Coimbatore western bypass on the fast track; phase one ready by 2025
ROADS & HIGHWAYS

Coimbatore western bypass on the fast track; phase one ready by 2025

The wait for improved traffic flow in Coimbatore might be nearing its end. The city's highway department is accelerating efforts to complete the first phase of the long-awaited western bypass project by August 2025.

This 32-kilometer project is divided into three phases. Phase one is seeing significant progress, with construction underway on an 11.8-kilometer, four-lane road stretching from Madukkarai to Madhampatti. The estimated cost for this initial phase is Rs 2 billion. While initial delays due to sand availability have been addressed, the department is pushing forward to complete the remaining work swiftly.

Progress is also being made on land acquisition for the subsequent phases. The second phase, covering nearly 10 kilometers from Madhampatti to Kanuvai, has already achieved 70% completion in land acquisition. To secure government funding, the department is aiming to finalise 90% of land acquisition within the next month. Land acquisition efforts have also begun for the final phase of the project.

However, K. Kathirmathiyon, Secretary, Coimbatore Consumer Cause, expressed concerns about potential delays. He emphasised the importance of thorough government planning to avoid project delays exceeding a year. He's also observed a tendency for project scopes to change mid-stream, sometimes leading to cancellations or downsizing. For Coimbatore, a city accustomed to delays, Kathirmathiyon urged the government to set clear timelines for land acquisition, especially if there are no legal roadblocks.

(Source: News18)

The wait for improved traffic flow in Coimbatore might be nearing its end. The city's highway department is accelerating efforts to complete the first phase of the long-awaited western bypass project by August 2025. This 32-kilometer project is divided into three phases. Phase one is seeing significant progress, with construction underway on an 11.8-kilometer, four-lane road stretching from Madukkarai to Madhampatti. The estimated cost for this initial phase is Rs 2 billion. While initial delays due to sand availability have been addressed, the department is pushing forward to complete the remaining work swiftly. Progress is also being made on land acquisition for the subsequent phases. The second phase, covering nearly 10 kilometers from Madhampatti to Kanuvai, has already achieved 70% completion in land acquisition. To secure government funding, the department is aiming to finalise 90% of land acquisition within the next month. Land acquisition efforts have also begun for the final phase of the project. However, K. Kathirmathiyon, Secretary, Coimbatore Consumer Cause, expressed concerns about potential delays. He emphasised the importance of thorough government planning to avoid project delays exceeding a year. He's also observed a tendency for project scopes to change mid-stream, sometimes leading to cancellations or downsizing. For Coimbatore, a city accustomed to delays, Kathirmathiyon urged the government to set clear timelines for land acquisition, especially if there are no legal roadblocks. (Source: News18)

Next Story
Infrastructure Transport

Large Format Store Planned At M G Road Metro Station

M G Road station in Bengaluru is set to host the city’s first large-format commercial and experience space, with planning led by Bangalore Metro Rail Corporation Limited. BMRCL has invited proposals to develop and operate a central business district destination at the Purple?Pink Line interchange. The plan positions the station as a commercial hub designed to serve a broad commuter base across the city. The proposal is part of a broader effort to activate transit nodes commercially. Tender documents set a minimum monthly rental of Rs 0.944 million (mn), inclusive of GST, for the large-format..

Next Story
Infrastructure Energy

Government Cancels Auction Of Eleven Critical Mineral Blocks

The government has cancelled the auction of 11 critical and strategic mineral blocks after receiving a poor investor response and failing to attract a sufficient number of qualified bidders. The decision represents a setback to plans to ramp up domestic exploration and production of critical minerals amid global supply chain disruptions and rising demand for materials used in clean energy and advanced technologies. The mines ministry issued an annulment notice setting out the reasons for the cancellations. The annulment notice indicated that the auction process for five mineral blocks was canc..

Next Story
Infrastructure Energy

Gujarat Pushes Biogas Growth With 193 Operational Units

Gujarat has operationalised 193 biogas plants across the state and is planning to add 60 more units as part of a broader push to scale up clean and sustainable energy solutions. The existing plants, established under various government-supported schemes, process organic waste including cattle dung and agricultural residue to produce biogas and a nutrient-rich slurry. The output is mainly used for cooking and other energy needs in rural and semi-urban communities, while also improving local waste management practices. The Gujarat Energy Development Agency (GEDA) is leading the initiative and is..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement