+
Wolffkran Crane Enables Complex Lavalette Dam Rehabilitation
Equipment

Wolffkran Crane Enables Complex Lavalette Dam Rehabilitation

For the complex rehabilitation of the historic Barrage de Lavalette in the Haute-Loire region of southern France, the construction consortium led by Legendre Génie Civil has deployed a tailored lifting solution from Wolffkran to address extreme space and logistical constraints.

A WOLFF 7534.16 Clear flat-top tower crane, mounted on a WOLFF City Portal 520, has been operational at the site since March 2025. The crane plays a central role in replacing three original floodgates dating back to the 1950s and modernising a fourth gate installed in the 1990s, all of which have experienced significant wear after decades of service.

With a hook height of 20.4 m, a jib length of 40 m and a maximum lifting capacity of 16 tonnes, the crane is being used to install temporary structures and to remove and position both old and new floodgates. The project is particularly challenging as the dam crest measures just 6.7 m in width, significantly restricting crane erection and delivery operations.

According to Wolffkran, wind gusts exceeding 45 km/h further complicated installation works, extending the crane assembly period from the planned two days to around three and a half days.

A key requirement of the project was to keep traffic moving, as a public road runs across the dam and could not be closed for the full construction duration. To address this, the crane was installed on a City Portal solution, allowing vehicles to pass underneath. Load distribution beams were first positioned to spread crane loads evenly across the dam crest, followed by erection of the portal structure and crane using heavy mobile cranes.

While the City Portal enables continued access, road closures are required on weekdays between 9 am and 2 pm, as safety regulations do not permit loads to be slewed over live traffic. All lifting operations are therefore carried out within this restricted window.

One of the most demanding tasks involved removing a floodgate counterweight weighing approximately 51 tonnes. As the concrete block could not be lifted in a single piece, it was cut into sections on site, with individual segments of up to 16 tonnes lifted using the WOLFF crane.

Legendre Génie Civil noted that Wolffkran was the only supplier able to provide a complete package under the site’s constraints, including the crane, portal solution, assembly, operation, service and maintenance. Wolffkran has been involved from the early planning stages and will continue supporting the project throughout the approximately 24-month construction period.

The Lavalette Dam project highlights the role of specialised crane solutions in enabling complex infrastructure rehabilitation works under highly constrained site conditions.

For the complex rehabilitation of the historic Barrage de Lavalette in the Haute-Loire region of southern France, the construction consortium led by Legendre Génie Civil has deployed a tailored lifting solution from Wolffkran to address extreme space and logistical constraints. A WOLFF 7534.16 Clear flat-top tower crane, mounted on a WOLFF City Portal 520, has been operational at the site since March 2025. The crane plays a central role in replacing three original floodgates dating back to the 1950s and modernising a fourth gate installed in the 1990s, all of which have experienced significant wear after decades of service. With a hook height of 20.4 m, a jib length of 40 m and a maximum lifting capacity of 16 tonnes, the crane is being used to install temporary structures and to remove and position both old and new floodgates. The project is particularly challenging as the dam crest measures just 6.7 m in width, significantly restricting crane erection and delivery operations. According to Wolffkran, wind gusts exceeding 45 km/h further complicated installation works, extending the crane assembly period from the planned two days to around three and a half days. A key requirement of the project was to keep traffic moving, as a public road runs across the dam and could not be closed for the full construction duration. To address this, the crane was installed on a City Portal solution, allowing vehicles to pass underneath. Load distribution beams were first positioned to spread crane loads evenly across the dam crest, followed by erection of the portal structure and crane using heavy mobile cranes. While the City Portal enables continued access, road closures are required on weekdays between 9 am and 2 pm, as safety regulations do not permit loads to be slewed over live traffic. All lifting operations are therefore carried out within this restricted window. One of the most demanding tasks involved removing a floodgate counterweight weighing approximately 51 tonnes. As the concrete block could not be lifted in a single piece, it was cut into sections on site, with individual segments of up to 16 tonnes lifted using the WOLFF crane. Legendre Génie Civil noted that Wolffkran was the only supplier able to provide a complete package under the site’s constraints, including the crane, portal solution, assembly, operation, service and maintenance. Wolffkran has been involved from the early planning stages and will continue supporting the project throughout the approximately 24-month construction period. The Lavalette Dam project highlights the role of specialised crane solutions in enabling complex infrastructure rehabilitation works under highly constrained site conditions.

Next Story
Building Material

NITI Aayog Unveils Cement Decarbonisation Roadmap

NITI Aayog has released a sector-specific decarbonisation roadmap for cement as part of three green transition reports covering cement, aluminium and MSMEs. The report projects cement production rising to around 2,100 million tonnes by 2070 from 391 million tonnes in 2023, while targeting a reduction in carbon intensity to 0.09–0.13 tCO₂e per tonne. It recommends clinker substitution, refuse-derived fuels, CCUS adoption and carbon trading mechanisms to enable deep decarbonisation. ..

Next Story
Technology

Genesys Launches Advanced GeoRadar System

Genesys International Corporation has launched an advanced Ground Penetrating Radar (GPR) solution from IDS GeoRadar for underground utility mapping in India. The system uses patented Equalised Scrambling Technology (EST) and Wide/Multi-Array Antenna Technology to deliver high-resolution three-dimensional imaging of subsurface infrastructure. The technology enables the detection and mapping of buried assets such as water pipelines, sewer networks, telecom cables and power lines. By providing detailed subsurface insights, the system aims to help urban authorities and infrastructure developers ..

Next Story
Infrastructure Urban

Hindustan Zinc Partners Virginia Tech to Boost Silver Recovery

Hindustan Zinc Limited recently signed a Memorandum of Understanding (MoU) with Virginia Tech to advance research aimed at improving silver recovery across its lead–zinc (Pb–Zn) concentrators. The collaboration will focus on refining flotation techniques and optimising reagent usage to improve concentrate quality and operational efficiency at processing plants.Virginia Tech, based in Blacksburg, Virginia, is globally recognised for its expertise in mining engineering, mineral processing and applied metallurgical research. Through this partnership, Hindustan Zinc will leverage global resear..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Open In App