Activists Urge Retention Of Saravanampatti Flyover Plan
ROADS & HIGHWAYS

Activists Urge Retention Of Saravanampatti Flyover Plan

Social activists have urged the Union Ministry of Road Transport and Highways to retain the proposed flyover at Saravanampatti Junction on Sathyamangalam Road and to oppose the National Highways Authority of India's plan to replace it with an at-grade junction improvement. The representation submitted by Coimbatore Consumer Cause argued that an at-grade solution would neither address growing traffic congestion nor improve road safety at the busy intersection. The group framed the flyover and related junction works as measures in the larger public interest.

Officials had sanctioned the project on March nine, 2022 under the Annual Plan 2021-2022 at an estimated cost of Rs 804.8 million (804.8 mn). The original design envisaged a four-lane flyover spanning 1,415 m from Amman Kovil to Saravanampatti and identified the junction as a black spot warranting a grade separator. Activists said the proposed construction was delayed while approval from Chennai Metro Rail Limited was awaited because of a proposed metro corridor.

During the delay the then National Highways wing of the State Highways Department proposed an at-grade junction improvement estimated at around Rs 120 million (120 mn), but tenders were not floated as the road was to be handed over to the NHAI. Activists contend that with the metro rail proposal no longer under consideration and the NHAI now overseeing the road, the flyover should be revived rather than pursuing the at-grade alternative. They recalled that a stakeholders meeting convened by the Coimbatore collector in 2023 had seen objections to the at-grade plan and led to restoration of the flyover proposal.

The organisation compared the situation with the Thudiyalur-Mettupalayam Road junction on NH-67, saying an earlier at-grade improvement had failed to ease congestion and become ineffective. It urged the union government to cancel the NHAI at-grade improvement proposal and proceed with construction of the Saravanampatti flyover from Ammankulam along with comprehensive junction improvements at Kalapatti Road and Thudiyalur Road intersections. The activists argued that only a grade separator would provide a long-term solution to increasing traffic volumes and ensure motorist safety.

Social activists have urged the Union Ministry of Road Transport and Highways to retain the proposed flyover at Saravanampatti Junction on Sathyamangalam Road and to oppose the National Highways Authority of India's plan to replace it with an at-grade junction improvement. The representation submitted by Coimbatore Consumer Cause argued that an at-grade solution would neither address growing traffic congestion nor improve road safety at the busy intersection. The group framed the flyover and related junction works as measures in the larger public interest. Officials had sanctioned the project on March nine, 2022 under the Annual Plan 2021-2022 at an estimated cost of Rs 804.8 million (804.8 mn). The original design envisaged a four-lane flyover spanning 1,415 m from Amman Kovil to Saravanampatti and identified the junction as a black spot warranting a grade separator. Activists said the proposed construction was delayed while approval from Chennai Metro Rail Limited was awaited because of a proposed metro corridor. During the delay the then National Highways wing of the State Highways Department proposed an at-grade junction improvement estimated at around Rs 120 million (120 mn), but tenders were not floated as the road was to be handed over to the NHAI. Activists contend that with the metro rail proposal no longer under consideration and the NHAI now overseeing the road, the flyover should be revived rather than pursuing the at-grade alternative. They recalled that a stakeholders meeting convened by the Coimbatore collector in 2023 had seen objections to the at-grade plan and led to restoration of the flyover proposal. The organisation compared the situation with the Thudiyalur-Mettupalayam Road junction on NH-67, saying an earlier at-grade improvement had failed to ease congestion and become ineffective. It urged the union government to cancel the NHAI at-grade improvement proposal and proceed with construction of the Saravanampatti flyover from Ammankulam along with comprehensive junction improvements at Kalapatti Road and Thudiyalur Road intersections. The activists argued that only a grade separator would provide a long-term solution to increasing traffic volumes and ensure motorist safety.

Related Stories

Gold Stories

Next Story
Resources

Schindler named among Forbes’ World’s Best Employers 2026

Schindler has been named among Forbes’ World’s Best Employers 2026, a global ranking recognising companies for their workplace environments.Compiled by Forbes in partnership with Statista, the ranking is based on independent employee feedback, including whether employees would recommend their organisation to friends and family.The company said the recognition reflected its focus on creating a workplace where employees can develop their expertise and build careers. ..

Next Story
Infrastructure Urban

India needs an export-execution mindset: Vishesh Jain

Interview with Vishesh Jain, Founder & CEO, EximpleWhat gaps in India’s global trade ecosystem led you to build Eximple, and what problem did you see businesses struggling with most?Eximple came out of a problem that all three founders had seen from different choke points in the trade ecosystem. India has millions of MSMEs and manufacturers, and many of them can make products that are genuinely competitive on quality. Yet only a small fraction is able to build meaningful international businesses. In our experience, the gap is usually not manufacturing capability; it is the ability to exe..

Next Story
Building Material

Nuvoco reports 13.5% revenue growth in Q2 FY27

Nuvoco Vistas Corp. Ltd. reported consolidated revenue of Rs 27.9 billion for Q2 FY27, up 13.5% year on year. Cement sales volume rose 9% to 4.7 million tonnes (MMT), while EBITDA increased 11% to Rs 4.11 billion.The company said it began its cement operations in 2014 with a 2.3 MMT per annum (MMTPA) operation at Nimbol. It now aims to reach 35 MMTPA of cement capacity by FY28, nearly 15 times its initial capacity. Its portfolio spans cement, ready-mix concrete and modern building materials.On sustainability and cost efficiency, Nuvoco partnered with CleanMax for a 46.4 MW wind-solar hybrid re..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

SPECIAL OFFER
QR Code