UP RERA Warns Builders of 5% Penalty for Incomplete Flat Handover
AVIATION & AIRPORTS

UP RERA Warns Builders of 5% Penalty for Incomplete Flat Handover

In response to numerous complaints from homebuyers, the Uttar Pradesh Real Estate Regulatory Authority (UP-Rera) has instructed all developers to immediately halt the practice of handing over incomplete apartments, often referred to as "canvas flats" or bare shell units. The authority warned that any violation of this directive could result in penalties of up to 5 per cent of the total cost of the real estate project.

The directive, issued on May 8 under Section 37 of the RERA Act, 2016, clearly states that possession of an apartment can only be offered once the unit is fully completed, all promised amenities are in place, and a registered sale or lease deed has been executed. This move is intended to safeguard homebuyers from being forced to accept unfinished properties, which UP-Rera has categorized as both illegal and a serious breach of the law, according to a report published in the Hindustan Times.

Mahendra Verma, Secretary of UP-Rera, stated that promoters found violating these rules could face fines of up to 5 per cent of the total project cost under Sections 38 and 61 of the RERA Act. He further explained that the authority had observed instances where some developers, during the execution of the Agreement for Sale (BBA), were coercing allottees into accepting physical possession of unfinished units. In many such cases, these units were being handed over without meeting the legal criteria. This practice, Verma noted, went against the spirit and letter of the RERA Act and its rules, ultimately defeating the purpose of the buyer protection framework established by the legislation. Consequently, the authority found it necessary to issue firm directives to ensure developers adhere strictly to the law and that the interests of homebuyers are not compromised.

According to Uttar Pradesh building bylaws, developers are required to obtain multiple no-objection certificates (NOCs) — including approvals related to fire safety, clearance of dues, and the provision of amenities such as parks, lifts, and swimming pools — before they can apply for an Occupancy Certificate (OC). Once all criteria are fulfilled, the Noida Authority inspects the project site. Officials confirmed that only after the OC is granted can possession be legally transferred; doing so beforehand is considered illegal.

The regulatory body also clarified that physical possession of a flat is permissible only after the builder secures a valid completion or occupancy certificate from the appropriate authority. Furthermore, developers are not allowed to demand more than 10 per cent of the property cost without first executing a registered agreement with the buyer.

The order defines a “ready-to-move-in” unit as one where all internal work — including flooring, plumbing, electrical fittings, fire safety installations, doors, windows, and other finishing elements — is fully completed, in accordance with the details mentioned in the project brochure and the sanctioned layout plan. As per Rule 1.8(3) of the UP Agreement for Sale Rules, 2018, the quoted price must cover land costs, construction charges, development fees, and all committed amenities. Any deviation from this is considered a breach of contract.

In response to numerous complaints from homebuyers, the Uttar Pradesh Real Estate Regulatory Authority (UP-Rera) has instructed all developers to immediately halt the practice of handing over incomplete apartments, often referred to as canvas flats or bare shell units. The authority warned that any violation of this directive could result in penalties of up to 5 per cent of the total cost of the real estate project.The directive, issued on May 8 under Section 37 of the RERA Act, 2016, clearly states that possession of an apartment can only be offered once the unit is fully completed, all promised amenities are in place, and a registered sale or lease deed has been executed. This move is intended to safeguard homebuyers from being forced to accept unfinished properties, which UP-Rera has categorized as both illegal and a serious breach of the law, according to a report published in the Hindustan Times.Mahendra Verma, Secretary of UP-Rera, stated that promoters found violating these rules could face fines of up to 5 per cent of the total project cost under Sections 38 and 61 of the RERA Act. He further explained that the authority had observed instances where some developers, during the execution of the Agreement for Sale (BBA), were coercing allottees into accepting physical possession of unfinished units. In many such cases, these units were being handed over without meeting the legal criteria. This practice, Verma noted, went against the spirit and letter of the RERA Act and its rules, ultimately defeating the purpose of the buyer protection framework established by the legislation. Consequently, the authority found it necessary to issue firm directives to ensure developers adhere strictly to the law and that the interests of homebuyers are not compromised.According to Uttar Pradesh building bylaws, developers are required to obtain multiple no-objection certificates (NOCs) — including approvals related to fire safety, clearance of dues, and the provision of amenities such as parks, lifts, and swimming pools — before they can apply for an Occupancy Certificate (OC). Once all criteria are fulfilled, the Noida Authority inspects the project site. Officials confirmed that only after the OC is granted can possession be legally transferred; doing so beforehand is considered illegal.The regulatory body also clarified that physical possession of a flat is permissible only after the builder secures a valid completion or occupancy certificate from the appropriate authority. Furthermore, developers are not allowed to demand more than 10 per cent of the property cost without first executing a registered agreement with the buyer.The order defines a “ready-to-move-in” unit as one where all internal work — including flooring, plumbing, electrical fittings, fire safety installations, doors, windows, and other finishing elements — is fully completed, in accordance with the details mentioned in the project brochure and the sanctioned layout plan. As per Rule 1.8(3) of the UP Agreement for Sale Rules, 2018, the quoted price must cover land costs, construction charges, development fees, and all committed amenities. Any deviation from this is considered a breach of contract.

Next Story
Infrastructure Energy

Invenia Wins Rs 3.6 Billion Contract for PowerGrid Data Centre

Invenia-STL Networks Limited, a leading digital infrastructure and IT services company, announced it has secured a major contract worth over Rs 3.6 billion from PowerGrid Teleservices Limited (PowerTel), a wholly owned subsidiary of the Power Grid Corporation of India Limited (PGCIL), the nation’s largest electric power transmission utility.Under the agreement, Invenia will design, build, commission and maintain the complete IT and cloud infrastructure for a greenfield Tier III data centre at PowerGrid’s Manesar facility. In addition, Invenia will establish a Disaster Recovery Data Centre ..

Next Story
Infrastructure Energy

Vikram Solar Secures 200 MW Order to Expand India’s Solar Capacity

Vikram Solar, one of India’s leading solar PV module manufacturers, has announced a major order of 200 MW high-efficiency solar modules from AB Energia, a specialist in end-to-end EPC solutions for commercial and industrial (C&I) solar projects. The modules, rated at 590 Wp and above, will be deployed across Maharashtra, Madhya Pradesh and Gujarat — three solar-progressive states accelerating their adoption of clean energy.Under this order, Vikram Solar will supply its advanced M10R N-Type TOPCon modules, designed for superior performance, reliability and higher energy yield. Deliverie..

Next Story
Real Estate

Shriram Properties Backs Neerathon 2025 to Promote Water Conservation

Shriram Properties Limited (SPL), one of India’s leading residential developers in the mid-market and mid-premium segments, reaffirmed its commitment to sustainability and community welfare by supporting IPA Neerathon 2025 in Chennai as the Title Sponsor. The event, which attracted thousands of participants across 10K, 5K and 3K categories at Island Grounds, was more than a race — it was a movement for water conservation and environmental stewardship.For SPL, this partnership aligns with its long-standing efforts to support initiatives beyond real estate, promoting sustainable communities ..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Talk to us?