343 infra projects witness estimated cost exceeding
ECONOMY & POLICY

343 infra projects witness estimated cost exceeding

Overruns of more than 4.5 Trillion have occurred in 343 infrastructure projects across the country. According to news agency PTI, each project requires an investment of more than 1500 million, and 835 projects have been delayed as a result of the overrun.

The total cost of carrying out the 1,438 projects was estimated to be Rs 20,35,794.75 billion. However, the project's completion cost is expected to be around Rs 24,86,069.52 billion, which is 22.12% higher than the original estimate, according to a December 2022 report cited by PTI. It was discovered that of the 835 projects that were delayed, 160 had overall delays ranging from 1 to 12 months, while 130 had delays of 61 months or more. The government has delayed 134 infrastructure projects for 13-24 months and 411 projects for 25-60 months. or 342 projects, neither the year of commissioning nor the estimated gestation period have been disclosed.

According to the implementing agencies, cost overruns were caused by a variety of factors, including delays in acquiring land and obtaining environmental and forest clearances. Other factors that contributed to the delays included the late submission of project financing documents, a change in scope, the equipment supply and tendering process, and law and order issues.

Furthermore, neither the year in which the project began nor its tentative timeline have been reported for 342 projects. The report also blamed the delays in project implementation on the implementation of COVID-19 lockdowns.

It was also reported that the companies in charge of the projects were failing to report revised cost estimates and project completion dates. This suggests that cost and time overrun figures are being underreported.

Overruns of more than 4.5 Trillion have occurred in 343 infrastructure projects across the country. According to news agency PTI, each project requires an investment of more than 1500 million, and 835 projects have been delayed as a result of the overrun. The total cost of carrying out the 1,438 projects was estimated to be Rs 20,35,794.75 billion. However, the project's completion cost is expected to be around Rs 24,86,069.52 billion, which is 22.12% higher than the original estimate, according to a December 2022 report cited by PTI. It was discovered that of the 835 projects that were delayed, 160 had overall delays ranging from 1 to 12 months, while 130 had delays of 61 months or more. The government has delayed 134 infrastructure projects for 13-24 months and 411 projects for 25-60 months. or 342 projects, neither the year of commissioning nor the estimated gestation period have been disclosed. According to the implementing agencies, cost overruns were caused by a variety of factors, including delays in acquiring land and obtaining environmental and forest clearances. Other factors that contributed to the delays included the late submission of project financing documents, a change in scope, the equipment supply and tendering process, and law and order issues. Furthermore, neither the year in which the project began nor its tentative timeline have been reported for 342 projects. The report also blamed the delays in project implementation on the implementation of COVID-19 lockdowns. It was also reported that the companies in charge of the projects were failing to report revised cost estimates and project completion dates. This suggests that cost and time overrun figures are being underreported.

Next Story
Infrastructure Transport

JNPA Becomes First Indian Port to Cross 10 Million TEU Capacity

The Jawaharlal Nehru Port Authority (JNPA), located at Uran in Navi Mumbai, has become the first port in India to achieve over 10 million TEUs (twenty-foot equivalent units) in container handling capacity.With the recent expansion, the port now operates five container terminals with a combined capacity of 10.4 million TEUs, alongside two liquid and two general cargo terminals.Handling more than half of India’s container traffic, JNPA processed 7.05 million TEUs in 2024 and has moved 15.39 million tonnes of containers and 16.64 million tonnes of total cargo in the first two months of FY 2025â..

Next Story
Infrastructure Transport

Nod for Rs. 36.26 billion Expansion of Pune Metro Line 2

The Union Cabinet has approved the Rs.36.26 billion expansion of Pune Metro Line 2, adding 12.75 km of track and 13 new stations to improve east–west connectivity across the city.The project aims to link Pune’s urban core with rapidly growing suburbs, supporting the city’s rising demand for efficient and sustainable transport solutions. This expansion is part of Corridor 2 of the Pune Metro and includes two key routes: Vanaz to Chandani Chowk (Corridor 2A) and Ramwadi to Wagholi/Vitthalwadi (Corridor 2B).It will connect residential, IT, and educational hubs in areas such as Bavdhan, Koth..

Next Story
Infrastructure Transport

Assembly begins for ‘Nayak’ TBM on Thane– Borivali Twin Tunnel Project

The assembly of ‘Nayak’, the first of four Tunnel Boring Machines (TBMs) for the Thane–Borivali Twin Tube Tunnel Project, has commenced at the Thane site. Built by German firm Herrenknecht AG and deployed by Megha Engineering & Infrastructure (MEIL), the TBM marks a key milestone in Mumbai’s ambitious 11.8-km underground road corridor beneath Sanjay Gandhi National Park.The twin tunnels will reduce the Thane–Borivali travel distance by 12 km and decongest Thane Ghodbunder Road. ‘Nayak’, with a 13.2-metre diameter, is designed to bore through challenging geological conditions ..

Advertisement

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Advertisement

Talk to us?