+
MMR has the highest number of delayed housing projects
Real Estate

MMR has the highest number of delayed housing projects

More than half the housing projects that have been delayed by over five years and are likely to reach completion post-2020 are in the Mumbai Metropolitan Region (MMR), data available with PropTiger show.

According to an analysis that includes 10 prime residential markets of the country, as many as 1,665 RERA-registered housing projects are delayed by over five years across India and are likely to see completing only after 2020. Of these, 880 projects constituting of over two lakh units are concentrated in the MMR market, counted as the most expensive property markets in India. On the other hand, a total of 125 projects are delayed across Noida, Greater Noida and Gurugram markets, consisting of over one lakh housing units.

 

Dealing with delays

 

List of projects delayed by over 5 years; set to see completion after 2020

City

No. of delayed projects

No. of delayed units

Ahmedabad

41

15,182

Bengaluru

45

22,972

Chennai

24

11,679

Greater Noida

53

64,510

Gurugram

34

21,259

Hyderabad

276

15,138

Kolkata

33

18,515

MMR*

880

204,380

Noida

38

30,643

Pune

241

47,462

Total

1,665

451,740

*Includes Mumbai, Navi Mumbai, Thane

Source: PropTiger DataLabs


“Liquidity issues could be cited as the single-biggest reason behind project delays in India, a phenomenon that has had an absolutely negative impact on buyer sentiment. The Rs 25,000-crore lifeline extended by the government in the form of an AIF would change much of that,” says Mani Rangarajan, Group COO, Elara Technologies, that owns PropTiger.com, Housing.com and Makaan.com.

“Housing projects in the MMR are more likely to meet the net-worth-positive and litigation-free conditions set under the AIF. This would mean a large part of the fund could be spent on completing projects in the Mumbai market. Because Mumbai is an expensive property market, the cost of project completion here would be comparatively lower than the ultimate price realisation. This would only help Mumbai’s case further,” he adds.

Project-delay wise, Hyderabad and Pune follow the MMR in the list, whereas many as 276 and 241 housing projects have been delayed for over five years, respectively. In terms of units, however, Hyderabad has one of the lowest score, at 15,138 delayed homes, in the list of 10 cities. In Pune, over 47,000 housing units delayed for more than half a decade would reach completion post-2020, data show.

Chennai has the lowest number of delayed projects (24) as well as units (11,679), primarily because the size of housing projects in this property market is comparatively smaller. Typically, builders launch housing projects with 50 units or less in Chennai which could be completed in a shorter time span. The chances of cost overruns in such projects are also low.

The markets covered in the analysis are Ahmedabad, Bengaluru, Chennai, Gurugram, Hyderabad, Kolkata, Mumbai, Noida-Greater Noida and Pune. While the budget range for housing projects in the MMR has been kept at Rs 2 crore, it is less than Rs 1.50 crore for other markets. Units of only up to 200-sq-m carpet area have been covered in the analysis.

While the analysis does not point out the specific reason behind the delay in these projects, majority of the projects have been stuck owing to liquidity crunch, delays in approvals, a periodic ban on construction activities and litigation.

Markets that might benefit from the recently announced Alternative Investment Fund (AIF)

The biggest beneficiary of the government’s recently announced Rs 25,000-crore AIF could be the MMR housing market. This, however, has more to do with the net-worth-positive state of the delayed projects here than their overwhelming numbers. This also has to do with the fact that a large number of delayed housing projects in the NCR would not meet the criterion to get funds under the AIF.

For a project to receive funding from the AIF, it has to be, among other things, net-worth positive – this means the completion cost and outstanding liabilities of these projects should exceed the worth of the receivables and the unsold inventory in these projects.

Real estate developers in Noida owned the city authority a whopping Rs 10,200 crore in dues in 2017. The fact that the outstanding dues may have doubled in the past two years casts serious aspersions on their net-worth positivity. Additionally, many developers in the region, including Amrapali, Jaypee, Unitech and 3C Company, have been dragged into litigation over charges of delays and misappropriation of funds. The Centre has clarified that projects that are seeing litigation in courts would not be considered under the stress fund.

