343 infra projects witness estimated cost exceeding
ECONOMY & POLICY

343 infra projects witness estimated cost exceeding

Overruns of more than 4.5 Trillion have occurred in 343 infrastructure projects across the country. According to news agency PTI, each project requires an investment of more than 1500 million, and 835 projects have been delayed as a result of the overrun.

The total cost of carrying out the 1,438 projects was estimated to be Rs 20,35,794.75 billion. However, the project's completion cost is expected to be around Rs 24,86,069.52 billion, which is 22.12% higher than the original estimate, according to a December 2022 report cited by PTI. It was discovered that of the 835 projects that were delayed, 160 had overall delays ranging from 1 to 12 months, while 130 had delays of 61 months or more. The government has delayed 134 infrastructure projects for 13-24 months and 411 projects for 25-60 months. or 342 projects, neither the year of commissioning nor the estimated gestation period have been disclosed.

According to the implementing agencies, cost overruns were caused by a variety of factors, including delays in acquiring land and obtaining environmental and forest clearances. Other factors that contributed to the delays included the late submission of project financing documents, a change in scope, the equipment supply and tendering process, and law and order issues.

Furthermore, neither the year in which the project began nor its tentative timeline have been reported for 342 projects. The report also blamed the delays in project implementation on the implementation of COVID-19 lockdowns.

It was also reported that the companies in charge of the projects were failing to report revised cost estimates and project completion dates. This suggests that cost and time overrun figures are being underreported.

"Join industry leaders at RAHSTA Expo, India's premier platform for roads, highways and traffic infrastructure. Register now to explore innovations, network with experts and shape the future of mobility."

Overruns of more than 4.5 Trillion have occurred in 343 infrastructure projects across the country. According to news agency PTI, each project requires an investment of more than 1500 million, and 835 projects have been delayed as a result of the overrun. The total cost of carrying out the 1,438 projects was estimated to be Rs 20,35,794.75 billion. However, the project's completion cost is expected to be around Rs 24,86,069.52 billion, which is 22.12% higher than the original estimate, according to a December 2022 report cited by PTI. It was discovered that of the 835 projects that were delayed, 160 had overall delays ranging from 1 to 12 months, while 130 had delays of 61 months or more. The government has delayed 134 infrastructure projects for 13-24 months and 411 projects for 25-60 months. or 342 projects, neither the year of commissioning nor the estimated gestation period have been disclosed. According to the implementing agencies, cost overruns were caused by a variety of factors, including delays in acquiring land and obtaining environmental and forest clearances. Other factors that contributed to the delays included the late submission of project financing documents, a change in scope, the equipment supply and tendering process, and law and order issues. Furthermore, neither the year in which the project began nor its tentative timeline have been reported for 342 projects. The report also blamed the delays in project implementation on the implementation of COVID-19 lockdowns. It was also reported that the companies in charge of the projects were failing to report revised cost estimates and project completion dates. This suggests that cost and time overrun figures are being underreported.

Next Story
Real Estate

Pecan Realty Completes Rs 1.5 Billion Transactions

Pecan Realty has recently completed four institutional transactions worth over Rs 1.5 billion over the past two years, strengthening its position as an execution-led real estate platform. The deals include resolution-led acquisitions, structured finance transactions and capital partnerships across its development portfolio.The transactions covered acquisitions through the National Company Law Tribunal process and helped provide repayment or exits to both private and public sector lenders. The company said the deals demonstrate its ability to resolve complex project situations, work with instit..

Next Story
Real Estate

SNN Estates Expands North Bengaluru Housing Project

SNN Estates has announced an expansion of its SNN Estates Felicity residential project in North Bengaluru following strong buyer demand, with 75 per cent of the first-phase inventory sold within three days of launch.The developer will add 76 apartments in the new phase, taking the project's estimated revenue potential to around Rs 1,000 crore upon completion of Phase 2.Spread across 6.5 acres in Rachenahalli, near Manyata Tech Park, the project comprises 604 apartments in 1.5, 2, 2.5, 3 and 4 BHK configurations. The development includes a 50,000-sq-ft clubhouse with amenities such as sports co..

Next Story
Infrastructure Urban

SCG Drives ASEAN Industrial Transformation Strategy

SCG is strengthening its focus on ASEAN as a key growth region by advancing industrial transformation, enhancing competitiveness and building resilient regional value chains. Thammasak Sethaudom, President and Chief Executive Officer, SCG, highlighted the need for industries to continuously develop capabilities, strengthen resilience and deepen regional cooperation to achieve sustainable long-term growth.SCG views ASEAN as an important growth engine alongside China, supported by favourable demographics, trade connectivity and investment flows. With ASEAN’s GDP projected to grow by around 4.7..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement