UP RERA Warns Builders of 5% Penalty for Incomplete Flat Handover
AVIATION & AIRPORTS

UP RERA Warns Builders of 5% Penalty for Incomplete Flat Handover

In response to numerous complaints from homebuyers, the Uttar Pradesh Real Estate Regulatory Authority (UP-Rera) has instructed all developers to immediately halt the practice of handing over incomplete apartments, often referred to as "canvas flats" or bare shell units. The authority warned that any violation of this directive could result in penalties of up to 5 per cent of the total cost of the real estate project.

The directive, issued on May 8 under Section 37 of the RERA Act, 2016, clearly states that possession of an apartment can only be offered once the unit is fully completed, all promised amenities are in place, and a registered sale or lease deed has been executed. This move is intended to safeguard homebuyers from being forced to accept unfinished properties, which UP-Rera has categorized as both illegal and a serious breach of the law, according to a report published in the Hindustan Times.

Mahendra Verma, Secretary of UP-Rera, stated that promoters found violating these rules could face fines of up to 5 per cent of the total project cost under Sections 38 and 61 of the RERA Act. He further explained that the authority had observed instances where some developers, during the execution of the Agreement for Sale (BBA), were coercing allottees into accepting physical possession of unfinished units. In many such cases, these units were being handed over without meeting the legal criteria. This practice, Verma noted, went against the spirit and letter of the RERA Act and its rules, ultimately defeating the purpose of the buyer protection framework established by the legislation. Consequently, the authority found it necessary to issue firm directives to ensure developers adhere strictly to the law and that the interests of homebuyers are not compromised.

According to Uttar Pradesh building bylaws, developers are required to obtain multiple no-objection certificates (NOCs) — including approvals related to fire safety, clearance of dues, and the provision of amenities such as parks, lifts, and swimming pools — before they can apply for an Occupancy Certificate (OC). Once all criteria are fulfilled, the Noida Authority inspects the project site. Officials confirmed that only after the OC is granted can possession be legally transferred; doing so beforehand is considered illegal.

The regulatory body also clarified that physical possession of a flat is permissible only after the builder secures a valid completion or occupancy certificate from the appropriate authority. Furthermore, developers are not allowed to demand more than 10 per cent of the property cost without first executing a registered agreement with the buyer.

The order defines a “ready-to-move-in” unit as one where all internal work — including flooring, plumbing, electrical fittings, fire safety installations, doors, windows, and other finishing elements — is fully completed, in accordance with the details mentioned in the project brochure and the sanctioned layout plan. As per Rule 1.8(3) of the UP Agreement for Sale Rules, 2018, the quoted price must cover land costs, construction charges, development fees, and all committed amenities. Any deviation from this is considered a breach of contract.

In response to numerous complaints from homebuyers, the Uttar Pradesh Real Estate Regulatory Authority (UP-Rera) has instructed all developers to immediately halt the practice of handing over incomplete apartments, often referred to as canvas flats or bare shell units. The authority warned that any violation of this directive could result in penalties of up to 5 per cent of the total cost of the real estate project.The directive, issued on May 8 under Section 37 of the RERA Act, 2016, clearly states that possession of an apartment can only be offered once the unit is fully completed, all promised amenities are in place, and a registered sale or lease deed has been executed. This move is intended to safeguard homebuyers from being forced to accept unfinished properties, which UP-Rera has categorized as both illegal and a serious breach of the law, according to a report published in the Hindustan Times.Mahendra Verma, Secretary of UP-Rera, stated that promoters found violating these rules could face fines of up to 5 per cent of the total project cost under Sections 38 and 61 of the RERA Act. He further explained that the authority had observed instances where some developers, during the execution of the Agreement for Sale (BBA), were coercing allottees into accepting physical possession of unfinished units. In many such cases, these units were being handed over without meeting the legal criteria. This practice, Verma noted, went against the spirit and letter of the RERA Act and its rules, ultimately defeating the purpose of the buyer protection framework established by the legislation. Consequently, the authority found it necessary to issue firm directives to ensure developers adhere strictly to the law and that the interests of homebuyers are not compromised.According to Uttar Pradesh building bylaws, developers are required to obtain multiple no-objection certificates (NOCs) — including approvals related to fire safety, clearance of dues, and the provision of amenities such as parks, lifts, and swimming pools — before they can apply for an Occupancy Certificate (OC). Once all criteria are fulfilled, the Noida Authority inspects the project site. Officials confirmed that only after the OC is granted can possession be legally transferred; doing so beforehand is considered illegal.The regulatory body also clarified that physical possession of a flat is permissible only after the builder secures a valid completion or occupancy certificate from the appropriate authority. Furthermore, developers are not allowed to demand more than 10 per cent of the property cost without first executing a registered agreement with the buyer.The order defines a “ready-to-move-in” unit as one where all internal work — including flooring, plumbing, electrical fittings, fire safety installations, doors, windows, and other finishing elements — is fully completed, in accordance with the details mentioned in the project brochure and the sanctioned layout plan. As per Rule 1.8(3) of the UP Agreement for Sale Rules, 2018, the quoted price must cover land costs, construction charges, development fees, and all committed amenities. Any deviation from this is considered a breach of contract.

Next Story
Infrastructure Energy

KEC Secures Rs 10, 380 Mn Substation Order in Saudi Arabia

KEC International Ltd., a global infrastructure EPC major, and an RPG Group company, has secured a new order worth Rs 10,380 million for the Design, Supply and Installation of a 380 kV GIS Substation in Saudi Arabia.Vimal Kejriwal, MD & CEO, KEC International Ltd., commented, “We are delighted with the successive order wins in our T&D business. In a landmark achievement, we have secured our largest ever substation order. This prestigious order in the Middle East has widened our portfolio and strengthened our presence in the region. With this strategic win, our year-to-date or..

Next Story
Infrastructure Urban

Central Bank of India executes first fully digital SCF deal on PSB Xchange

In a major advancement for India’s banking sector, Central Bank of India (CBI) has successfully completed the country’s first fully digital supply chain finance (SCF) transaction on PSB Xchange—a unified multi-lender platform launched by PSB Alliance. PSB Xchange is designed to connect public and private sector banks, NBFCs, and fintechs with corporates and their channel partners to facilitate supply chain finance and small business loans. The transaction marks the first time a fintech-originated corporate lead has been seamlessly processed through the PSB Xchange ecosystem. The lead fl..

Next Story
Infrastructure Energy

Atlanta Electricals secures Rs 1,835 Mn transformer order from BNC Power

Atlanta Electricals Limited (“Atlanta”) has secured an order worth Rs 1,835 million from BNC Power Projects Ltd for the supply of extra high voltage (EHV) transformers and a bus reactor for its Pugal site. The contract includes a mix of 315 MVA, 400 KV and 100 MVA, 132 KV transformers along with a 400 KV bus reactor. The project scope encompasses design, manufacturing, testing, and supply to the project site. Deliveries will be sequenced following engineering and drawing approvals, offering multi-quarter execution visibility and ensuring a steady production run-rate. The order will be ex..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Talk to us?