Building with Brains
Technology

Building with Brains

The annual worldwide revenue for BIM products and services solutions is expected to grow from $1.8 billion in 2012 to almost $6.5 billion in 2020. Nirmalya Chatterjee elaborates on the technology, its uses and benefits in the construction industry.

For decades, architects, MEP designers and contractors used CAD-based libraries supplied by building product manufacturers for obtaining geometric data describing the product. As it applies to an HVAC system, this process is accurate in terms of geometry but limits integration of that information with the building’s structure and systems, often leading to on-site design changes. For example, if the rerouting piping or ductwork to avoid obstructions is not detected in the original design, it can ultimately affect both the project timeline and cost. To counter this problem, Building Information Modelling (BIM) was introduced under the virtua building concept by Graphisoft’s ArchiCAD in its debut in 1987.

Of late, BIM is being used by Tekla India for constructing the Chenab River Bridge Project in Jammu and Kashmir. Work on the project started in late 2004 and continued till early 2008. During this period, the foundations and piers were completed on the Kauri Village side. However, owing to geological obstacles and engineering challenges in the Udhampur Srinagar Baramulla Railway project, work on the bridge was suspended till September 2009. Currently, the Afcons-led JV – the main contractor of the project – has received the design approval for the viaduct portion and is expecting approval for the arch portion within the next three months.

Improved productivity

One of the biggest challenges for the contractor has been the number of drawings for the project. There are 65 segments in the viaduct, each with two assembly and around 100 part-list drawings. Overall, there will be over 7,000 drawings just for the viaduct. Proof checking and verifying each of these on site significantly slows down the actual erection and construction. However, the use of BIM has reduced these design errors and improved productivity.

Intelligent management

The BIM used includes an extensive range of connections with its automated clash-checking efficiently exposing conflicts in the structure. It also executes reinforced concrete, braces, elements and block constructions. The bridge geometry has been measured several times and the results compared with the model. In the pre-construction stage, the software helped the contractor understand the owner’s vision behind the design. During the planning stage, it helped in procurement and formulating better construction processes. During site management, it helped in centralising essential planning and management data. As the bridge is logistically challenging, BIM has helped organise the plate material for better logistics, besides getting the plans approved by local authorities with the accurate model.

Comprehensive design tool

The bridge uses 3D visualisation, which reduces design errors and enhances labour productivity. The process of visualisation, CAD tools and design methods have been integrated into the process. One can also connect models directly to 3D site measurements, which eliminates transfer of errors owing to human factors and data format conversions.

Major risks

Despite recent developments, adopting a single BIM technology in any project involves two major risks. The first includes lack of collaboration on the part of the project team and second, the lack of confidence of users in its accuracy. Thus, it is essential to recognise the value of BIM as a source of intelligent information and train industry players to use the technology. Reluctance on the part of some customers to adopt this technology could be owing to switching costs and uncertainty about its value-addition and services provided. Project teams usually rely on purpose-built models customised for specific project needs. In case of an owner, contractor and designer, the biggest problem lies in adopting new processes.

Lack of training

Implementation of BIM in India also lacks proper training facilities. Most firms still use 2D drafting tools as they do not wish to invest time in training their staff. Also, very few wish to pay the extra cost for digital models of their project. We have started BIM educational training hubs across several cities with an aim to train over 500 engineers by 2012.

Myths dispelled

Most firms believe that BIM results in loss of productivity during the transition period. But, these are just initial losses that can be compensated for in the longer run. In fact, BIM integrates seamlessly with current ways of working. The present systems need supporting technologies to aggregate information across different app­lications, thus transforming the industry’s design and construction pro­­cesses.

Cost savings

The standard way to calculate the Return on Investment (ROI) of any technology is to compare its cost and effect on productivity against the first year’s labour and training costs. In case of BIM, the results can vary from 20 to 60 per cent depending on the size of a company and the type of projects it executes. Although cost and labour savings are easy to calculate, most companies do not wish to publish figures for their BIM-generated revenue as it is difficult to establish accurate metrics for that. Customers can expect to save almost 30-40 per cent costs by using this technology in their projects.

However, this may vary depending on various factors such as project size and complexity, time, and available resources, etc.
In sum, BIM represents a breakthrough in building de­sign technology. The market for BIM software and services, though still nascent in India, is evolving rapidly. As building green be­comes increasingly imperative, the adoption of BIM tools and practices will become a priority as they can significantly affect the efficient use of scarce and valuable resources.

BIM advantage!

The technology includes both monitoring as well as wind effect and vibration studies in bridges designed in steel and concrete along with new technologies like laser scanning. The 3D model can be used to enter output measurements and dimensions and with the means of laser scanning creates a source model to accelerate the renovation of old bridges.

About the author:

Nirmalya Chatterjee, COO, Tekla India, is a graduate in engineering and management. He has served the company for the past six years and is the founder member of its India operations. Chatterjee has over 18 years of experience in the industry and is involved in promoting the BIM technology solution ‘Tekla Structures’, which addresses the complete lifecycle needs of construction projects.

If you have an innovative technology to share, write in at feedback@ASAPPmedia.com

The annual worldwide revenue for BIM products and services solutions is expected to grow from $1.8 billion in 2012 to almost $6.5 billion in 2020. Nirmalya Chatterjee elaborates on the technology, its uses and benefits in the construction industry.For decades, architects, MEP designers and contractors used CAD-based libraries supplied by building product manufacturers for obtaining geometric data describing the product. As it applies to an HVAC system, this process is accurate in terms of geometry but limits integration of that information with the building’s structure and systems, often leading to on-site design changes. For example, if the rerouting piping or ductwork to avoid obstructions is not detected in the original design, it can ultimately affect both the project timeline and cost. To counter this problem, Building Information Modelling (BIM) was introduced under the virtua building concept by Graphisoft’s ArchiCAD in its debut in 1987.Of late, BIM is being used by Tekla India for constructing the Chenab River Bridge Project in Jammu and Kashmir. Work on the project started in late 2004 and continued till early 2008. During this period, the foundations and piers were completed on the Kauri Village side. However, owing to geological obstacles and engineering challenges in the Udhampur Srinagar Baramulla Railway project, work on the bridge was suspended till September 2009. Currently, the Afcons-led JV – the main contractor of the project – has received the design approval for the viaduct portion and is expecting approval for the arch portion within the next three months.Improved productivityOne of the biggest challenges for the contractor has been the number of drawings for the project. There are 65 segments in the viaduct, each with two assembly and around 100 part-list drawings. Overall, there will be over 7,000 drawings just for the viaduct. Proof checking and verifying each of these on site significantly slows down the actual erection and construction. However, the use of BIM has reduced these design errors and improved productivity.Intelligent managementThe BIM used includes an extensive range of connections with its automated clash-checking efficiently exposing conflicts in the structure. It also executes reinforced concrete, braces, elements and block constructions. The bridge geometry has been measured several times and the results compared with the model. In the pre-construction stage, the software helped the contractor understand the owner’s vision behind the design. During the planning stage, it helped in procurement and formulating better construction processes. During site management, it helped in centralising essential planning and management data. As the bridge is logistically challenging, BIM has helped organise the plate material for better logistics, besides getting the plans approved by local authorities with the accurate model.Comprehensive design toolThe bridge uses 3D visualisation, which reduces design errors and enhances labour productivity. The process of visualisation, CAD tools and design methods have been integrated into the process. One can also connect models directly to 3D site measurements, which eliminates transfer of errors owing to human factors and data format conversions.Major risksDespite recent developments, adopting a single BIM technology in any project involves two major risks. The first includes lack of collaboration on the part of the project team and second, the lack of confidence of users in its accuracy. Thus, it is essential to recognise the value of BIM as a source of intelligent information and train industry players to use the technology. Reluctance on the part of some customers to adopt this technology could be owing to switching costs and uncertainty about its value-addition and services provided. Project teams usually rely on purpose-built models customised for specific project needs. In case of an owner, contractor and designer, the biggest problem lies in adopting new processes.Lack of trainingImplementation of BIM in India also lacks proper training facilities. Most firms still use 2D drafting tools as they do not wish to invest time in training their staff. Also, very few wish to pay the extra cost for digital models of their project. We have started BIM educational training hubs across several cities with an aim to train over 500 engineers by 2012.Myths dispelledMost firms believe that BIM results in loss of productivity during the transition period. But, these are just initial losses that can be compensated for in the longer run. In fact, BIM integrates seamlessly with current ways of working. The present systems need supporting technologies to aggregate information across different app­lications, thus transforming the industry’s design and construction pro­­cesses.Cost savingsThe standard way to calculate the Return on Investment (ROI) of any technology is to compare its cost and effect on productivity against the first year’s labour and training costs. In case of BIM, the results can vary from 20 to 60 per cent depending on the size of a company and the type of projects it executes. Although cost and labour savings are easy to calculate, most companies do not wish to publish figures for their BIM-generated revenue as it is difficult to establish accurate metrics for that. Customers can expect to save almost 30-40 per cent costs by using this technology in their projects.However, this may vary depending on various factors such as project size and complexity, time, and available resources, etc.In sum, BIM represents a breakthrough in building de­sign technology. The market for BIM software and services, though still nascent in India, is evolving rapidly. As building green be­comes increasingly imperative, the adoption of BIM tools and practices will become a priority as they can significantly affect the efficient use of scarce and valuable resources.BIM advantage!The technology includes both monitoring as well as wind effect and vibration studies in bridges designed in steel and concrete along with new technologies like laser scanning. The 3D model can be used to enter output measurements and dimensions and with the means of laser scanning creates a source model to accelerate the renovation of old bridges.About the author:Nirmalya Chatterjee, COO, Tekla India, is a graduate in engineering and management. He has served the company for the past six years and is the founder member of its India operations. Chatterjee has over 18 years of experience in the industry and is involved in promoting the BIM technology solution ‘Tekla Structures’, which addresses the complete lifecycle needs of construction projects.If you have an innovative technology to share, write in at feedback@ASAPPmedia.com

