Avinashi Road flyover requires additional 1.65 hectares of land
ROADS & HIGHWAYS

Avinashi Road flyover requires additional 1.65 hectares of land

Coimbatore is progressing with the construction of the Avinashi Road elevated expressway, with approximately 45% of the project already completed. However, the highways department has identified a need for an additional 1.65 hectares of land to continue the development.

A senior official from the state highways department informed TNIE that the construction of the flyover above the railway lines is pending approval from the Southern Railway. Presently, three special gears have been deployed for the installation of the decks. Out of the total 304 decks required, around 115 have been successfully installed.

To accommodate the widened road near the ramp at eight different locations, approximately 1.65 hectares of land is necessary to ensure the project's completion. The department has already submitted the land acquisition file to Chennai. Once the notification is published in the Gazette, the land acquisition process will commence.

Sources state that a budget of approximately Rs 310 crore has been allocated for land acquisition. Landowners who willingly participate in the negotiation meeting can expect to receive 25% more than the market value for their land. The negotiation meeting will be scheduled subsequent to the gazette notification.

Construction of the flyover, which spans 10.01 km in length and 17.25m in width, commenced on December 3, 2020, and is anticipated to conclude in August 2024. The four-lane flyover starts from Uppilipalayam near the police quarters and extends to Goldwins near the KMCH. It will feature ramps at eight different locations, including four entry points and four exit points near Anna Statue, Nava India, Hope College, and the Airport junction.

Coimbatore is progressing with the construction of the Avinashi Road elevated expressway, with approximately 45% of the project already completed. However, the highways department has identified a need for an additional 1.65 hectares of land to continue the development.A senior official from the state highways department informed TNIE that the construction of the flyover above the railway lines is pending approval from the Southern Railway. Presently, three special gears have been deployed for the installation of the decks. Out of the total 304 decks required, around 115 have been successfully installed.To accommodate the widened road near the ramp at eight different locations, approximately 1.65 hectares of land is necessary to ensure the project's completion. The department has already submitted the land acquisition file to Chennai. Once the notification is published in the Gazette, the land acquisition process will commence.Sources state that a budget of approximately Rs 310 crore has been allocated for land acquisition. Landowners who willingly participate in the negotiation meeting can expect to receive 25% more than the market value for their land. The negotiation meeting will be scheduled subsequent to the gazette notification.Construction of the flyover, which spans 10.01 km in length and 17.25m in width, commenced on December 3, 2020, and is anticipated to conclude in August 2024. The four-lane flyover starts from Uppilipalayam near the police quarters and extends to Goldwins near the KMCH. It will feature ramps at eight different locations, including four entry points and four exit points near Anna Statue, Nava India, Hope College, and the Airport junction.

Next Story
Building Material

Suraj Estate Wins Euromoney Award for India’s Best Residential Developer

"Suraj Estate Developers Limited has received the Euromoney Real Estate Award 2025 for ‘India’s Best Residential Developer’, positioning the company among globally benchmarked leaders in the sector. The recognition reflects its four-decade legacy in delivering high-quality residential and redevelopment-led projects across South Central Mumbai. The Euromoney Real Estate Awards, presented by the London-based Euromoney magazine, are widely regarded as one of the most credible global assessments of performance in real estate, banking and finance. Winners are selected through surveys of inte..

Next Story
Building Material

Lloyds Metals, Tata Steel Sign MoU to Explore Strategic Collaboration

"Lloyds Metals and Energy Limited has signed a non-binding Memorandum of Understanding with Tata Steel Limited to evaluate potential areas of strategic cooperation across mining, logistics, pelletisation and steelmaking. The MoU was signed by B Prabhakaran, Managing Director of Lloyds Metals, and Mr T V Narendran, CEO and Managing Director of Tata Steel. The partnership framework aims to leverage the natural operational synergies between both companies and assess opportunities in greenfield steel projects, iron ore mining, slurry pipeline infrastructure, pellet manufacturing in iron ore–ric..

Next Story
Building Material

IndiaAI, Gujarat Govt Host Regional Conclave Ahead of 2026 AI Summit

The IndiaAI Mission under the Ministry of Electronics and Information Technology, along with the Government of Gujarat and IIT Gandhinagar, convened a Regional Pre-Summit Event at Mahatma Mandir, Gandhinagar. The initiative is part of the build-up to the India–AI Impact Summit 2026, scheduled for 15–20 February 2026 at Bharat Mandapam, New Delhi. The conclave brought together senior policymakers, technology leaders, researchers and industry practitioners to examine how AI can accelerate economic, digital and social transformation across sectors. The programme focused on the overarching th..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Advertisement

Open In App