Infrastructure Projects Record Rs. 3.28 tn Cost Overrun in October
Real Estate

Infrastructure Projects Record Rs. 3.28 tn Cost Overrun in October

Infrastructure projects valued at more than Rs. 500 mn each recorded a cumulative cost overrun of approximately Rs. 3.28 tn in October 2026, according to a monthly report released by the Ministry of Statistics and Programme Implementation (MoSPI). The report monitored 1,862 ongoing projects across 17 central ministries and departments.

The total revised cost of the projects stood at Rs. 38.11 tn, compared with an original estimated cost of Rs. 34.83 tn. The report did not specify the number of individual projects that had recorded cost overruns. Cumulative expenditure reached Rs. 1.79 tn, representing 46.88 per cent of the project cost.

MoSPI said 649 projects, or 35 per cent of the total, had achieved more than 80 per cent physical progress. A further 326 projects, or 18 per cent, had crossed 80 per cent financial completion. The distribution of projects across early and advanced stages indicated a pipeline combining newly started developments with schemes nearing completion.

Transport and logistics accounted for the largest number of projects, at 1,324, with a cumulative cost of Rs. 2.04 tn. Of the overall total, 790 were mega projects with costs of Rs. 10 bn or more, while 1,072 were major projects below that threshold. The report said physical and financial progress broadly moved in tandem, although financial progress was relatively higher during the early stages because of upfront expenditure.

The Ministry of Road Transport and Highways had the largest portfolio, with 972 projects, accounting for 52 per cent of the total and a revised cost of Rs. 955 bn. The Ministry of Railways followed with 288 projects and a revised cost of Rs. 738 bn, while the Coal Ministry had 121 projects valued at Rs. 222 bn. Petroleum and natural gas, power, housing and urban affairs, and water resources departments accounted for 117, 108, 50 and 33 projects respectively.

Infrastructure projects valued at more than Rs. 500 mn each recorded a cumulative cost overrun of approximately Rs. 3.28 tn in October 2026, according to a monthly report released by the Ministry of Statistics and Programme Implementation (MoSPI). The report monitored 1,862 ongoing projects across 17 central ministries and departments. The total revised cost of the projects stood at Rs. 38.11 tn, compared with an original estimated cost of Rs. 34.83 tn. The report did not specify the number of individual projects that had recorded cost overruns. Cumulative expenditure reached Rs. 1.79 tn, representing 46.88 per cent of the project cost. MoSPI said 649 projects, or 35 per cent of the total, had achieved more than 80 per cent physical progress. A further 326 projects, or 18 per cent, had crossed 80 per cent financial completion. The distribution of projects across early and advanced stages indicated a pipeline combining newly started developments with schemes nearing completion. Transport and logistics accounted for the largest number of projects, at 1,324, with a cumulative cost of Rs. 2.04 tn. Of the overall total, 790 were mega projects with costs of Rs. 10 bn or more, while 1,072 were major projects below that threshold. The report said physical and financial progress broadly moved in tandem, although financial progress was relatively higher during the early stages because of upfront expenditure. The Ministry of Road Transport and Highways had the largest portfolio, with 972 projects, accounting for 52 per cent of the total and a revised cost of Rs. 955 bn. The Ministry of Railways followed with 288 projects and a revised cost of Rs. 738 bn, while the Coal Ministry had 121 projects valued at Rs. 222 bn. Petroleum and natural gas, power, housing and urban affairs, and water resources departments accounted for 117, 108, 50 and 33 projects respectively.

Related Stories

Gold Stories

Next Story
Equipment

SDLG Debuts K Series and Unmanned Wheel Loaders at bauma CHINA

SDLG recently unveiled its new K Series wheel loaders at bauma CHINA 2026 in Shanghai, showcasing six flagship models, including diesel, battery-electric, hybrid and unmanned intelligent wheel loaders.Designed for heavy-duty loading and material handling, the K Series comprises the L959K diesel, L986KEV battery-electric and L9160KHB hybrid models. The machines feature two-layer corrosion protection, improved operator cabins with reduced noise and vibration, digital interfaces, 360-degree camera systems and obstacle detection alerts. One-touch digging, automatic weighing and centralised lubrica..

Next Story
Real Estate

Sumadhura Group to invest Rs 6 billion in Tamil Nadu industrial park

Sumadhura Group has signed a memorandum of understanding (MoU) with the Tamil Nadu Government to develop a 52-acre Grade A industrial and logistics park at Vishnuvakkam, Chennai, with an investment of Rs 6 billion over the next two years.The MoU was signed at VETTRI – Tamil Nadu Investment & Conversion Conclave 2026, presided over by Chief Minister C. Joseph Vijay. The proposed development will have a built-up area of 1.2 million sq ft and is expected to generate more than 4,000 direct and indirect jobs.Under the agreement, the state government will facilitate regulatory and infrastructu..

Next Story
Real Estate

Brigade Group’s BuzzWorks enters Chennai with 65,000 sq ft

BuzzWorks, the flexible workspace and managed office solutions arm of Brigade Group, has entered Chennai with 65,000 sq ft of managed office space across two facilities at Brigade Tech Boulevard on Pallavaram–Thoraipakkam Radial Road and Brigade Vantage on Old Mahabalipuram Road (OMR).The facilities will cater to workspace demand from Global Capability Centres (GCCs), IT-BPM, engineering, manufacturing and BFSI companies. The two centres are expected to generate a combined annual revenue of approximately Rs 100 million. BuzzWorks plans to add a further 100,000 sq ft in Chennai by FY28.Siddha..

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

SPECIAL OFFER
QR Code