417 infrastructure projects in India face Rs 4.77 tn cost overrun
ECONOMY & POLICY

417 infrastructure projects in India face Rs 4.77 tn cost overrun

An official report reveals that in September of this year, 417 infrastructure projects, each requiring an investment of Rs 1.5 billion or more, experienced cost overruns exceed Rs 4.77 trillion. The Ministry of Statistics and Programme Implementation, overseeing projects valued at Rs 1.5 billion and above, reported that out of 1,763 projects, 417 faced cost overruns, and 842 projects encountered delays.

The initial cost of implementing the 1,763 projects was Rs 24,86,4027 million, with the projected completion cost expected to reach Rs 29,64,3451.3 million, indicating an overall cost overrun of Rs 4,77,9424.3 million (19.22% of the original cost), as per the ministry's September 2023 report.

As of September 2023, the expenditure on these projects amounted to Rs 15,44,6006.7 million, representing 52.11% of the anticipated project cost. The report noted a decrease in the number of delayed projects to 617 when considering the latest completion schedule. Additionally, 298 projects lacked reported commissioning years or tentative gestation periods.

Among the 842 delayed projects, 194 experienced delays of 1-12 months, 190 were delayed for 13-24 months, 323 projects faced delays of 25-60 months, and 123 projects were delayed for more than 60 months. The average time overrun for these 842 delayed projects was 36.94 months. Reasons for time overruns cited by project implementing agencies included delays in land acquisition, obtaining forest and environment clearances, and insufficient infrastructure support and linkages. Other factors included delays in project financing tie-ups, finalisation of detailed engineering, changes in scope, tendering, ordering and equipment supply, as well as law and order problems.

The report highlighted state-wise lockdowns due to COVID-19 in 2020 and 2021 as contributing to project implementation delays. Furthermore, it observed that project executing agencies often fail to report revised cost estimates and commissioning schedules for many projects, suggesting potential underreporting of time and cost overrun figures.

An official report reveals that in September of this year, 417 infrastructure projects, each requiring an investment of Rs 1.5 billion or more, experienced cost overruns exceed Rs 4.77 trillion. The Ministry of Statistics and Programme Implementation, overseeing projects valued at Rs 1.5 billion and above, reported that out of 1,763 projects, 417 faced cost overruns, and 842 projects encountered delays. The initial cost of implementing the 1,763 projects was Rs 24,86,4027 million, with the projected completion cost expected to reach Rs 29,64,3451.3 million, indicating an overall cost overrun of Rs 4,77,9424.3 million (19.22% of the original cost), as per the ministry's September 2023 report. As of September 2023, the expenditure on these projects amounted to Rs 15,44,6006.7 million, representing 52.11% of the anticipated project cost. The report noted a decrease in the number of delayed projects to 617 when considering the latest completion schedule. Additionally, 298 projects lacked reported commissioning years or tentative gestation periods. Among the 842 delayed projects, 194 experienced delays of 1-12 months, 190 were delayed for 13-24 months, 323 projects faced delays of 25-60 months, and 123 projects were delayed for more than 60 months. The average time overrun for these 842 delayed projects was 36.94 months. Reasons for time overruns cited by project implementing agencies included delays in land acquisition, obtaining forest and environment clearances, and insufficient infrastructure support and linkages. Other factors included delays in project financing tie-ups, finalisation of detailed engineering, changes in scope, tendering, ordering and equipment supply, as well as law and order problems. The report highlighted state-wise lockdowns due to COVID-19 in 2020 and 2021 as contributing to project implementation delays. Furthermore, it observed that project executing agencies often fail to report revised cost estimates and commissioning schedules for many projects, suggesting potential underreporting of time and cost overrun figures.

Next Story
Infrastructure Urban

Implementation Status of Jal Jeevan Mission

Since August 2019 the Government has implemented Jal Jeevan Mission to provide assured potable water through household tap connections in rural India. At the start of the mission only 32.3 million (mn) rural households, representing 16.7 per cent, were reported to have tap water connections. States and union territories have reported that 125.8 mn additional rural households have since been provided with tap connections. As a result, of about 193.6 mn rural households roughly 158.2 mn, or 81.71 per cent, are reported to have tap water supply at home.\n\nThe State, district and village level st..

Next Story
Infrastructure Urban

Jal Jeevan Mission Reaches Eighty One Per Cent Rural Coverage

The Government reported substantial progress under the Jal Jeevan Mission, launched in August 2019 to provide tap water to every rural household. At launch only 32.3 million (mn) rural households had tap connections and states and Union territories reported provision of 125.8 mn additional households by March 2026. Consequently, out of about 193.6 mn rural households around 158.2 mn, or 81.71 per cent, are reported to have tap water at home. The Finance Minister announced extension of the mission until 2028 in the 2025-26 budget speech. The Swachh Bharat Mission Grameen, launched in October 20..

Next Story
Infrastructure Urban

Empowering Local Governance for Sustainable Rural Water Supply

The Ministry of Jal Shakti has aligned the Jal Jeevan Mission (JJM) with the 73rd Amendment to strengthen village level planning and community ownership of water supply. Gram Panchayats, village water and sanitation committees and Pani Samitis are to plan, implement, manage and maintain piped water systems, with gram sabha processes formalising handover and oversight. Implementation support agencies including non government organisations, community based organisations and self help groups have been empanelled to train local committees and promote women participation. Under JJM, the department ..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement