+
Wolffkran Crane Enables Complex Lavalette Dam Rehabilitation
Equipment

Wolffkran Crane Enables Complex Lavalette Dam Rehabilitation

For the complex rehabilitation of the historic Barrage de Lavalette in the Haute-Loire region of southern France, the construction consortium led by Legendre Génie Civil has deployed a tailored lifting solution from Wolffkran to address extreme space and logistical constraints.

A WOLFF 7534.16 Clear flat-top tower crane, mounted on a WOLFF City Portal 520, has been operational at the site since March 2025. The crane plays a central role in replacing three original floodgates dating back to the 1950s and modernising a fourth gate installed in the 1990s, all of which have experienced significant wear after decades of service.

With a hook height of 20.4 m, a jib length of 40 m and a maximum lifting capacity of 16 tonnes, the crane is being used to install temporary structures and to remove and position both old and new floodgates. The project is particularly challenging as the dam crest measures just 6.7 m in width, significantly restricting crane erection and delivery operations.

According to Wolffkran, wind gusts exceeding 45 km/h further complicated installation works, extending the crane assembly period from the planned two days to around three and a half days.

A key requirement of the project was to keep traffic moving, as a public road runs across the dam and could not be closed for the full construction duration. To address this, the crane was installed on a City Portal solution, allowing vehicles to pass underneath. Load distribution beams were first positioned to spread crane loads evenly across the dam crest, followed by erection of the portal structure and crane using heavy mobile cranes.

While the City Portal enables continued access, road closures are required on weekdays between 9 am and 2 pm, as safety regulations do not permit loads to be slewed over live traffic. All lifting operations are therefore carried out within this restricted window.

One of the most demanding tasks involved removing a floodgate counterweight weighing approximately 51 tonnes. As the concrete block could not be lifted in a single piece, it was cut into sections on site, with individual segments of up to 16 tonnes lifted using the WOLFF crane.

Legendre Génie Civil noted that Wolffkran was the only supplier able to provide a complete package under the site’s constraints, including the crane, portal solution, assembly, operation, service and maintenance. Wolffkran has been involved from the early planning stages and will continue supporting the project throughout the approximately 24-month construction period.

The Lavalette Dam project highlights the role of specialised crane solutions in enabling complex infrastructure rehabilitation works under highly constrained site conditions.

For the complex rehabilitation of the historic Barrage de Lavalette in the Haute-Loire region of southern France, the construction consortium led by Legendre Génie Civil has deployed a tailored lifting solution from Wolffkran to address extreme space and logistical constraints. A WOLFF 7534.16 Clear flat-top tower crane, mounted on a WOLFF City Portal 520, has been operational at the site since March 2025. The crane plays a central role in replacing three original floodgates dating back to the 1950s and modernising a fourth gate installed in the 1990s, all of which have experienced significant wear after decades of service. With a hook height of 20.4 m, a jib length of 40 m and a maximum lifting capacity of 16 tonnes, the crane is being used to install temporary structures and to remove and position both old and new floodgates. The project is particularly challenging as the dam crest measures just 6.7 m in width, significantly restricting crane erection and delivery operations. According to Wolffkran, wind gusts exceeding 45 km/h further complicated installation works, extending the crane assembly period from the planned two days to around three and a half days. A key requirement of the project was to keep traffic moving, as a public road runs across the dam and could not be closed for the full construction duration. To address this, the crane was installed on a City Portal solution, allowing vehicles to pass underneath. Load distribution beams were first positioned to spread crane loads evenly across the dam crest, followed by erection of the portal structure and crane using heavy mobile cranes. While the City Portal enables continued access, road closures are required on weekdays between 9 am and 2 pm, as safety regulations do not permit loads to be slewed over live traffic. All lifting operations are therefore carried out within this restricted window. One of the most demanding tasks involved removing a floodgate counterweight weighing approximately 51 tonnes. As the concrete block could not be lifted in a single piece, it was cut into sections on site, with individual segments of up to 16 tonnes lifted using the WOLFF crane. Legendre Génie Civil noted that Wolffkran was the only supplier able to provide a complete package under the site’s constraints, including the crane, portal solution, assembly, operation, service and maintenance. Wolffkran has been involved from the early planning stages and will continue supporting the project throughout the approximately 24-month construction period. The Lavalette Dam project highlights the role of specialised crane solutions in enabling complex infrastructure rehabilitation works under highly constrained site conditions.

Related Stories

Gold Stories

Next Story
Infrastructure Urban

Assam Gets Approval For 350,000 PMAY Homes

Assam Chief Minister Himanta Biswa Sarma met Union Agriculture Minister Shivraj Singh Chouhan in New Delhi, where the minister handed an approval document for 310,000 new homes under the Pradhan Mantri Awas Yojana. The chief minister subsequently posted on X expressing gratitude and noting that the minister had formally handed approval for 380,000 homes as well. The release and the social media post contained varying figures, with broader references to 350,000 homes reported in some summaries. The approvals carry central assistance equivalent to Rs 50 billion (bn), corresponding to the five th..

Next Story
Infrastructure Urban

KPIGreen Achieves Highest Energised Capacity of 630+ MW DC

KPI Green Energy energised more than 630 MW DC of capacity in the June to August quarter, marking the highest quarterly addition in the company's history. The capacity was brought online across its Independent Power Producer (IPP) and Engineering, Procurement and Construction (EPC) businesses. The company said the achievement reflected the scale, speed and consistency of its project execution engine. The firm described the quarter as a material operational milestone since its founding. The milestone covers a diversified mix of IPP assets and projects executed under the EPC vertical, spanning u..

Next Story
Infrastructure Energy

Adani Energy Solutions Wins Rs 47 bn Maharashtra Transmission Project

Adani Energy Solutions has won a transmission contract in Maharashtra valued at Rs 47 billion (Rs 47 bn) to evacuate 4,500 megawatt (MW) of renewable and storage power. The company informed exchanges that the project will facilitate pumped storage potential near Satara and strengthen the inter-regional corridor between the Western and Southern grids. The award follows a competitive bidding process and will support renewable energy evacuation to major load centres in the state. The scope includes establishment of a 765/400 kV substation at Satara, construction of a Kolhapur-Satara 765 kV double..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

SPECIAL OFFER
QR Code