Next Story
Real Estate

CRDA Approves Rs 17.32 Bn Tenders for Housing and Infra

The Capital Region Development Authority (CRDA), during its forty-seventh meeting chaired by Chief Minister N. Chandrababu Naidu, approved tenders worth Rs 17.32 billion to develop key infrastructure in Amaravati’s core capital area.Municipal Administration and Urban Development Minister Ponguru Narayana announced that Rs 5.14 billion was sanctioned for completing gazetted officers’ towers initiated between 2014 and 2019. In addition, Rs 1.94 billion was approved for external infrastructure, Rs 5.07 billion for nine towers for non-gazetted employees, and Rs 5.17 billion for twelve new towe..

Next Story
Real Estate

Prestige Estates Nets Rs 30 Bn in NCR Debut Launch

Prestige Estates Projects Limited has recorded sales of over Rs 30 billion within one week of launching its first residential project in the National Capital Region (NCR). The project, The Prestige City, located in Indirapuram Extension on National Highway twenty-four, sold one thousand two hundred units during its initial launch phase.This marks the Bengaluru-based developer’s maiden entry into NCR’s residential real estate market. The company attributes the strong response to brand trust, strategic location, and rising demand for premium, planned communities.The launch covered two reside..

Next Story
Infrastructure Transport

Palakkad Railway Division Upgrades Turnouts for Safety

The Southern Railway’s Palakkad Division has implemented a series of infrastructure upgrades to enhance train safety and operational efficiency. Over the past one year, the division has replaced one hundred thirty-three ageing fifty-two kilogram turnouts with robust sixty kilogram Thick Web Switches, engineered for high-speed durability and increased strength.Seventy-seven track layouts were corrected using advanced computer-based geometry solutions, involving precise longitudinal and lateral alignment with the aid of the T-28 Track Relaying Machine. These corrections improve track stability..

Advertisement

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Advertisement

Talk to us?