Nashik Faces Tight Deadline As 35 Kumbh Projects Lag
ECONOMY & POLICY

Nashik Faces Tight Deadline As 35 Kumbh Projects Lag

Nashik authorities face a major execution challenge as 35 major road and bridge projects for the Simhastha Kumbh Mela remain largely incomplete with around 70 per cent of the work pending. The Nashik Municipal Corporation's Public Works Department is managing 28 road projects and seven bridge projects across roughly 150 km of routes. The projects were sanctioned with an estimated expenditure of Rs 14 billion (bn) but progress is reportedly only about 30 per cent, increasing pressure on officials to accelerate work.

Among the bridges, the structure over the Nasardi River at Milind Nagar has progressed more rapidly, reaching about 45 per cent completion, while many other sites are still in initial or intermediate stages. Municipal officers have said that phased administrative clearances delayed start dates, reducing effective execution time. This has compounded concerns over whether the full programme can be completed by March 2027.

State planners approved an extensive development plan covering roads, bridges, water supply, electricity, river ghats, sanitation, technology and security, generating a complex matrix of tasks for multiple agencies. Hundreds of individual works were cleared or proposed, with major infrastructure projects representing a particularly heavy workload to finish within the limited timeframe. Coordination among the Nashik Municipal Corporation, public works, water resources, electricity distribution, police and local bodies will be critical to avoid further delays.

Officials have held coordination meetings that highlighted persistent issues in land acquisition, tendering and interdepartmental execution, and they intend to prioritise remaining tasks and monitor contractors more closely. The coming months are expected to be decisive as authorities seek to speed up construction while maintaining quality and safety standards. Failure to meet targets could leave key access routes and river crossings incomplete when the festival begins.

Based on present figures for the 35 major works, roughly 70 per cent remains to be finished and public representatives have questioned how many sanctioned projects have actually started. Authorities will need to compress schedules and streamline approvals to achieve completion by the deadline, and residents will be watching execution closely.

Nashik authorities face a major execution challenge as 35 major road and bridge projects for the Simhastha Kumbh Mela remain largely incomplete with around 70 per cent of the work pending. The Nashik Municipal Corporation's Public Works Department is managing 28 road projects and seven bridge projects across roughly 150 km of routes. The projects were sanctioned with an estimated expenditure of Rs 14 billion (bn) but progress is reportedly only about 30 per cent, increasing pressure on officials to accelerate work. Among the bridges, the structure over the Nasardi River at Milind Nagar has progressed more rapidly, reaching about 45 per cent completion, while many other sites are still in initial or intermediate stages. Municipal officers have said that phased administrative clearances delayed start dates, reducing effective execution time. This has compounded concerns over whether the full programme can be completed by March 2027. State planners approved an extensive development plan covering roads, bridges, water supply, electricity, river ghats, sanitation, technology and security, generating a complex matrix of tasks for multiple agencies. Hundreds of individual works were cleared or proposed, with major infrastructure projects representing a particularly heavy workload to finish within the limited timeframe. Coordination among the Nashik Municipal Corporation, public works, water resources, electricity distribution, police and local bodies will be critical to avoid further delays. Officials have held coordination meetings that highlighted persistent issues in land acquisition, tendering and interdepartmental execution, and they intend to prioritise remaining tasks and monitor contractors more closely. The coming months are expected to be decisive as authorities seek to speed up construction while maintaining quality and safety standards. Failure to meet targets could leave key access routes and river crossings incomplete when the festival begins. Based on present figures for the 35 major works, roughly 70 per cent remains to be finished and public representatives have questioned how many sanctioned projects have actually started. Authorities will need to compress schedules and streamline approvals to achieve completion by the deadline, and residents will be watching execution closely.

Related Stories

Gold Stories

Next Story
Infrastructure Transport

Mumbai-Ahmedabad Bullet Train’s Surat-Vapi Section Set for 2027

The first section of the Mumbai-Ahmedabad Bullet Train corridor, linking Surat and Vapi, is targeted to begin services in 2027. Construction is expected to be completed by December 2026, while Railway Minister Ashwini Vaishnaw has indicated that an inauguration could take place around the middle of 2027. The National High Speed Rail Corporation (NHSRCL) said the train being manufactured in India is expected to reach the tracks around April or May 2027. The train will undergo extensive testing before the section is opened for passenger services. The project began construction in 2021 and includ..

Next Story
Infrastructure Transport

Indian Railways Approves Four Projects Worth Rs. 7.36 bn Across Four States

Indian Railways has approved four projects with a combined value of Rs. 7.36 bn across Uttar Pradesh, Maharashtra, Andhra Pradesh and Gujarat. The programme covers train protection, signalling, electric traction supply and a road overbridge, with each project assigned to a different railway zone. In Uttar Pradesh, Rs. 2.52 bn has been approved to extend the Kavach 4.0 automatic train protection system across 607.7 km in the Lucknow Division of North Eastern Railway. The system monitors train movements and can apply the brakes if a driver fails to observe a signal or exceeds a safe speed. The w..

Next Story
Infrastructure Urban

Chandru Raheja Sells 1.49% Stake in Mindspace REIT for Rs. 5 bn

Billionaire Chandru Lachmandas Raheja has sold a 1.49 per cent holding in Mindspace Business Parks REIT for Rs. 5 bn through a bulk deal on the BSE. The transaction involved 9.9 mn units and was executed at an average price of Rs. 505 per unit, according to exchange data. Following the sale, units of Mindspace Business Parks REIT were trading 0.18 per cent lower at Rs. 504.05 on Tuesday. Exchange data did not identify the buyers involved in the transaction. Raheja is the chairman of real estate company K Raheja Corp. The sale involved 99,00,990 units, representing 1.49 per cent of the Mumbai-b..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

SPECIAL OFFER
QR Code