458 infra projects affected by cost overrun of Rs 5.71 Tn
ECONOMY & POLICY

458 infra projects affected by cost overrun of Rs 5.71 Tn

According to an official assessment, in May of this year, there were 458 infrastructure projects with an investment of at least Rs 1.50 billion that had cost overruns of more than Rs 5.71 trillion. 458 out of 1,817 projects reported cost overruns, while 831 projects were delayed, according to the Ministry of Statistics and Programme Implementation (MoSPI), which keeps an eye on infrastructure projects of Rs 1.50 billion and above. 1,817 projects were initially estimated to have cost Rs 27 trillion in total to implement; it is expected that these projects will require an additional Rs 33 trillion to complete. The study states that the total amount spent on these projects up to May 2024 is Rs 17 trillion, or 51.3% of the projects' estimated total cost.

But if the delay is determined using the most recent completion timetable, the number of projects that are delayed dropped to 554, it said. Of the 831 projects that have been postponed, 245 have been delayed for a total of 1 to 12 months, 188 for 13 to 24 months, 271 for 25 to 60 months, and 127 for longer than 60 months. Among these 831 postponed projects, the average time overrun is 35.1 months. Various project implementing agencies have claimed that land acquisition, environmental clearance, financial challenges, contractual and internal issues, staffing shortages, and legal issues are among the reasons for time overruns.

According to an official assessment, in May of this year, there were 458 infrastructure projects with an investment of at least Rs 1.50 billion that had cost overruns of more than Rs 5.71 trillion. 458 out of 1,817 projects reported cost overruns, while 831 projects were delayed, according to the Ministry of Statistics and Programme Implementation (MoSPI), which keeps an eye on infrastructure projects of Rs 1.50 billion and above. 1,817 projects were initially estimated to have cost Rs 27 trillion in total to implement; it is expected that these projects will require an additional Rs 33 trillion to complete. The study states that the total amount spent on these projects up to May 2024 is Rs 17 trillion, or 51.3% of the projects' estimated total cost. But if the delay is determined using the most recent completion timetable, the number of projects that are delayed dropped to 554, it said. Of the 831 projects that have been postponed, 245 have been delayed for a total of 1 to 12 months, 188 for 13 to 24 months, 271 for 25 to 60 months, and 127 for longer than 60 months. Among these 831 postponed projects, the average time overrun is 35.1 months. Various project implementing agencies have claimed that land acquisition, environmental clearance, financial challenges, contractual and internal issues, staffing shortages, and legal issues are among the reasons for time overruns.

Next Story
Infrastructure Urban

ABB to Invest Rs 6.25 Billion to Expand India Manufacturing

ABB recently announced plans to invest approximately Rs 6.25 billion ($75 million) in India during 2026 to expand its manufacturing footprint and research and development capabilities. The investment follows more than $35 million spent in 2025 and reflects the company’s continued focus on strengthening its ‘local-for-local’ strategy in the country.The investment will support ABB’s Electrification, Motion and Automation businesses and expand manufacturing capacity for infrastructure sectors such as renewable energy, metro rail, data centres and industrial applications. Approximately 300..

Next Story
Equipment

Six WOLFF Cranes Handle 60,000 m³ Concrete for German Hospital

Six WOLFF tower cranes are playing a key role in constructing a new hospital complex in Memmingen, Germany, supporting large-scale material handling for the project. The facility is being built on a 7.7-hectare site and will feature six floors, around 480 beds and a gross floor area exceeding 75,000 sq m.Building shell works began recently in February 2025. One WOLFF 6531.12 Cross crane supported early site preparation before being dismantled in autumn 2025, while five remaining cranes continue operations. Over an average deployment period of 16 months, the cranes are expected to move approxim..

Next Story
Equipment

REC Funds Rs 115.6 Million CSR Support for Bihar Eye Hospital

REC recently committed Rs 115.6 million under its Corporate Social Responsibility (CSR) programme for the procurement of clinical and non-clinical equipment at Sankara Eye Hospital in Saharsa, Bihar. The initiative aims to strengthen healthcare infrastructure and improve access to specialised eye care services in the region.A Memorandum of Agreement (MoA) was recently signed between Pradeep Fellows, Executive Director (CSR), REC Limited, and Wg Cdr V. Shankar (Retd), Trustee and Executive Director of Sankara Eye Hospital, at the REC office in the SCOPE Complex, New Delhi.The support is expecte..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement