343 infra projects witness estimated cost exceeding
ECONOMY & POLICY

343 infra projects witness estimated cost exceeding

Overruns of more than 4.5 Trillion have occurred in 343 infrastructure projects across the country. According to news agency PTI, each project requires an investment of more than 1500 million, and 835 projects have been delayed as a result of the overrun.

The total cost of carrying out the 1,438 projects was estimated to be Rs 20,35,794.75 billion. However, the project's completion cost is expected to be around Rs 24,86,069.52 billion, which is 22.12% higher than the original estimate, according to a December 2022 report cited by PTI. It was discovered that of the 835 projects that were delayed, 160 had overall delays ranging from 1 to 12 months, while 130 had delays of 61 months or more. The government has delayed 134 infrastructure projects for 13-24 months and 411 projects for 25-60 months. or 342 projects, neither the year of commissioning nor the estimated gestation period have been disclosed.

According to the implementing agencies, cost overruns were caused by a variety of factors, including delays in acquiring land and obtaining environmental and forest clearances. Other factors that contributed to the delays included the late submission of project financing documents, a change in scope, the equipment supply and tendering process, and law and order issues.

Furthermore, neither the year in which the project began nor its tentative timeline have been reported for 342 projects. The report also blamed the delays in project implementation on the implementation of COVID-19 lockdowns.

It was also reported that the companies in charge of the projects were failing to report revised cost estimates and project completion dates. This suggests that cost and time overrun figures are being underreported.

Overruns of more than 4.5 Trillion have occurred in 343 infrastructure projects across the country. According to news agency PTI, each project requires an investment of more than 1500 million, and 835 projects have been delayed as a result of the overrun. The total cost of carrying out the 1,438 projects was estimated to be Rs 20,35,794.75 billion. However, the project's completion cost is expected to be around Rs 24,86,069.52 billion, which is 22.12% higher than the original estimate, according to a December 2022 report cited by PTI. It was discovered that of the 835 projects that were delayed, 160 had overall delays ranging from 1 to 12 months, while 130 had delays of 61 months or more. The government has delayed 134 infrastructure projects for 13-24 months and 411 projects for 25-60 months. or 342 projects, neither the year of commissioning nor the estimated gestation period have been disclosed. According to the implementing agencies, cost overruns were caused by a variety of factors, including delays in acquiring land and obtaining environmental and forest clearances. Other factors that contributed to the delays included the late submission of project financing documents, a change in scope, the equipment supply and tendering process, and law and order issues. Furthermore, neither the year in which the project began nor its tentative timeline have been reported for 342 projects. The report also blamed the delays in project implementation on the implementation of COVID-19 lockdowns. It was also reported that the companies in charge of the projects were failing to report revised cost estimates and project completion dates. This suggests that cost and time overrun figures are being underreported.

Next Story
Infrastructure Transport

Smart Roads, Smarter India

India’s infrastructure boom is not only about laying more kilometres of highways – it’s about building them smarter, safer and more sustainably. From drones mapping fragile Himalayan slopes to 3D machine-controlled graders reducing human error, technology is steadily reshaping the way projects are planned and executed. Yet, the journey towards digitisation remains complex, demanding not just capital but also coordination, training and vision.Until recently, engineers largely depended on Survey of India toposheets and traditional survey methods like total stations or DGPS to prepare detai..

Next Story
Real Estate

What Does DCPR 2034 Mean?

The Maharashtra government has eased approval norms for high-rise buildings under DCPR 2034, enabling the municipal commissioner to sanction projects up to 180 m on large plots. This change is expected to streamline approvals, reduce procedural delays and accelerate redevelopment, drawing reactions from developers, planners and industry experts about its implications for Mumbai’s vertical growth.Under the revised DCPR 2034 rules, buildings on plots of 2,000 sq m or more can now be approved up to 180 m by the municipal commissioner, provided structural and geotechnical reports are certified b..

Next Story
Infrastructure Urban

Driving Infrastructure Forward with Trustworthy AI

At its Year in Infrastructure 2025 conference in Amsterdam, Bentley Systems reaffirmed its vision for trustworthy AI and connected digital ecosystems shaping the future of infrastructure engineering. The company unveiled AI-powered design applications and Bentley Infrastructure Cloud Connect, a unifying platform connecting data, workflows and professionals across the project lifecycle.“AI is poised to transform infrastructure,” said Nicholas Cumins, CEO, Bentley Systems. “At Bentley, our vision is for AI to empower engineers – not replace them. Trustworthy AI, built on infrastruct..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Talk to us?