+
343 infra projects witness estimated cost exceeding
ECONOMY & POLICY

343 infra projects witness estimated cost exceeding

Overruns of more than 4.5 Trillion have occurred in 343 infrastructure projects across the country. According to news agency PTI, each project requires an investment of more than 1500 million, and 835 projects have been delayed as a result of the overrun.

The total cost of carrying out the 1,438 projects was estimated to be Rs 20,35,794.75 billion. However, the project's completion cost is expected to be around Rs 24,86,069.52 billion, which is 22.12% higher than the original estimate, according to a December 2022 report cited by PTI. It was discovered that of the 835 projects that were delayed, 160 had overall delays ranging from 1 to 12 months, while 130 had delays of 61 months or more. The government has delayed 134 infrastructure projects for 13-24 months and 411 projects for 25-60 months. or 342 projects, neither the year of commissioning nor the estimated gestation period have been disclosed.

According to the implementing agencies, cost overruns were caused by a variety of factors, including delays in acquiring land and obtaining environmental and forest clearances. Other factors that contributed to the delays included the late submission of project financing documents, a change in scope, the equipment supply and tendering process, and law and order issues.

Furthermore, neither the year in which the project began nor its tentative timeline have been reported for 342 projects. The report also blamed the delays in project implementation on the implementation of COVID-19 lockdowns.

It was also reported that the companies in charge of the projects were failing to report revised cost estimates and project completion dates. This suggests that cost and time overrun figures are being underreported.

Overruns of more than 4.5 Trillion have occurred in 343 infrastructure projects across the country. According to news agency PTI, each project requires an investment of more than 1500 million, and 835 projects have been delayed as a result of the overrun. The total cost of carrying out the 1,438 projects was estimated to be Rs 20,35,794.75 billion. However, the project's completion cost is expected to be around Rs 24,86,069.52 billion, which is 22.12% higher than the original estimate, according to a December 2022 report cited by PTI. It was discovered that of the 835 projects that were delayed, 160 had overall delays ranging from 1 to 12 months, while 130 had delays of 61 months or more. The government has delayed 134 infrastructure projects for 13-24 months and 411 projects for 25-60 months. or 342 projects, neither the year of commissioning nor the estimated gestation period have been disclosed. According to the implementing agencies, cost overruns were caused by a variety of factors, including delays in acquiring land and obtaining environmental and forest clearances. Other factors that contributed to the delays included the late submission of project financing documents, a change in scope, the equipment supply and tendering process, and law and order issues. Furthermore, neither the year in which the project began nor its tentative timeline have been reported for 342 projects. The report also blamed the delays in project implementation on the implementation of COVID-19 lockdowns. It was also reported that the companies in charge of the projects were failing to report revised cost estimates and project completion dates. This suggests that cost and time overrun figures are being underreported.

Next Story
Infrastructure Urban

Eicher Delivers First 13.5 m Electric Intercity Sleeper Bus

Eicher Trucks & Buses, a business unit of VE Commercial Vehicles Ltd., has recently delivered its first 13.5 m electric intercity sleeper bus, marking a key milestone in India’s long-distance electric mobility segment. The first bus is being operated by LeafyBus, with plans to deploy 35 buses by March 2026 across high-demand intercity corridors in North India.The initial deployment will cover routes such as Delhi–Dehradun and Delhi–Lucknow, supporting LeafyBus’ expansion across environmentally sensitive and high-density travel corridors.Commenting on the partnership, Suresh Chettia..

Next Story
Infrastructure Urban

HCSS Showcases Unified Construction Platform at CONEXPO 2026

HCSS will recently present the next evolution of its connected construction management platform at CONEXPO-CON/AGG 2026, bringing together construction workflows, data and teams on a single platform across the entire project lifecycle. The event will be held from 3–7 March 2026 in Las Vegas, Nevada. HCSS will host two booths at the show, demonstrating how its integrated software ecosystem enables seamless collaboration between the office, field and shop, from bid stage through to project closeout. Steve McGough, President and CEO, HCSS, said, “For 40 years, we’ve done everything within..

Next Story
Building Material

Berger Paints Q3 Profit Declines Despite Volume Growth

Berger Paints India has reported a mixed performance for the quarter ended 31 December 2025, with healthy volume growth and margin improvement offset by softer demand conditions and cost pressures. On a consolidated basis, revenue from operations for the quarter stood at Rs 29,840 million, compared to Rs 29,751 million in the corresponding quarter last year, reflecting a marginal increase of 0.3 per cent. EBITDA (excluding other income) was Rs 4,710 million, slightly lower than Rs 4,717 million a year earlier. Net profit declined by 8.3 per cent to Rs 2,713 million from Rs 2,960 million. Sta..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Open In App