Bridge execution delays impact on cost-overun
ROADS & HIGHWAYS

Bridge execution delays impact on cost-overun

When the construction of a bridge faces delays, the cost overrun is much higher compared to any other road or rail projects.

Hardik Agrawal, Director, Dineshchandra R Agrawal Infracon, says “Bridge construction is heavily dependent on construction materials such as cement and steel, which are price-sensitive. If the material cost is quantified compared to the overall project cost, it is much higher than any other segment.”

The most complex bridge projects are the ones across deep valleys, wide rivers and sea crossings. “Geological surprises at the foundation are among the complexities involved,” says NN Sinha, Chairman, National Highways Authority of India (NHAI), and Managing Director, National Highways & Infrastructure Development Corporation (NHIDCL). “Technical expertise, in terms of design and supervision, is shallow, leading many clients to look to foreign shores. Also, lack of local manufacturing and testing of advanced materials such as cables, weathered steel and fibre-reinforcement are other weaknesses.”


RVR Kishore, Project Director, Hindustan Construction Company, agrees that the challenges in bridge construction basically revolve around the geology of the river. “Detailed investigation and preliminary planning are crucial and should be done by the client or contractor,” he suggests. “It is important to first determine the construction methodology, followed by the design of the structure.”


For his part, Vivek Gautam, COO - Strategic Business Group – Core Infra, Tata Projects, points to complexities such as terrain type, RoW, vehicular traffic congestion, dense urban localities and green and regulatory clearances. He mentions the company’s recent project involving DMRC’s 9.63-km Dilshad Garden-Ghaziabad New Bus Adda elevated metro extension. “It included a 170-m bridge across Hindon River. The bridge section was challenging as it was on the upstream side of the river barrage and almost full of water. To reduce time and overcome challenges, we opted for the precast method and the bridge was executed in two parts, thereby safely completing it within 180 days.”


Nitesh Kumar Asati, Joint General Manager, IRCON, says, “Various challenges in bridge construction include selection of girders and bearings, methodology of stressing, finalisation of borrow pits, launching schemes, CRS inspection, etc, with all quality and safety standards as per the statutory requirement. However, use of specialised equipment and technology will definitely help in ensuring timely project completion. During construction, we need to ensure the achievement of various milestones as per the programme submitted by the agency by conducting regular progress review meetings with our agencies and the client. It is imperative for a dedicated team to focus on the various sequential and parallel activities of a bridge, which is a great managerial challenge.”


Referring to Bogibeel Bridge as a feather in the cap of Indian Railway engineers, HCC and Gammon, Shashikant Limaye, Member Expert Committee, Pune Metro Project, says, “Several new technologies were used in this bridge comprising 124-m span steel through girders with a composite RCC deck carrying a two-lane road.” He further mentions the Chenab Bridge along the Udhampur-Srinagar Rail Link, which comprises a 467-m steel truss arch span rising 350 m above the riverbed, as a unique example of a bridge in an earthquake-prone region. Afcons is steadfastly making progress on this unique project. A 145-m-tall viaduct on the Jiribaum-Tupul Railway Line between Silchar and Manipur is another unique project in progress.


That said, if we were to compare India’s approach to bridge construction to other parts of the world, we are still at a nascent stage. However, with the 20-km MTHL and several other bridges coming up across the Ganga and Brahmaputra, the future is bright – and connected!


