+
UP RERA Warns Builders of 5% Penalty for Incomplete Flat Handover
AVIATION & AIRPORTS

UP RERA Warns Builders of 5% Penalty for Incomplete Flat Handover

In response to numerous complaints from homebuyers, the Uttar Pradesh Real Estate Regulatory Authority (UP-Rera) has instructed all developers to immediately halt the practice of handing over incomplete apartments, often referred to as "canvas flats" or bare shell units. The authority warned that any violation of this directive could result in penalties of up to 5 per cent of the total cost of the real estate project.

The directive, issued on May 8 under Section 37 of the RERA Act, 2016, clearly states that possession of an apartment can only be offered once the unit is fully completed, all promised amenities are in place, and a registered sale or lease deed has been executed. This move is intended to safeguard homebuyers from being forced to accept unfinished properties, which UP-Rera has categorized as both illegal and a serious breach of the law, according to a report published in the Hindustan Times.

Mahendra Verma, Secretary of UP-Rera, stated that promoters found violating these rules could face fines of up to 5 per cent of the total project cost under Sections 38 and 61 of the RERA Act. He further explained that the authority had observed instances where some developers, during the execution of the Agreement for Sale (BBA), were coercing allottees into accepting physical possession of unfinished units. In many such cases, these units were being handed over without meeting the legal criteria. This practice, Verma noted, went against the spirit and letter of the RERA Act and its rules, ultimately defeating the purpose of the buyer protection framework established by the legislation. Consequently, the authority found it necessary to issue firm directives to ensure developers adhere strictly to the law and that the interests of homebuyers are not compromised.

According to Uttar Pradesh building bylaws, developers are required to obtain multiple no-objection certificates (NOCs) — including approvals related to fire safety, clearance of dues, and the provision of amenities such as parks, lifts, and swimming pools — before they can apply for an Occupancy Certificate (OC). Once all criteria are fulfilled, the Noida Authority inspects the project site. Officials confirmed that only after the OC is granted can possession be legally transferred; doing so beforehand is considered illegal.

The regulatory body also clarified that physical possession of a flat is permissible only after the builder secures a valid completion or occupancy certificate from the appropriate authority. Furthermore, developers are not allowed to demand more than 10 per cent of the property cost without first executing a registered agreement with the buyer.

The order defines a “ready-to-move-in” unit as one where all internal work — including flooring, plumbing, electrical fittings, fire safety installations, doors, windows, and other finishing elements — is fully completed, in accordance with the details mentioned in the project brochure and the sanctioned layout plan. As per Rule 1.8(3) of the UP Agreement for Sale Rules, 2018, the quoted price must cover land costs, construction charges, development fees, and all committed amenities. Any deviation from this is considered a breach of contract.

Your next big infra connection is waiting at RAHSTA 2025 – Asia’s Biggest Roads & Highways Expo, Jio World Convention Centre, Mumbai. Don’t miss out!

In response to numerous complaints from homebuyers, the Uttar Pradesh Real Estate Regulatory Authority (UP-Rera) has instructed all developers to immediately halt the practice of handing over incomplete apartments, often referred to as canvas flats or bare shell units. The authority warned that any violation of this directive could result in penalties of up to 5 per cent of the total cost of the real estate project.The directive, issued on May 8 under Section 37 of the RERA Act, 2016, clearly states that possession of an apartment can only be offered once the unit is fully completed, all promised amenities are in place, and a registered sale or lease deed has been executed. This move is intended to safeguard homebuyers from being forced to accept unfinished properties, which UP-Rera has categorized as both illegal and a serious breach of the law, according to a report published in the Hindustan Times.Mahendra Verma, Secretary of UP-Rera, stated that promoters found violating these rules could face fines of up to 5 per cent of the total project cost under Sections 38 and 61 of the RERA Act. He further explained that the authority had observed instances where some developers, during the execution of the Agreement for Sale (BBA), were coercing allottees into accepting physical possession of unfinished units. In many such cases, these units were being handed over without meeting the legal criteria. This practice, Verma noted, went against the spirit and letter of the RERA Act and its rules, ultimately defeating the purpose of the buyer protection framework established by the legislation. Consequently, the authority found it necessary to issue firm directives to ensure developers adhere strictly to the law and that the interests of homebuyers are not compromised.According to Uttar Pradesh building bylaws, developers are required to obtain multiple no-objection certificates (NOCs) — including approvals related to fire safety, clearance of dues, and the provision of amenities such as parks, lifts, and swimming pools — before they can apply for an Occupancy Certificate (OC). Once all criteria are fulfilled, the Noida Authority inspects the project site. Officials confirmed that only after the OC is granted can possession be legally transferred; doing so beforehand is considered illegal.The regulatory body also clarified that physical possession of a flat is permissible only after the builder secures a valid completion or occupancy certificate from the appropriate authority. Furthermore, developers are not allowed to demand more than 10 per cent of the property cost without first executing a registered agreement with the buyer.The order defines a “ready-to-move-in” unit as one where all internal work — including flooring, plumbing, electrical fittings, fire safety installations, doors, windows, and other finishing elements — is fully completed, in accordance with the details mentioned in the project brochure and the sanctioned layout plan. As per Rule 1.8(3) of the UP Agreement for Sale Rules, 2018, the quoted price must cover land costs, construction charges, development fees, and all committed amenities. Any deviation from this is considered a breach of contract.

Next Story
Real Estate

Maharashtra to Revise Infrastructure Policies

The Government of Maharashtra will make every possible effort to frame infrastructure-related policies, including those that promote housing in the state, in line with changing requirements. This assurance was given by Mrs. Meghana Sakore Bordikar, Minister of State, Government of Maharashtra, while addressing the two-day NAREDCO 17th National Convention, “India Builds: Reimagining Growth through Real Estate and Infrastructure”. At the convention, Dr Niranjan Hiranandani, Chairman of NAREDCO, called for a new blueprint for infrastructure policies in the present context.The Minister assured..

Next Story
Real Estate

Agami Realty Enters Mumbai's Luxury Market

Agami Realty, a leading real estate developer with a legacy of over five decades, has marked its foray into Mumbai’s luxury residential market with two significant redevelopment projects in Bandra, valued at an estimated Rs 9.5 billion. The company, known for its boutique developments that blend sustainability, technology, and design excellence, has already received a strong response to its Bandra offering.Agami Eternity, the firm’s first completed premium redevelopment project in Mumbai, recently received its Occupancy Certificate. Located in Bandra East, the project was designed by inter..

Next Story
Real Estate

Hafele Launches Its Third Licht Experience Centre in India

Hafele, a global leader in interior solutions, has announced the launch of its third Licht Experience Centre in Ahmedabad. This new centre, located at 302, 31 Five, Opp. Palladium, Corporate Road, Makarba, follows the successful openings in Chandigarh and Indore, further strengthening Hafele's footprint in India. The name “Licht,” which means “light” in German, captures the essence of this experience, where technology meets aesthetics to redefine interior spaces.The Ahmedabad Licht Experience Centre was inaugurated by Mr Frank Schloeder, Managing Director of Hafele South Asia, and Mr P..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Talk to us?