343 infra projects witness estimated cost exceeding
ECONOMY & POLICY

343 infra projects witness estimated cost exceeding

Overruns of more than 4.5 Trillion have occurred in 343 infrastructure projects across the country. According to news agency PTI, each project requires an investment of more than 1500 million, and 835 projects have been delayed as a result of the overrun.

The total cost of carrying out the 1,438 projects was estimated to be Rs 20,35,794.75 billion. However, the project's completion cost is expected to be around Rs 24,86,069.52 billion, which is 22.12% higher than the original estimate, according to a December 2022 report cited by PTI. It was discovered that of the 835 projects that were delayed, 160 had overall delays ranging from 1 to 12 months, while 130 had delays of 61 months or more. The government has delayed 134 infrastructure projects for 13-24 months and 411 projects for 25-60 months. or 342 projects, neither the year of commissioning nor the estimated gestation period have been disclosed.

According to the implementing agencies, cost overruns were caused by a variety of factors, including delays in acquiring land and obtaining environmental and forest clearances. Other factors that contributed to the delays included the late submission of project financing documents, a change in scope, the equipment supply and tendering process, and law and order issues.

Furthermore, neither the year in which the project began nor its tentative timeline have been reported for 342 projects. The report also blamed the delays in project implementation on the implementation of COVID-19 lockdowns.

It was also reported that the companies in charge of the projects were failing to report revised cost estimates and project completion dates. This suggests that cost and time overrun figures are being underreported.

Overruns of more than 4.5 Trillion have occurred in 343 infrastructure projects across the country. According to news agency PTI, each project requires an investment of more than 1500 million, and 835 projects have been delayed as a result of the overrun. The total cost of carrying out the 1,438 projects was estimated to be Rs 20,35,794.75 billion. However, the project's completion cost is expected to be around Rs 24,86,069.52 billion, which is 22.12% higher than the original estimate, according to a December 2022 report cited by PTI. It was discovered that of the 835 projects that were delayed, 160 had overall delays ranging from 1 to 12 months, while 130 had delays of 61 months or more. The government has delayed 134 infrastructure projects for 13-24 months and 411 projects for 25-60 months. or 342 projects, neither the year of commissioning nor the estimated gestation period have been disclosed. According to the implementing agencies, cost overruns were caused by a variety of factors, including delays in acquiring land and obtaining environmental and forest clearances. Other factors that contributed to the delays included the late submission of project financing documents, a change in scope, the equipment supply and tendering process, and law and order issues. Furthermore, neither the year in which the project began nor its tentative timeline have been reported for 342 projects. The report also blamed the delays in project implementation on the implementation of COVID-19 lockdowns. It was also reported that the companies in charge of the projects were failing to report revised cost estimates and project completion dates. This suggests that cost and time overrun figures are being underreported.

Next Story
Building Material

Jindal Aluminium Marks 56 Years of Industrial Leadership

Jindal Aluminium Limited has marked its 56th Inception Day, celebrating a legacy built on vision, resilience and manufacturing leadership. Founded in 1968 and incorporated in 1970 by Padma Bhushan Dr Sitaram Jindal, the company has grown into a major force in India’s downstream aluminium sector under the leadership of Pragun Jindal Khaitan.The company is India’s largest manufacturer of aluminium extruded products and the second-largest producer of aluminium flat-rolled products. With a turnover of around Rs 5,500 crore and a workforce of over 4,000, Jindal Aluminium continues to strengthen..

Next Story
Infrastructure Transport

Tunnelling Begins for Thane, Borivali twin tunnel project

Tunnelling work has commenced for the 11.84-km Thane–Borivali Twin Tunnel, set to be India’s longest urban road tunnel, marking a key milestone in Mumbai’s infrastructure development.As per a post shared by Mumbai Metropolitan Region Development Authority on social media platform X, the tunnel boring machine (TBM) ‘Nayak’—the country’s largest single-shield hard rock TBM for an urban tunnel—was launched by Devendra Fadnavis on Tuesday. The event was attended by Eknath Shinde and Sunetra Pawar, among other dignitaries. A second TBM, ‘Arjuna’, is expected to be launched so..

Next Story
Infrastructure Transport

Large Format Store Planned At M G Road Metro Station

M G Road station in Bengaluru is set to host the city’s first large-format commercial and experience space, with planning led by Bangalore Metro Rail Corporation Limited. BMRCL has invited proposals to develop and operate a central business district destination at the Purple?Pink Line interchange. The plan positions the station as a commercial hub designed to serve a broad commuter base across the city. The proposal is part of a broader effort to activate transit nodes commercially. Tender documents set a minimum monthly rental of Rs 0.944 million (mn), inclusive of GST, for the large-format..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement