UP RERA Warns Builders of 5% Penalty for Incomplete Flat Handover
AVIATION & AIRPORTS

UP RERA Warns Builders of 5% Penalty for Incomplete Flat Handover

In response to numerous complaints from homebuyers, the Uttar Pradesh Real Estate Regulatory Authority (UP-Rera) has instructed all developers to immediately halt the practice of handing over incomplete apartments, often referred to as "canvas flats" or bare shell units. The authority warned that any violation of this directive could result in penalties of up to 5 per cent of the total cost of the real estate project.

The directive, issued on May 8 under Section 37 of the RERA Act, 2016, clearly states that possession of an apartment can only be offered once the unit is fully completed, all promised amenities are in place, and a registered sale or lease deed has been executed. This move is intended to safeguard homebuyers from being forced to accept unfinished properties, which UP-Rera has categorized as both illegal and a serious breach of the law, according to a report published in the Hindustan Times.

Mahendra Verma, Secretary of UP-Rera, stated that promoters found violating these rules could face fines of up to 5 per cent of the total project cost under Sections 38 and 61 of the RERA Act. He further explained that the authority had observed instances where some developers, during the execution of the Agreement for Sale (BBA), were coercing allottees into accepting physical possession of unfinished units. In many such cases, these units were being handed over without meeting the legal criteria. This practice, Verma noted, went against the spirit and letter of the RERA Act and its rules, ultimately defeating the purpose of the buyer protection framework established by the legislation. Consequently, the authority found it necessary to issue firm directives to ensure developers adhere strictly to the law and that the interests of homebuyers are not compromised.

According to Uttar Pradesh building bylaws, developers are required to obtain multiple no-objection certificates (NOCs) — including approvals related to fire safety, clearance of dues, and the provision of amenities such as parks, lifts, and swimming pools — before they can apply for an Occupancy Certificate (OC). Once all criteria are fulfilled, the Noida Authority inspects the project site. Officials confirmed that only after the OC is granted can possession be legally transferred; doing so beforehand is considered illegal.

The regulatory body also clarified that physical possession of a flat is permissible only after the builder secures a valid completion or occupancy certificate from the appropriate authority. Furthermore, developers are not allowed to demand more than 10 per cent of the property cost without first executing a registered agreement with the buyer.

The order defines a “ready-to-move-in” unit as one where all internal work — including flooring, plumbing, electrical fittings, fire safety installations, doors, windows, and other finishing elements — is fully completed, in accordance with the details mentioned in the project brochure and the sanctioned layout plan. As per Rule 1.8(3) of the UP Agreement for Sale Rules, 2018, the quoted price must cover land costs, construction charges, development fees, and all committed amenities. Any deviation from this is considered a breach of contract.

In response to numerous complaints from homebuyers, the Uttar Pradesh Real Estate Regulatory Authority (UP-Rera) has instructed all developers to immediately halt the practice of handing over incomplete apartments, often referred to as canvas flats or bare shell units. The authority warned that any violation of this directive could result in penalties of up to 5 per cent of the total cost of the real estate project.The directive, issued on May 8 under Section 37 of the RERA Act, 2016, clearly states that possession of an apartment can only be offered once the unit is fully completed, all promised amenities are in place, and a registered sale or lease deed has been executed. This move is intended to safeguard homebuyers from being forced to accept unfinished properties, which UP-Rera has categorized as both illegal and a serious breach of the law, according to a report published in the Hindustan Times.Mahendra Verma, Secretary of UP-Rera, stated that promoters found violating these rules could face fines of up to 5 per cent of the total project cost under Sections 38 and 61 of the RERA Act. He further explained that the authority had observed instances where some developers, during the execution of the Agreement for Sale (BBA), were coercing allottees into accepting physical possession of unfinished units. In many such cases, these units were being handed over without meeting the legal criteria. This practice, Verma noted, went against the spirit and letter of the RERA Act and its rules, ultimately defeating the purpose of the buyer protection framework established by the legislation. Consequently, the authority found it necessary to issue firm directives to ensure developers adhere strictly to the law and that the interests of homebuyers are not compromised.According to Uttar Pradesh building bylaws, developers are required to obtain multiple no-objection certificates (NOCs) — including approvals related to fire safety, clearance of dues, and the provision of amenities such as parks, lifts, and swimming pools — before they can apply for an Occupancy Certificate (OC). Once all criteria are fulfilled, the Noida Authority inspects the project site. Officials confirmed that only after the OC is granted can possession be legally transferred; doing so beforehand is considered illegal.The regulatory body also clarified that physical possession of a flat is permissible only after the builder secures a valid completion or occupancy certificate from the appropriate authority. Furthermore, developers are not allowed to demand more than 10 per cent of the property cost without first executing a registered agreement with the buyer.The order defines a “ready-to-move-in” unit as one where all internal work — including flooring, plumbing, electrical fittings, fire safety installations, doors, windows, and other finishing elements — is fully completed, in accordance with the details mentioned in the project brochure and the sanctioned layout plan. As per Rule 1.8(3) of the UP Agreement for Sale Rules, 2018, the quoted price must cover land costs, construction charges, development fees, and all committed amenities. Any deviation from this is considered a breach of contract.

Next Story
Products

unWOOD transforms plastic waste into durable wood alternative

unWOOD, a breakthrough innovation, is converting hard-to-recycle plastic waste into a durable alternative to natural wood. Developed through a proprietary process called Intelligent Compounding, unWOOD uses a Macro Molecular Fiber Matrix (MMFM) structure to replicate the strength, look, and feel of hardwood—without the environmental cost.Conceptualised by Dr Babu Padmanabhan, the material addresses key flaws in traditional plastic recycling by consuming minimal energy, using zero water, and generating no microplastics. “Any application that introduces plastics into areas where it cannot be..

Next Story
Real Estate

India's first AI-integrated campus announced in Noida

Yashoda Hospital and Bhutani Infra have announced plans to develop India’s first fully AI-integrated mixed-use campus in Greater Noida West. The upcoming project will feature a hospital, retail spaces, offices, SOHOs, serviced apartments, and a hotel—all operating within a self-learning, generative AI-powered ecosystem.The AI-first campus will integrate real-time data systems, predictive analytics, and adaptive infrastructure to offer personalised experiences across functions. From AI-enabled footfall tracking and dynamic energy optimisation to smart F&B and retail insights, the develo..

Next Story
Infrastructure Urban

Postal Dept Unveils Stamp Honouring 125 Years of Kodaikanal Observatory

The Department of Posts is proud to release a commemorative postage stamp celebrating 125 years of the Kodaikanal Solar Observatory (KSO). Recognising the legacy of the KSO through this special stamp is a fitting tribute to one of India’s most significant scientific institutions and highlights the nation’s long-standing contribution to global science.The Commemorative stamp was released by S Rajendra Kumar, Chief Postmaster General, Karnataka Circle in the gracious presence of A S Kiran Kumar, Chairperson, Governing Council, IIA and Former Chairman, ISRO and other esteemed guests at Indian..

Advertisement

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Advertisement

Talk to us?