Coimbatore western bypass on the fast track; phase one ready by 2025
ROADS & HIGHWAYS

Coimbatore western bypass on the fast track; phase one ready by 2025

The wait for improved traffic flow in Coimbatore might be nearing its end. The city's highway department is accelerating efforts to complete the first phase of the long-awaited western bypass project by August 2025.

This 32-kilometer project is divided into three phases. Phase one is seeing significant progress, with construction underway on an 11.8-kilometer, four-lane road stretching from Madukkarai to Madhampatti. The estimated cost for this initial phase is Rs 2 billion. While initial delays due to sand availability have been addressed, the department is pushing forward to complete the remaining work swiftly.

Progress is also being made on land acquisition for the subsequent phases. The second phase, covering nearly 10 kilometers from Madhampatti to Kanuvai, has already achieved 70% completion in land acquisition. To secure government funding, the department is aiming to finalise 90% of land acquisition within the next month. Land acquisition efforts have also begun for the final phase of the project.

However, K. Kathirmathiyon, Secretary, Coimbatore Consumer Cause, expressed concerns about potential delays. He emphasised the importance of thorough government planning to avoid project delays exceeding a year. He's also observed a tendency for project scopes to change mid-stream, sometimes leading to cancellations or downsizing. For Coimbatore, a city accustomed to delays, Kathirmathiyon urged the government to set clear timelines for land acquisition, especially if there are no legal roadblocks.

(Source: News18)

The wait for improved traffic flow in Coimbatore might be nearing its end. The city's highway department is accelerating efforts to complete the first phase of the long-awaited western bypass project by August 2025. This 32-kilometer project is divided into three phases. Phase one is seeing significant progress, with construction underway on an 11.8-kilometer, four-lane road stretching from Madukkarai to Madhampatti. The estimated cost for this initial phase is Rs 2 billion. While initial delays due to sand availability have been addressed, the department is pushing forward to complete the remaining work swiftly. Progress is also being made on land acquisition for the subsequent phases. The second phase, covering nearly 10 kilometers from Madhampatti to Kanuvai, has already achieved 70% completion in land acquisition. To secure government funding, the department is aiming to finalise 90% of land acquisition within the next month. Land acquisition efforts have also begun for the final phase of the project. However, K. Kathirmathiyon, Secretary, Coimbatore Consumer Cause, expressed concerns about potential delays. He emphasised the importance of thorough government planning to avoid project delays exceeding a year. He's also observed a tendency for project scopes to change mid-stream, sometimes leading to cancellations or downsizing. For Coimbatore, a city accustomed to delays, Kathirmathiyon urged the government to set clear timelines for land acquisition, especially if there are no legal roadblocks. (Source: News18)

Related Stories

Gold Stories

Next Story
Real Estate

Anshul Singhal launches Vantrock with Rs 42 billion development plan

Real estate professional Anshul Singhal has launched Vantrock Real Assets Private Limited (VRAPL), a Mumbai-headquartered platform focused initially on warehousing, industrial and logistics parks. The company plans to develop approximately 11.5 million sq ft of assets, with an estimated gross development value (GDV) of Rs 42 billion (approximately USD 434 million) on completion.The first phase will cover around 3 million sq ft across the National Capital Region (NCR), Bengaluru and Pune, with an estimated development value of Rs 11 billion (approximately USD 113 million). Construction is sched..

Next Story
Infrastructure Transport

Afcons wins CII award for biodiversity management

Afcons Infrastructure has received the Confederation of Indian Industry (CII) National Award for Environmental Best Practices 2026 in the Biodiversity Management category for its work on the Mumbai-Ahmedabad High Speed Rail Project’s C-2 package.The award was presented at a ceremony in Chennai on 9 October 2026. It was received by Mihir Mishra, Vice-President, CPE, and Sumon Paul, Assistant General Manager, HSE, along with the Afcons team.The project adopted several resource recovery and waste management practices. These included recycling concrete washout waste to recover sand, aggregates a..

Next Story
Technology

Indian businesses lead globally in planned AI investment, says Autodesk

Indian organisations are moving towards deeper integration of artificial intelligence (AI), digital technologies and sustainability into business operations, according to Autodesk’s 2026 State of Design & Make report. The fourth edition of the annual study highlights growing AI adoption, measurable outcomes from digital transformation and the role of sustainability in long-term business growth.The report found that 64 per cent of Indian organisations are approaching or have achieved their current AI goals. While 88 per cent believe AI will enhance their industry, up from 78 per cent in 2..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

SPECIAL OFFER
QR Code