WOLFF cranes constructing high bridge over Neckar Valley
Equipment

WOLFF cranes constructing high bridge over Neckar Valley

When completed, this impressive 667-m-long and up to 90-m-high bridge will span the Neckar Valley near the small town of Horb in Baden-W'rttemberg. Thanks to this new bypass, traffic in the centre of Horb will be alleviated and the region's transport infrastructure will be upgraded. But until then, there will be plenty to do for the Porr GmbH & Co. KGaA construction company and the five WOLFF cranes that are in use at the enormous construction site. Their figures are also impressive: Two freestanding WOLFF cranes are operating on 96.4- and 100.9-m-high towers " a structural challenge for the Wolffkran team.

At present, the two WOLFF 7534.16 Clear cranes are drawing a lot of attention in the Neckar Valley: Both are around 100 m high and tower over the first 70-m elements of the new viaduct. Since the fall of 2023, they have been moving heavy freestanding steel components, formwork, reinforcements, and concrete buckets. With their 75-m jibs, they can lift a maximum of 16.5 tonne and 3.4 tonne at the top (4-strand operation). "This is normally not possible with a freestanding crane," explains Wolfgang Kavelius, Sales Manager at Wolffkran GmbH. "But the special design of the bridge piers meant that no tie-ins could be used, or they would have been disproportion-ately complex and expensive."

The technical WOLFF team makes it possible For this reason, Porr turned to the technical support team at Wolffkran, which not only developed a suitable crane concept but also a special structural solution for the two Porr-owned WOLFF cranes. "To ensure the necessary stability, the towers were assembled using three different tower elements," explains Peter Hegen-bart, Head of Sales Project Engineering at Wolffkran GmbH. The lower third of the towers is formed by the TV 33 tower element with a side length of 3.3 meters. Above this is a transition area composed of tower sections with a side length of 2.5 meters, which leads into the upper half of the tower made of 2x2-meter tower sections (TV 20). ?This specialized structure makes it possible to limit the maximum tower deformation to well under two meters, thus allowing the cranes to be operated safely as freestanding units," says Hegenbart.

?Thanks to Wolffkran's experience and technical expertise, we can use our own WOLFF 7534 Clear cranes as planned. This also allowed us to simply rent the additional 3.3-meter tower elements we needed for the project. We appreciate this flexibility, which goes above and beyond the normal standard, from our long-standing part-ner Wolffkran," says Markus Jahn, Project Manager at Porr.

Two-stage assembly in the narrow Neckar Valley In the inaccessible terrain of the Neckar Valley, which is also trav-ersed by an ICE railway line and a cycle path, the available space is very limited, which makes the construction site logistics particularly challenging. Because it was not possible to use a sufficiently large mobile crane to erect the two WOLFF 7534.16 Clear cranes to their ultimate heights, the assembly was carried out in two stages. After the mobile crane had assembled the tower to a height of around 60 meters, the cranes climbed the remaining 40 meters to the top using an external climbing mechanism. For space reasons, both cranes were placed on foundation anchors. As construction progresses, the complex assembly process, which takes two days per crane, will have to be repeated, as one of the two cranes will be moved to follow the progress of the expanding bridge.

The WOLFF 7534.16 Clear are currently being supported by a WOLFF 6031.12 Clear with a 65-meter jib and a 47.3-meter hook height. As the construction process moves forward, a WOLFF 7534.16 Clear and a WOLFF 6031.12 Clear from the Porr crane fleet will support the pack.

"Join industry leaders at RAHSTA Expo, India's premier platform for roads, highways and traffic infrastructure. Register now to explore innovations, network with experts and shape the future of mobility."

