..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Talk to us?