BMC is yet to recover Rs 0.65 billion fine pending for road contractor
ROADS & HIGHWAYS

BMC is yet to recover Rs 0.65 billion fine pending for road contractor

As the company dragged it into arbitration in February, former Colaba corporator Makarand Narwekar from the BJP claimed that BMC is still owed Rs 64.6 billion, which it terminated four months after it handed down a penalty of Rs 16.00 billion to be paid within 30 days for cement concrete (CC) road works in Mumbai for the second time.

This is the first instance in which a contractor has brought the civic body into arbitration following the termination of a contract in recent memory. In the arbitration matter, Narwekar insisted that BMC choose a special counsel. Narwekar stated that, according to the BMC order, the penalty needed to be paid within 30 days. He demanded that the BMC initiate a civil suit against the contractor for the payment of the penalty. He questioned why the BMC was delaying action and allowing the contractor to exploit the civic body. Narwekar emphasised the necessity for the civic body to take firm action against contractors, considering taxpayer funds were involved. He also mentioned that by the onset of the monsoon in June, 50% of the scheduled 397 km of cement concrete (CC) road works in the city were supposed to be completed, but only 25% of that target had been achieved. Narwekar pointed out that CM Eknath Shinde himself had instructed BMC to concrete all roads. He requested municipal commissioner Bhushan Gagrani release a status report on CC roads by June 1. Narwekar stated that out of the 2050-km network of roads in Mumbai, just over 1,200 km had been concretized. In November 2023, BMC terminated RSIIL's contract for the first time for failing to initiate work. Two months later, it awarded CC contracts for 397 km of roads in the eastern and western suburbs worth Rs 60.80 billion. Officials acknowledged that only 25% of this work had been completed. They explained that when RSIIL was awarded its contract in January 2023, 50 stretches were supposed to be ready before the last monsoon. Subsequently, 400 stretches were to be taken up from October 2023 to May 2024, and the last 450 stretches were scheduled for October 2024 to May 2025. Narwekar stated that the achievement of these deadlines could only be ascertained through a status report.

As the company dragged it into arbitration in February, former Colaba corporator Makarand Narwekar from the BJP claimed that BMC is still owed Rs 64.6 billion, which it terminated four months after it handed down a penalty of Rs 16.00 billion to be paid within 30 days for cement concrete (CC) road works in Mumbai for the second time. This is the first instance in which a contractor has brought the civic body into arbitration following the termination of a contract in recent memory. In the arbitration matter, Narwekar insisted that BMC choose a special counsel. Narwekar stated that, according to the BMC order, the penalty needed to be paid within 30 days. He demanded that the BMC initiate a civil suit against the contractor for the payment of the penalty. He questioned why the BMC was delaying action and allowing the contractor to exploit the civic body. Narwekar emphasised the necessity for the civic body to take firm action against contractors, considering taxpayer funds were involved. He also mentioned that by the onset of the monsoon in June, 50% of the scheduled 397 km of cement concrete (CC) road works in the city were supposed to be completed, but only 25% of that target had been achieved. Narwekar pointed out that CM Eknath Shinde himself had instructed BMC to concrete all roads. He requested municipal commissioner Bhushan Gagrani release a status report on CC roads by June 1. Narwekar stated that out of the 2050-km network of roads in Mumbai, just over 1,200 km had been concretized. In November 2023, BMC terminated RSIIL's contract for the first time for failing to initiate work. Two months later, it awarded CC contracts for 397 km of roads in the eastern and western suburbs worth Rs 60.80 billion. Officials acknowledged that only 25% of this work had been completed. They explained that when RSIIL was awarded its contract in January 2023, 50 stretches were supposed to be ready before the last monsoon. Subsequently, 400 stretches were to be taken up from October 2023 to May 2024, and the last 450 stretches were scheduled for October 2024 to May 2025. Narwekar stated that the achievement of these deadlines could only be ascertained through a status report.

Next Story
Infrastructure Transport

Cabinet Approves Key Highway and Rail Projects in Bihar Region

The Union Cabinet on Wednesday approved the four-laning of the 84.2-km Mokama-Munger section of the Buxar-Bhagalpur high-speed corridor, a key industrial region in poll-bound Bihar. The Cabinet also sanctioned the doubling of the 177-km Bhagalpur-Dumka-Rampurhat railway line, which passes through Bihar, Jharkhand, and West Bengal, at a cost of Rs 31.7 billion.The Rs 44.5 billion highway project will be constructed under the hybrid annuity model, a variant of public-private partnership. The Mokama-Munger stretch was the only remaining two-lane section of the 363-km Buxar-Bhagalpur corridor. Fou..

Next Story
Infrastructure Transport

NGT Issues Notice on Bengaluru Twin Tunnel Project

The National Green Tribunal (NGT) on Wednesday issued notices in response to a petition filed by Bengaluru Praja Vedike and others, challenging the Bengaluru twin tunnel road project. Petitioners claim the project was “hastily announced” and bypassed mandatory environmental impact assessment procedures.Notices have been served to the Karnataka Government, Greater Bengaluru Authority, State Environment Impact Assessment Authority (SEIAA), Bengaluru Smart Infrastructure Ltd (B-SMILE), the Union Ministry of Environment, Forest and Climate Change, and project consultants.The 16.74-km twin-tube..

Next Story
Real Estate

India’s Residential Sales to Dip Slightly in FY26

Residential sales in India’s seven major cities are projected to decline by up to 3 per cent year-on-year in FY26 to 620–640 million square feet (msf), amid a moderation in sales velocity, according to ratings agency Icra.In FY25, sales stood at 643 msf, down 8 per cent YoY, following a sharp contraction in new launches and moderated demand in the affordable and mid-income segments. This slowdown came after the sector posted a robust compound annual growth rate of 26 per cent in area sales between FY22 and FY24.Icra noted: “Having seen a strong upcycle, the sector entered an equilibrium ..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Talk to us?