SHRIYAL SETHUMADHAVAN

When the construction of a bridge faces delays, the cost overrun is much higher compared to any other road or rail projects.Hardik Agrawal, Director, Dineshchandra R Agrawal Infracon, says “Bridge construction is heavily dependent on construction materials such as cement and steel, which are price-sensitive. If the material cost is quantified compared to the overall project cost, it is much higher than any other segment.”The most complex bridge projects are the ones across deep valleys, wide rivers and sea crossings. “Geological surprises at the foundation are among the complexities involved,” says NN Sinha, Chairman, National Highways Authority of India (NHAI), and Managing Director, National Highways & Infrastructure Development Corporation (NHIDCL). “Technical expertise, in terms of design and supervision, is shallow, leading many clients to look to foreign shores. Also, lack of local manufacturing and testing of advanced materials such as cables, weathered steel and fibre-reinforcement are other weaknesses.”RVR Kishore, Project Director, Hindustan Construction Company, agrees that the challenges in bridge construction basically revolve around the geology of the river. “Detailed investigation and preliminary planning are crucial and should be done by the client or contractor,” he suggests. “It is important to first determine the construction methodology, followed by the design of the structure.” For his part, Vivek Gautam, COO - Strategic Business Group – Core Infra, Tata Projects, points to complexities such as terrain type, RoW, vehicular traffic congestion, dense urban localities and green and regulatory clearances. He mentions the company’s recent project involving DMRC’s 9.63-km Dilshad Garden-Ghaziabad New Bus Adda elevated metro extension. “It included a 170-m bridge across Hindon River. The bridge section was challenging as it was on the upstream side of the river barrage and almost full of water. To reduce time and overcome challenges, we opted for the precast method and the bridge was executed in two parts, thereby safely completing it within 180 days.”Nitesh Kumar Asati, Joint General Manager, IRCON, says, “Various challenges in bridge construction include selection of girders and bearings, methodology of stressing, finalisation of borrow pits, launching schemes, CRS inspection, etc, with all quality and safety standards as per the statutory requirement. However, use of specialised equipment and technology will definitely help in ensuring timely project completion. During construction, we need to ensure the achievement of various milestones as per the programme submitted by the agency by conducting regular progress review meetings with our agencies and the client. It is imperative for a dedicated team to focus on the various sequential and parallel activities of a bridge, which is a great managerial challenge.”Referring to Bogibeel Bridge as a feather in the cap of Indian Railway engineers, HCC and Gammon, Shashikant Limaye, Member Expert Committee, Pune Metro Project, says, “Several new technologies were used in this bridge comprising 124-m span steel through girders with a composite RCC deck carrying a two-lane road.” He further mentions the Chenab Bridge along the Udhampur-Srinagar Rail Link, which comprises a 467-m steel truss arch span rising 350 m above the riverbed, as a unique example of a bridge in an earthquake-prone region. Afcons is steadfastly making progress on this unique project. A 145-m-tall viaduct on the Jiribaum-Tupul Railway Line between Silchar and Manipur is another unique project in progress.That said, if we were to compare India’s approach to bridge construction to other parts of the world, we are still at a nascent stage. However, with the 20-km MTHL and several other bridges coming up across the Ganga and Brahmaputra, the future is bright – and connected!SHRIYAL SETHUMADHAVAN

Next Story
Infrastructure Transport

Cabinet Clears Rs 15.07 Bn Greenfield Airport Project in Kota-Bundi

The Cabinet Committee on Economic Affairs, chaired by Prime Minister Narendra Modi, has approved the Airports Authority of India’s (AAI) proposal for the development of a Greenfield Airport at Kota-Bundi, Rajasthan, at an estimated cost of Rs 15.07 billion.Kota, located on the banks of the Chambal River, is widely recognised as the industrial capital of Rajasthan and a prominent educational coaching hub. To support the region’s growing needs, the Government of Rajasthan has handed over 440.06 hectares of land to AAI for the project.The new Greenfield Airport will be designed to handle oper..

Next Story
Infrastructure Urban

Govt may extend MSME NPA classification period to 180 days

The Union government is considering a proposal to extend the non-performing asset (NPA) classification period for loans to micro, small and medium enterprises (MSMEs) from the existing 90 days to 180 days, according to a senior government official who requested anonymity.“The proposal to extend the loan default period for MSMEs from 90 days to 180 days is likely to be taken up by the Cabinet soon,” the official said.The move is expected to provide relief to cash-strapped MSMEs, especially against the backdrop of steep US tariffs, giving them more time to regularise their loan repayments.Ne..

Next Story
Infrastructure Urban

FedEx, IIT Madras Launch SMART Centre for Sustainable, AI-led Logistics

FedEx has partnered with the Indian Institute of Technology (IIT) Madras to inaugurate the SMART Centre (Supply Chain Modelling, Algorithms, Research and Technology Centre) on the institute’s campus. The facility will drive innovation in sustainable and AI-driven logistics solutions. Backed by a five-year $5 million grant from FedEx, the SMART Centre aims to combine advanced research, digital technologies, and industry expertise to transform supply chains with a focus on agility, resilience, and environmental responsibility.The centre will also spearhead interdisciplinary projects in ar..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Talk to us?