417 infrastructure projects in India face Rs 4.77 tn cost overrun
ECONOMY & POLICY

417 infrastructure projects in India face Rs 4.77 tn cost overrun

An official report reveals that in September of this year, 417 infrastructure projects, each requiring an investment of Rs 1.5 billion or more, experienced cost overruns exceed Rs 4.77 trillion. The Ministry of Statistics and Programme Implementation, overseeing projects valued at Rs 1.5 billion and above, reported that out of 1,763 projects, 417 faced cost overruns, and 842 projects encountered delays.

The initial cost of implementing the 1,763 projects was Rs 24,86,4027 million, with the projected completion cost expected to reach Rs 29,64,3451.3 million, indicating an overall cost overrun of Rs 4,77,9424.3 million (19.22% of the original cost), as per the ministry's September 2023 report.

As of September 2023, the expenditure on these projects amounted to Rs 15,44,6006.7 million, representing 52.11% of the anticipated project cost. The report noted a decrease in the number of delayed projects to 617 when considering the latest completion schedule. Additionally, 298 projects lacked reported commissioning years or tentative gestation periods.

Among the 842 delayed projects, 194 experienced delays of 1-12 months, 190 were delayed for 13-24 months, 323 projects faced delays of 25-60 months, and 123 projects were delayed for more than 60 months. The average time overrun for these 842 delayed projects was 36.94 months. Reasons for time overruns cited by project implementing agencies included delays in land acquisition, obtaining forest and environment clearances, and insufficient infrastructure support and linkages. Other factors included delays in project financing tie-ups, finalisation of detailed engineering, changes in scope, tendering, ordering and equipment supply, as well as law and order problems.

The report highlighted state-wise lockdowns due to COVID-19 in 2020 and 2021 as contributing to project implementation delays. Furthermore, it observed that project executing agencies often fail to report revised cost estimates and commissioning schedules for many projects, suggesting potential underreporting of time and cost overrun figures.

An official report reveals that in September of this year, 417 infrastructure projects, each requiring an investment of Rs 1.5 billion or more, experienced cost overruns exceed Rs 4.77 trillion. The Ministry of Statistics and Programme Implementation, overseeing projects valued at Rs 1.5 billion and above, reported that out of 1,763 projects, 417 faced cost overruns, and 842 projects encountered delays. The initial cost of implementing the 1,763 projects was Rs 24,86,4027 million, with the projected completion cost expected to reach Rs 29,64,3451.3 million, indicating an overall cost overrun of Rs 4,77,9424.3 million (19.22% of the original cost), as per the ministry's September 2023 report. As of September 2023, the expenditure on these projects amounted to Rs 15,44,6006.7 million, representing 52.11% of the anticipated project cost. The report noted a decrease in the number of delayed projects to 617 when considering the latest completion schedule. Additionally, 298 projects lacked reported commissioning years or tentative gestation periods. Among the 842 delayed projects, 194 experienced delays of 1-12 months, 190 were delayed for 13-24 months, 323 projects faced delays of 25-60 months, and 123 projects were delayed for more than 60 months. The average time overrun for these 842 delayed projects was 36.94 months. Reasons for time overruns cited by project implementing agencies included delays in land acquisition, obtaining forest and environment clearances, and insufficient infrastructure support and linkages. Other factors included delays in project financing tie-ups, finalisation of detailed engineering, changes in scope, tendering, ordering and equipment supply, as well as law and order problems. The report highlighted state-wise lockdowns due to COVID-19 in 2020 and 2021 as contributing to project implementation delays. Furthermore, it observed that project executing agencies often fail to report revised cost estimates and commissioning schedules for many projects, suggesting potential underreporting of time and cost overrun figures.

Next Story
Infrastructure Energy

Adani Power To Build 2,400 MW Plant in Bihar

Adani Power on Saturday (September 13, 2025) announced plans to set up a 2,400 MW ultra super-critical power plant in Bihar at an investment of $3 billion (around Rs 26.48 billion).The company has signed a 25-year Power Supply Agreement (PSA) with Bihar State Power Generation Company Ltd (BSPGCL) to supply electricity from the project, which will be located at Pirpainti in Bhagalpur district.The PSA follows a Letter of Award issued by BSPGCL to Adani Power on behalf of North Bihar Power Distribution Company Ltd (NBPDCL) and South Bihar Power Distribution Company Ltd (SBPDCL) in August. Adani P..

Next Story
Infrastructure Energy

NTPC Plans Nuclear Power Projects Via JV and Standalone Routes

Power major NTPC is planning to develop nuclear power projects both through joint ventures and on a standalone basis, CMD Gurdeep Singh has said.The company is collaborating with nuclear technology providers and state governments to explore individual nuclear projects, Singh added.Currently, the NTPC Group has an installed capacity of 82,926 MW across 53 NTPC-owned stations and 53 joint venture or subsidiary stations, drawing power from coal, liquid fuel, hydro, and solar sources.In December 2024, Singh had announced NTPC’s ambitious plan to enter the nuclear energy sector, a move expected t..

Next Story
Infrastructure Transport

RVNL Wins $21.6 Million Bhopal Division Traction Substation

Rail Vikas Nigam (RVNL) has been declared the lowest bidder for a $21.6 million traction substation contract awarded by the West Central Railway.The project covers the design, modification, supply, erection, testing, and commissioning of a 220/132kV/2×25kV Scott-connected traction substation, switching posts, Auto-Transformer installations, and Supervisory Control and Data Acquisition (SCADA) systems in the Bina–RTA section of the Bhopal Division. The execution period is set at 540 days.In a regulatory filing, RVNL stated that the order was secured in the ordinary course of business and doe..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Talk to us?