Coimbatore western bypass on the fast track; phase one ready by 2025
ROADS & HIGHWAYS

Coimbatore western bypass on the fast track; phase one ready by 2025

The wait for improved traffic flow in Coimbatore might be nearing its end. The city's highway department is accelerating efforts to complete the first phase of the long-awaited western bypass project by August 2025.

This 32-kilometer project is divided into three phases. Phase one is seeing significant progress, with construction underway on an 11.8-kilometer, four-lane road stretching from Madukkarai to Madhampatti. The estimated cost for this initial phase is Rs 2 billion. While initial delays due to sand availability have been addressed, the department is pushing forward to complete the remaining work swiftly.

Progress is also being made on land acquisition for the subsequent phases. The second phase, covering nearly 10 kilometers from Madhampatti to Kanuvai, has already achieved 70% completion in land acquisition. To secure government funding, the department is aiming to finalise 90% of land acquisition within the next month. Land acquisition efforts have also begun for the final phase of the project.

However, K. Kathirmathiyon, Secretary, Coimbatore Consumer Cause, expressed concerns about potential delays. He emphasised the importance of thorough government planning to avoid project delays exceeding a year. He's also observed a tendency for project scopes to change mid-stream, sometimes leading to cancellations or downsizing. For Coimbatore, a city accustomed to delays, Kathirmathiyon urged the government to set clear timelines for land acquisition, especially if there are no legal roadblocks.

(Source: News18)

The wait for improved traffic flow in Coimbatore might be nearing its end. The city's highway department is accelerating efforts to complete the first phase of the long-awaited western bypass project by August 2025. This 32-kilometer project is divided into three phases. Phase one is seeing significant progress, with construction underway on an 11.8-kilometer, four-lane road stretching from Madukkarai to Madhampatti. The estimated cost for this initial phase is Rs 2 billion. While initial delays due to sand availability have been addressed, the department is pushing forward to complete the remaining work swiftly. Progress is also being made on land acquisition for the subsequent phases. The second phase, covering nearly 10 kilometers from Madhampatti to Kanuvai, has already achieved 70% completion in land acquisition. To secure government funding, the department is aiming to finalise 90% of land acquisition within the next month. Land acquisition efforts have also begun for the final phase of the project. However, K. Kathirmathiyon, Secretary, Coimbatore Consumer Cause, expressed concerns about potential delays. He emphasised the importance of thorough government planning to avoid project delays exceeding a year. He's also observed a tendency for project scopes to change mid-stream, sometimes leading to cancellations or downsizing. For Coimbatore, a city accustomed to delays, Kathirmathiyon urged the government to set clear timelines for land acquisition, especially if there are no legal roadblocks. (Source: News18)

Next Story
Technology

Six ways a smarter workflow leads to faster, more accurate bids

In today’s fast-paced civil construction environment, estimators need more than just solid numbers. They need smart, streamlined processes. This article explores six key ways connected workflows can transform the estimated approach, help in minimising risk, move faster, and improve accuracy. By integrating tools, data, and teams, one can produce stronger bids with less rework, fewer surprises, and more confidence. As an estimator, the job goes beyond producing numbers. They are responsible for delivering bids that are fast, accurate, and built to win. In today’s civil construction ind..

Next Story
Real Estate

Experion Launches Women-Only Co-Living Project in Greater Noida

Experion, part of Singapore-based AT Capital Group, has launched its first co-living space under its managed rental housing brand, VLIV, in Greater Noida. The all-women residence features 730 twin-sharing beds with a strong focus on safety, comfort, and well-being. VLIV has committed a $300 million investment to create a structured, service-led rental housing ecosystem in India. The brand aims to scale up to 20,000 beds in the next few years, with a long-term target of 100,000 beds nationwide. “India’s rental housing is fragmented. VLIV is our way of building long-term, dependabl..

Next Story
Infrastructure Urban

Officine Maccaferri Acquires CPT to Bolster Tunnelling Tech

Ambienta’s platform company, Officine Maccaferri S.p.A., has acquired CPT Group, a leading Italian developer of robotic prefabrication systems and digital control technologies for mechanised tunnelling. The move positions Maccaferri as a global player in integrated tunnelling solutions, blending traditional and advanced mechanised systems. Based in Nova Milanese, CPT serves major global contractors across Europe, Southeast Asia, and Australia. The company offers robotic prefabrication (Robofactory), productivity-monitoring software for Tunnel Boring Machines (TBMs), and eco-designed spa..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Talk to us?