BMC is yet to recover Rs 0.65 billion fine pending for road contractor
ROADS & HIGHWAYS

BMC is yet to recover Rs 0.65 billion fine pending for road contractor

As the company dragged it into arbitration in February, former Colaba corporator Makarand Narwekar from the BJP claimed that BMC is still owed Rs 64.6 billion, which it terminated four months after it handed down a penalty of Rs 16.00 billion to be paid within 30 days for cement concrete (CC) road works in Mumbai for the second time.

This is the first instance in which a contractor has brought the civic body into arbitration following the termination of a contract in recent memory. In the arbitration matter, Narwekar insisted that BMC choose a special counsel. Narwekar stated that, according to the BMC order, the penalty needed to be paid within 30 days. He demanded that the BMC initiate a civil suit against the contractor for the payment of the penalty. He questioned why the BMC was delaying action and allowing the contractor to exploit the civic body. Narwekar emphasised the necessity for the civic body to take firm action against contractors, considering taxpayer funds were involved. He also mentioned that by the onset of the monsoon in June, 50% of the scheduled 397 km of cement concrete (CC) road works in the city were supposed to be completed, but only 25% of that target had been achieved. Narwekar pointed out that CM Eknath Shinde himself had instructed BMC to concrete all roads. He requested municipal commissioner Bhushan Gagrani release a status report on CC roads by June 1. Narwekar stated that out of the 2050-km network of roads in Mumbai, just over 1,200 km had been concretized. In November 2023, BMC terminated RSIIL's contract for the first time for failing to initiate work. Two months later, it awarded CC contracts for 397 km of roads in the eastern and western suburbs worth Rs 60.80 billion. Officials acknowledged that only 25% of this work had been completed. They explained that when RSIIL was awarded its contract in January 2023, 50 stretches were supposed to be ready before the last monsoon. Subsequently, 400 stretches were to be taken up from October 2023 to May 2024, and the last 450 stretches were scheduled for October 2024 to May 2025. Narwekar stated that the achievement of these deadlines could only be ascertained through a status report.

As the company dragged it into arbitration in February, former Colaba corporator Makarand Narwekar from the BJP claimed that BMC is still owed Rs 64.6 billion, which it terminated four months after it handed down a penalty of Rs 16.00 billion to be paid within 30 days for cement concrete (CC) road works in Mumbai for the second time. This is the first instance in which a contractor has brought the civic body into arbitration following the termination of a contract in recent memory. In the arbitration matter, Narwekar insisted that BMC choose a special counsel. Narwekar stated that, according to the BMC order, the penalty needed to be paid within 30 days. He demanded that the BMC initiate a civil suit against the contractor for the payment of the penalty. He questioned why the BMC was delaying action and allowing the contractor to exploit the civic body. Narwekar emphasised the necessity for the civic body to take firm action against contractors, considering taxpayer funds were involved. He also mentioned that by the onset of the monsoon in June, 50% of the scheduled 397 km of cement concrete (CC) road works in the city were supposed to be completed, but only 25% of that target had been achieved. Narwekar pointed out that CM Eknath Shinde himself had instructed BMC to concrete all roads. He requested municipal commissioner Bhushan Gagrani release a status report on CC roads by June 1. Narwekar stated that out of the 2050-km network of roads in Mumbai, just over 1,200 km had been concretized. In November 2023, BMC terminated RSIIL's contract for the first time for failing to initiate work. Two months later, it awarded CC contracts for 397 km of roads in the eastern and western suburbs worth Rs 60.80 billion. Officials acknowledged that only 25% of this work had been completed. They explained that when RSIIL was awarded its contract in January 2023, 50 stretches were supposed to be ready before the last monsoon. Subsequently, 400 stretches were to be taken up from October 2023 to May 2024, and the last 450 stretches were scheduled for October 2024 to May 2025. Narwekar stated that the achievement of these deadlines could only be ascertained through a status report.

Next Story
Resources

Skyview by Empyrean is Making Benchmarks in the Indian Ropeway Industry

FIL Industries Private Limited, the parent company of Empyrean Skyview Projects that pioneered ropeway mobility solutions in India with Jammu’s Skyview Gondola, is currently developing the Dehradun-Mussoorie ropeway and is on track to complete Phase I by September 2026. The ropeway is set to be India’s longest passenger aerial monocable covering 5.8 km between the foothills of Dehradun in Purkulgam and MDDA taxi stand in the hills of Mussoorie in just under 20 minutes. The firm pioneered green mobility solutions in India with the development of the flagship Skyview Gondola in Jam..

Next Story
Technology

Creativity is for Humans, Productivity is for Robots!

On most construction sites, the rhythm of progress is measured by the clang of steel, the hum of machinery and the sweat of thousands. But increasingly, new sounds are entering the mix: the quiet efficiency of algorithms, the hum of drones overhead, and the precision of robotic arms at work. Behind the concrete and cables, an invisible force is taking hold: data. It is turning blueprints into living simulations, managing fleets of machines, and helping engineers make decisions before a single brick is laid. This is not the construction of tomorrow; it is the architecture of today – built on ..

Next Story
Infrastructure Urban

Bhartiya Urban Unveils ‘Bhartiya Converge’ GCC Enablement Platform

Bhartiya Urban has launched Bhartiya Converge, its latest business venture designed to become India’s premier platform for enabling Global Capability Centres (GCCs). The initiative offers an integrated ecosystem aimed at helping global clients gain a competitive edge in today’s rapidly evolving business environment. Focused on enhancing turnaround time and operational efficiencies, the company seeks to deliver better business outcomes powered by top-tier talent. Bhartiya Converge presents a customised and integrated suite of microservices that addresses the nuanced and evolving operational..

Advertisement

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Advertisement

Talk to us?