When completed, this impressive 667-m-long and up to 90-m-high bridge will span the Neckar Valley near the small town of Horb in Baden-W'rttemberg. Thanks to this new bypass, traffic in the centre of Horb will be alleviated and the region's transport infrastructure will be upgraded. But until then, there will be plenty to do for the Porr GmbH & Co. KGaA construction company and the five WOLFF cranes that are in use at the enormous construction site. Their figures are also impressive: Two freestanding WOLFF cranes are operating on 96.4- and 100.9-m-high towers a structural challenge for the Wolffkran team. At present, the two WOLFF 7534.16 Clear cranes are drawing a lot of attention in the Neckar Valley: Both are around 100 m high and tower over the first 70-m elements of the new viaduct. Since the fall of 2023, they have been moving heavy freestanding steel components, formwork, reinforcements, and concrete buckets. With their 75-m jibs, they can lift a maximum of 16.5 tonne and 3.4 tonne at the top (4-strand operation). This is normally not possible with a freestanding crane, explains Wolfgang Kavelius, Sales Manager at Wolffkran GmbH. But the special design of the bridge piers meant that no tie-ins could be used, or they would have been disproportion-ately complex and expensive. The technical WOLFF team makes it possible For this reason, Porr turned to the technical support team at Wolffkran, which not only developed a suitable crane concept but also a special structural solution for the two Porr-owned WOLFF cranes. To ensure the necessary stability, the towers were assembled using three different tower elements, explains Peter Hegen-bart, Head of Sales Project Engineering at Wolffkran GmbH. The lower third of the towers is formed by the TV 33 tower element with a side length of 3.3 meters. Above this is a transition area composed of tower sections with a side length of 2.5 meters, which leads into the upper half of the tower made of 2x2-meter tower sections (TV 20). ?This specialized structure makes it possible to limit the maximum tower deformation to well under two meters, thus allowing the cranes to be operated safely as freestanding units, says Hegenbart. ?Thanks to Wolffkran's experience and technical expertise, we can use our own WOLFF 7534 Clear cranes as planned. This also allowed us to simply rent the additional 3.3-meter tower elements we needed for the project. We appreciate this flexibility, which goes above and beyond the normal standard, from our long-standing part-ner Wolffkran, says Markus Jahn, Project Manager at Porr. Two-stage assembly in the narrow Neckar Valley In the inaccessible terrain of the Neckar Valley, which is also trav-ersed by an ICE railway line and a cycle path, the available space is very limited, which makes the construction site logistics particularly challenging. Because it was not possible to use a sufficiently large mobile crane to erect the two WOLFF 7534.16 Clear cranes to their ultimate heights, the assembly was carried out in two stages. After the mobile crane had assembled the tower to a height of around 60 meters, the cranes climbed the remaining 40 meters to the top using an external climbing mechanism. For space reasons, both cranes were placed on foundation anchors. As construction progresses, the complex assembly process, which takes two days per crane, will have to be repeated, as one of the two cranes will be moved to follow the progress of the expanding bridge. The WOLFF 7534.16 Clear are currently being supported by a WOLFF 6031.12 Clear with a 65-meter jib and a 47.3-meter hook height. As the construction process moves forward, a WOLFF 7534.16 Clear and a WOLFF 6031.12 Clear from the Porr crane fleet will support the pack.

Next Story
Resources

G R Infraprojects Founder Vinod Agarwal Passes Away

Vinod Kumar Agarwal, Founder and Promoter of G R Infraprojects, has passed away. He had been associated with the company since its inception in 1995. His vision, determination and entrepreneurial acumen laid the foundation for the company and helped shape its growth into a leading name in India’s infrastructure sector.Agarwal served as Managing Director from 2008 to 2021 and later as Chairman and Whole-time Director from 2021 to 2025. He stepped down from the office of Director on 10 November 2025. During his leadership tenure, the company moved through significant phases of growth, operatio..

Next Story
Infrastructure Energy

Centre Prioritising Energy Security With Coal Gasification

Union minister for Coal and Mines G Kishan Reddy said the Centre is prioritising energy security through a strategic shift to coal gasification and has announced incentives totalling Rs 460 billion (bn) to support the effort. He said more than 35 companies will start coal gasification activities in India within two months and that the government is encouraging firms that bring technology to close the domestic technology gap. The minister described the initiative as aimed at reducing import dependence and developing indigenous capacity. India has the fifth-largest coal reserve in the world, and..

Next Story
Infrastructure Urban

BHEL and Coal India Invest Rs 250 bn in Odisha Gasification

Bharat Heavy Electricals (BHEL) and Coal India (CIL) are jointly investing Rs 250 billion in a coal gasification project in Odisha, with the Prime Minister laying the foundation stone in Jharsuguda. Union Coal and Mines Minister G Kishan Reddy described the initiative as a transformative shift in coal utilisation that will open industrial avenues for the state. The project moves coal beyond conventional power generation to industrial feedstocks. Coal gasification will convert coal into synthesis gas, a versatile feedstock for chemicals, fertilisers and synthetic fuels, and the technology is ex..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement