UP RERA Warns Builders of 5% Penalty for Incomplete Flat Handover
AVIATION & AIRPORTS

UP RERA Warns Builders of 5% Penalty for Incomplete Flat Handover

In response to numerous complaints from homebuyers, the Uttar Pradesh Real Estate Regulatory Authority (UP-Rera) has instructed all developers to immediately halt the practice of handing over incomplete apartments, often referred to as "canvas flats" or bare shell units. The authority warned that any violation of this directive could result in penalties of up to 5 per cent of the total cost of the real estate project.

The directive, issued on May 8 under Section 37 of the RERA Act, 2016, clearly states that possession of an apartment can only be offered once the unit is fully completed, all promised amenities are in place, and a registered sale or lease deed has been executed. This move is intended to safeguard homebuyers from being forced to accept unfinished properties, which UP-Rera has categorized as both illegal and a serious breach of the law, according to a report published in the Hindustan Times.

Mahendra Verma, Secretary of UP-Rera, stated that promoters found violating these rules could face fines of up to 5 per cent of the total project cost under Sections 38 and 61 of the RERA Act. He further explained that the authority had observed instances where some developers, during the execution of the Agreement for Sale (BBA), were coercing allottees into accepting physical possession of unfinished units. In many such cases, these units were being handed over without meeting the legal criteria. This practice, Verma noted, went against the spirit and letter of the RERA Act and its rules, ultimately defeating the purpose of the buyer protection framework established by the legislation. Consequently, the authority found it necessary to issue firm directives to ensure developers adhere strictly to the law and that the interests of homebuyers are not compromised.

According to Uttar Pradesh building bylaws, developers are required to obtain multiple no-objection certificates (NOCs) — including approvals related to fire safety, clearance of dues, and the provision of amenities such as parks, lifts, and swimming pools — before they can apply for an Occupancy Certificate (OC). Once all criteria are fulfilled, the Noida Authority inspects the project site. Officials confirmed that only after the OC is granted can possession be legally transferred; doing so beforehand is considered illegal.

The regulatory body also clarified that physical possession of a flat is permissible only after the builder secures a valid completion or occupancy certificate from the appropriate authority. Furthermore, developers are not allowed to demand more than 10 per cent of the property cost without first executing a registered agreement with the buyer.

The order defines a “ready-to-move-in” unit as one where all internal work — including flooring, plumbing, electrical fittings, fire safety installations, doors, windows, and other finishing elements — is fully completed, in accordance with the details mentioned in the project brochure and the sanctioned layout plan. As per Rule 1.8(3) of the UP Agreement for Sale Rules, 2018, the quoted price must cover land costs, construction charges, development fees, and all committed amenities. Any deviation from this is considered a breach of contract.

In response to numerous complaints from homebuyers, the Uttar Pradesh Real Estate Regulatory Authority (UP-Rera) has instructed all developers to immediately halt the practice of handing over incomplete apartments, often referred to as canvas flats or bare shell units. The authority warned that any violation of this directive could result in penalties of up to 5 per cent of the total cost of the real estate project.The directive, issued on May 8 under Section 37 of the RERA Act, 2016, clearly states that possession of an apartment can only be offered once the unit is fully completed, all promised amenities are in place, and a registered sale or lease deed has been executed. This move is intended to safeguard homebuyers from being forced to accept unfinished properties, which UP-Rera has categorized as both illegal and a serious breach of the law, according to a report published in the Hindustan Times.Mahendra Verma, Secretary of UP-Rera, stated that promoters found violating these rules could face fines of up to 5 per cent of the total project cost under Sections 38 and 61 of the RERA Act. He further explained that the authority had observed instances where some developers, during the execution of the Agreement for Sale (BBA), were coercing allottees into accepting physical possession of unfinished units. In many such cases, these units were being handed over without meeting the legal criteria. This practice, Verma noted, went against the spirit and letter of the RERA Act and its rules, ultimately defeating the purpose of the buyer protection framework established by the legislation. Consequently, the authority found it necessary to issue firm directives to ensure developers adhere strictly to the law and that the interests of homebuyers are not compromised.According to Uttar Pradesh building bylaws, developers are required to obtain multiple no-objection certificates (NOCs) — including approvals related to fire safety, clearance of dues, and the provision of amenities such as parks, lifts, and swimming pools — before they can apply for an Occupancy Certificate (OC). Once all criteria are fulfilled, the Noida Authority inspects the project site. Officials confirmed that only after the OC is granted can possession be legally transferred; doing so beforehand is considered illegal.The regulatory body also clarified that physical possession of a flat is permissible only after the builder secures a valid completion or occupancy certificate from the appropriate authority. Furthermore, developers are not allowed to demand more than 10 per cent of the property cost without first executing a registered agreement with the buyer.The order defines a “ready-to-move-in” unit as one where all internal work — including flooring, plumbing, electrical fittings, fire safety installations, doors, windows, and other finishing elements — is fully completed, in accordance with the details mentioned in the project brochure and the sanctioned layout plan. As per Rule 1.8(3) of the UP Agreement for Sale Rules, 2018, the quoted price must cover land costs, construction charges, development fees, and all committed amenities. Any deviation from this is considered a breach of contract.

Next Story
Infrastructure Urban

Coal Ministry Achieves Milestones under Special Campaign 5.0

The Ministry of Coal and its Public Sector Undertakings (PSUs) have achieved notable milestones under the Special Campaign 5.0, focusing on cleanliness, operational efficiency, and sustainability across the coal sector. During the implementation phase from 2–31 October 2025, over 1,205 sites were cleaned, covering 68,04,087 sq ft, nearing the target of 82,51,511 sq ft. Scrap disposal of 5,813 MT against a target of 8,678 MT generated Rs 228.7 million in revenue. In addition, 1,11,248 physical and 30,331 electronic files were reviewed, with 74,123 weeded out or closed. Key initiatives showc..

Next Story
Infrastructure Energy

Vesting Orders Issued for Three Coal Blocks under Commercial Auctions

The Ministry of Coal’s Nominated Authority has issued vesting orders for three coal blocks under commercial coal block auctions on 23 October 2025. The Coal Mine Development and Production Agreements (CMDPAs) for these mines were earlier signed on 21 August 2025. The three blocks include Rajgamar Dipside (Deavnara), Tangardihi North, and Mahuagarhi. Of these, two are partially explored while one is fully explored, with a combined peak rated capacity of around 1 MTPA and geological reserves of approximately 1,484.41 million tonnes. These mines are expected to generate annual revenue of abou..

Next Story
Infrastructure Urban

TEC, IIT-Hyderabad Partner to Boost 6G and Telecom Standards

The Telecommunication Engineering Centre (TEC), technical arm of the Department of Telecommunications (DoT), has signed a Memorandum of Understanding (MoU) with the Indian Institute of Technology Hyderabad (IIT Hyderabad) for joint research and technical collaboration in advanced telecom technologies and standardisation. The partnership focuses on developing India-specific standards and test frameworks for next-generation networks, including 6G, Artificial Intelligence (AI), and Non-Terrestrial Networks (NTNs). It also aims to enhance India’s participation in international standardisation f..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Talk to us?