Coimbatore western bypass on the fast track; phase one ready by 2025
ROADS & HIGHWAYS

Coimbatore western bypass on the fast track; phase one ready by 2025

The wait for improved traffic flow in Coimbatore might be nearing its end. The city's highway department is accelerating efforts to complete the first phase of the long-awaited western bypass project by August 2025.

This 32-kilometer project is divided into three phases. Phase one is seeing significant progress, with construction underway on an 11.8-kilometer, four-lane road stretching from Madukkarai to Madhampatti. The estimated cost for this initial phase is Rs 2 billion. While initial delays due to sand availability have been addressed, the department is pushing forward to complete the remaining work swiftly.

Progress is also being made on land acquisition for the subsequent phases. The second phase, covering nearly 10 kilometers from Madhampatti to Kanuvai, has already achieved 70% completion in land acquisition. To secure government funding, the department is aiming to finalise 90% of land acquisition within the next month. Land acquisition efforts have also begun for the final phase of the project.

However, K. Kathirmathiyon, Secretary, Coimbatore Consumer Cause, expressed concerns about potential delays. He emphasised the importance of thorough government planning to avoid project delays exceeding a year. He's also observed a tendency for project scopes to change mid-stream, sometimes leading to cancellations or downsizing. For Coimbatore, a city accustomed to delays, Kathirmathiyon urged the government to set clear timelines for land acquisition, especially if there are no legal roadblocks.

(Source: News18)

The wait for improved traffic flow in Coimbatore might be nearing its end. The city's highway department is accelerating efforts to complete the first phase of the long-awaited western bypass project by August 2025. This 32-kilometer project is divided into three phases. Phase one is seeing significant progress, with construction underway on an 11.8-kilometer, four-lane road stretching from Madukkarai to Madhampatti. The estimated cost for this initial phase is Rs 2 billion. While initial delays due to sand availability have been addressed, the department is pushing forward to complete the remaining work swiftly. Progress is also being made on land acquisition for the subsequent phases. The second phase, covering nearly 10 kilometers from Madhampatti to Kanuvai, has already achieved 70% completion in land acquisition. To secure government funding, the department is aiming to finalise 90% of land acquisition within the next month. Land acquisition efforts have also begun for the final phase of the project. However, K. Kathirmathiyon, Secretary, Coimbatore Consumer Cause, expressed concerns about potential delays. He emphasised the importance of thorough government planning to avoid project delays exceeding a year. He's also observed a tendency for project scopes to change mid-stream, sometimes leading to cancellations or downsizing. For Coimbatore, a city accustomed to delays, Kathirmathiyon urged the government to set clear timelines for land acquisition, especially if there are no legal roadblocks. (Source: News18)

Related Stories

Gold Stories

Next Story
Products

Koemmerling opens Navi Mumbai experience centre

Koemmerling, a brand of the profine Group, has expanded its presence in the Mumbai metropolitan region with the opening of a new experience centre in Navi Mumbai and launched its Allure S46 minimal sliding door system for the Indian market.Located in CBD Belapur, the facility was inaugurated by Peter Mrosik, Owner and CEO, profine Group, along with Farid Khan, Chairman and Managing Director, profine India, and Kamal Bajaj, CEO, profine India.The company said the new centre will showcase its portfolio of uPVC and aluminium window and door systems to architects, developers and homeowners.The ina..

Next Story
Products

India's waterproofing market nears Rs 150 bn milestone

India's waterproofing industry is approaching a market size of Rs 150 billion and is expected to surpass the $2 billion milestone, according to speakers at the 2nd India International Waterproofers Conference & Expo 2026 organised by the Waterproofers Association of India (WAI) in New Delhi.The two-day event brought together more than 20 speakers, 55 international delegates and 53 exhibition booths, with discussions focusing on climate-resilient construction, advanced waterproofing technologies and international collaboration.Inaugurating the event, Durga Shanker Mishra, former Secretary, ..

Next Story
Real Estate

Dilip Buildcon Q1 FY27 Revenue at Rs 23.78 billion

Dilip Buildcon Limited reported consolidated revenue from operations of Rs 2,378 crore in Q1 FY27, along with EBITDA of Rs 429 crore and profit after tax of Rs 128 crore.Consolidated EBITDA margin stood at 18.1%, improving from 17.1% in Q4 FY26. On a standalone basis, revenue from operations was Rs 1,930 crore, EBITDA stood at Rs 199 crore and PAT was Rs 39 crore, with an EBITDA margin of 10.3%.The company’s order book stood at Rs 27,691 crore as of 30 June 2026, compared with Rs 28,830 crore as of 31 March 2026. Roads and highways accounted for 17.1% of the order book, irrigation and water ..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement