Coimbatore western bypass on the fast track; phase one ready by 2025
ROADS & HIGHWAYS

Coimbatore western bypass on the fast track; phase one ready by 2025

The wait for improved traffic flow in Coimbatore might be nearing its end. The city's highway department is accelerating efforts to complete the first phase of the long-awaited western bypass project by August 2025.

This 32-kilometer project is divided into three phases. Phase one is seeing significant progress, with construction underway on an 11.8-kilometer, four-lane road stretching from Madukkarai to Madhampatti. The estimated cost for this initial phase is Rs 2 billion. While initial delays due to sand availability have been addressed, the department is pushing forward to complete the remaining work swiftly.

Progress is also being made on land acquisition for the subsequent phases. The second phase, covering nearly 10 kilometers from Madhampatti to Kanuvai, has already achieved 70% completion in land acquisition. To secure government funding, the department is aiming to finalise 90% of land acquisition within the next month. Land acquisition efforts have also begun for the final phase of the project.

However, K. Kathirmathiyon, Secretary, Coimbatore Consumer Cause, expressed concerns about potential delays. He emphasised the importance of thorough government planning to avoid project delays exceeding a year. He's also observed a tendency for project scopes to change mid-stream, sometimes leading to cancellations or downsizing. For Coimbatore, a city accustomed to delays, Kathirmathiyon urged the government to set clear timelines for land acquisition, especially if there are no legal roadblocks.

(Source: News18)

The wait for improved traffic flow in Coimbatore might be nearing its end. The city's highway department is accelerating efforts to complete the first phase of the long-awaited western bypass project by August 2025. This 32-kilometer project is divided into three phases. Phase one is seeing significant progress, with construction underway on an 11.8-kilometer, four-lane road stretching from Madukkarai to Madhampatti. The estimated cost for this initial phase is Rs 2 billion. While initial delays due to sand availability have been addressed, the department is pushing forward to complete the remaining work swiftly. Progress is also being made on land acquisition for the subsequent phases. The second phase, covering nearly 10 kilometers from Madhampatti to Kanuvai, has already achieved 70% completion in land acquisition. To secure government funding, the department is aiming to finalise 90% of land acquisition within the next month. Land acquisition efforts have also begun for the final phase of the project. However, K. Kathirmathiyon, Secretary, Coimbatore Consumer Cause, expressed concerns about potential delays. He emphasised the importance of thorough government planning to avoid project delays exceeding a year. He's also observed a tendency for project scopes to change mid-stream, sometimes leading to cancellations or downsizing. For Coimbatore, a city accustomed to delays, Kathirmathiyon urged the government to set clear timelines for land acquisition, especially if there are no legal roadblocks. (Source: News18)

Next Story
Infrastructure Urban

VECV Sales Rise 7.8 Per Cent In May 2026

VE Commercial Vehicles recorded sales of 7,978 units in May 2026, compared to 7,401 units in May 2025, registering growth of 7.8 per cent. This included 7,789 units from the Eicher brand and 189 units from the Volvo brand.Eicher branded trucks and buses reported sales of 7,789 units during the month, up 7.3 per cent from 7,258 units a year earlier. In the domestic commercial vehicle market, Eicher sales rose 9.1 per cent to 7,375 units from 6,758 units in May 2025.Exports declined 17.2 per cent to 414 units from 500 units in the corresponding month last year. Volvo Trucks and Volvo Buses recor..

Next Story
Infrastructure Urban

Table Space Strengthens DESYN Leadership Team

Table Space has announced strategic leadership appointments within DESYN, its integrated Design and Build business, as it looks to strengthen operations across key enterprise and GCC markets in India. DESYN was launched as a strategic extension of Table Space’s workspace solutions portfolio to meet rising demand for agile, high-quality and rapidly deployable enterprise workspaces.Shruti Ookabhoy has joined DESYN as Executive Director and will lead the Design vertical, focusing on design capability, operational excellence and team development across markets. She brings over 22 years of experi..

Next Story
Infrastructure Transport

Concord Associate Bags Rs 2.79 Bn Kavach Order

Concord Control Systems said its associate company, Progota India, has received a Rs 2.79 bn domestic order from Indian Railways for the supply, installation, testing and commissioning of on-board Kavach 4.0 loco equipment.The order is scheduled for execution within 12 months and strengthens Concord’s role in India’s railway safety and signalling ecosystem. Kavach is India’s indigenous automatic train protection system, designed to improve operational safety by helping prevent signal passing at danger and reducing collision risks.Gaurav Lath, Joint Managing Director, Concord Control Syst..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

-->