More than half the housing projects that have been delayed by over five years and are likely to reach completion post-2020 are in the Mumbai Metropolitan Region (MMR), data available with PropTiger show. According to an analysis that includes 10 prime residential markets of the country, as many as 1,665 RERA-registered housing projects are delayed by over five years across India and are likely to see completing only after 2020. Of these, 880 projects constituting of over two lakh units are concentrated in the MMR market, counted as the most expensive property markets in India. On the other hand, a total of 125 projects are delayed across Noida, Greater Noida and Gurugram markets, consisting of over one lakh housing units.   Dealing with delays   List of projects delayed by over 5 years; set to see completion after 2020 City No. of delayed projects No. of delayed units Ahmedabad 41 15,182 Bengaluru 45 22,972 Chennai 24 11,679 Greater Noida 53 64,510 Gurugram 34 21,259 Hyderabad 276 15,138 Kolkata 33 18,515 MMR* 880 204,380 Noida 38 30,643 Pune 241 47,462 Total 1,665 451,740 *Includes Mumbai, Navi Mumbai, Thane Source: PropTiger DataLabs “Liquidity issues could be cited as the single-biggest reason behind project delays in India, a phenomenon that has had an absolutely negative impact on buyer sentiment. The Rs 25,000-crore lifeline extended by the government in the form of an AIF would change much of that,” says Mani Rangarajan, Group COO, Elara Technologies, that owns PropTiger.com, Housing.com and Makaan.com. “Housing projects in the MMR are more likely to meet the net-worth-positive and litigation-free conditions set under the AIF. This would mean a large part of the fund could be spent on completing projects in the Mumbai market. Because Mumbai is an expensive property market, the cost of project completion here would be comparatively lower than the ultimate price realisation. This would only help Mumbai’s case further,” he adds. Project-delay wise, Hyderabad and Pune follow the MMR in the list, whereas many as 276 and 241 housing projects have been delayed for over five years, respectively. In terms of units, however, Hyderabad has one of the lowest score, at 15,138 delayed homes, in the list of 10 cities. In Pune, over 47,000 housing units delayed for more than half a decade would reach completion post-2020, data show. Chennai has the lowest number of delayed projects (24) as well as units (11,679), primarily because the size of housing projects in this property market is comparatively smaller. Typically, builders launch housing projects with 50 units or less in Chennai which could be completed in a shorter time span. The chances of cost overruns in such projects are also low. The markets covered in the analysis are Ahmedabad, Bengaluru, Chennai, Gurugram, Hyderabad, Kolkata, Mumbai, Noida-Greater Noida and Pune. While the budget range for housing projects in the MMR has been kept at Rs 2 crore, it is less than Rs 1.50 crore for other markets. Units of only up to 200-sq-m carpet area have been covered in the analysis. While the analysis does not point out the specific reason behind the delay in these projects, majority of the projects have been stuck owing to liquidity crunch, delays in approvals, a periodic ban on construction activities and litigation. Markets that might benefit from the recently announced Alternative Investment Fund (AIF) The biggest beneficiary of the government’s recently announced Rs 25,000-crore AIF could be the MMR housing market. This, however, has more to do with the net-worth-positive state of the delayed projects here than their overwhelming numbers. This also has to do with the fact that a large number of delayed housing projects in the NCR would not meet the criterion to get funds under the AIF. For a project to receive funding from the AIF, it has to be, among other things, net-worth positive – this means the completion cost and outstanding liabilities of these projects should exceed the worth of the receivables and the unsold inventory in these projects. Real estate developers in Noida owned the city authority a whopping Rs 10,200 crore in dues in 2017. The fact that the outstanding dues may have doubled in the past two years casts serious aspersions on their net-worth positivity. Additionally, many developers in the region, including Amrapali, Jaypee, Unitech and 3C Company, have been dragged into litigation over charges of delays and misappropriation of funds. The Centre has clarified that projects that are seeing litigation in courts would not be considered under the stress fund.

Next Story
Infrastructure Transport

Lucknow Metro East-West Corridor Consultancy Contract Awarded

The Uttar Pradesh Metro Rail Corporation has awarded the first construction-related consultancy contract for the Lucknow Metro East West Corridor to a joint venture of AYESA Ingenieria Arquitectura SAU and AYESA India Pvt Ltd. The firm was declared the lowest bidder for the Detailed Design Consultant contract for Lucknow Metro Line-2 under Phase 1B and the contract was recommended following the financial bid. The contract is valued at Rs 159.0 million (mn), covering design services for the corridor. Lucknow Metro Line-2 envisages the construction of an 11.165 kilometre corridor connecting Cha..

Next Story
Infrastructure Urban

Div Com Kashmir Urges Fast Tracking Of Jhelum Water Transport Project

The Divisional Commissioner of Kashmir has called for the fast-tracking of the Jhelum water transport project, urging district administrations and relevant agencies to accelerate planning and clearances. In a meeting convened at the divisional headquarters, the commissioner instructed officials from irrigation, public health engineering and municipal departments to prioritise the project and coordinate survey and design work. The directive emphasised removal of administrative bottlenecks and close monitoring to ensure timely mobilisation of resources and contractors. Officials were told to in..

Next Story
Infrastructure Urban

Interarch Reports Strong Q3 And Nine Month Results

Interarch Building Solutions Limited reported unaudited results for the third quarter and nine months ended 31 December 2025, recording strong revenue growth driven by execution and a robust order book. Net revenue for the third quarter rose by 43.7 per cent to Rs 5.225 billion (bn), compared with Rs 3.636 bn a year earlier, reflecting heightened demand in pre-engineered building projects. The company’s total order book as at 31 January 2026 stood at Rs 16.85 bn, supporting near-term visibility. EBITDA excluding other income for the quarter increased by 43.2 per cent to Rs 503 million (mn),..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Open In App