DC Ganderbal Reviews Srinagar Ring Road Phase-II, Phase-IIA
ROADS & HIGHWAYS

DC Ganderbal Reviews Srinagar Ring Road Phase-II, Phase-IIA

Ganderbal Deputy Commissioner Shreya Singhal chaired a meeting on November 23 to review the progress of the ongoing Srinagar Ring Road Phase-II and Phase-IIA projects. The meeting focused on execution-related issues and measures required to keep work moving along the project alignments.

Officials presented a detailed account of the status of both projects, covering highway construction, structural works, land acquisition and the disbursement of compensation. The review also considered bottlenecks that could affect the timely execution of work and the need for coordinated action by the departments and agencies involved.

The meeting discussed a traffic management plan proposed by the National Highways Authority of India (NHAI) for the construction period. Singhal directed the Traffic Police, Civil Police, Revenue authorities and NHAI to jointly prepare a comprehensive plan to address potential disruptions and maintain smooth vehicular movement while construction is under way.

The Deputy Commissioner emphasised close coordination among all concerned departments and executing agencies. She instructed officials to follow the timelines fixed during the meeting and stressed that identified issues should be resolved on priority to support the timely completion of the projects.

Singhal also underlined the need to minimise inconvenience to the general public during the works. The meeting was attended by the Additional Deputy Commissioner, Ganderbal; Assistant Commissioner Revenue, Ganderbal; Superintending Engineers from Public Works (Roads and Buildings), Kashmir Power Distribution Corporation and NHAI; Executive Engineers from Irrigation and Flood Control and Public Health Engineering; Tehsildars of Lar and Wakura; and other concerned officials.

The review brought together administrative, engineering, revenue, policing and executing authorities responsible for different aspects of the projects. Their discussions covered both physical progress and supporting requirements, including compensation payments, land-related matters and arrangements for managing traffic during construction.

Ganderbal Deputy Commissioner Shreya Singhal chaired a meeting on November 23 to review the progress of the ongoing Srinagar Ring Road Phase-II and Phase-IIA projects. The meeting focused on execution-related issues and measures required to keep work moving along the project alignments. Officials presented a detailed account of the status of both projects, covering highway construction, structural works, land acquisition and the disbursement of compensation. The review also considered bottlenecks that could affect the timely execution of work and the need for coordinated action by the departments and agencies involved. The meeting discussed a traffic management plan proposed by the National Highways Authority of India (NHAI) for the construction period. Singhal directed the Traffic Police, Civil Police, Revenue authorities and NHAI to jointly prepare a comprehensive plan to address potential disruptions and maintain smooth vehicular movement while construction is under way. The Deputy Commissioner emphasised close coordination among all concerned departments and executing agencies. She instructed officials to follow the timelines fixed during the meeting and stressed that identified issues should be resolved on priority to support the timely completion of the projects. Singhal also underlined the need to minimise inconvenience to the general public during the works. The meeting was attended by the Additional Deputy Commissioner, Ganderbal; Assistant Commissioner Revenue, Ganderbal; Superintending Engineers from Public Works (Roads and Buildings), Kashmir Power Distribution Corporation and NHAI; Executive Engineers from Irrigation and Flood Control and Public Health Engineering; Tehsildars of Lar and Wakura; and other concerned officials. The review brought together administrative, engineering, revenue, policing and executing authorities responsible for different aspects of the projects. Their discussions covered both physical progress and supporting requirements, including compensation payments, land-related matters and arrangements for managing traffic during construction.

Related Stories

Gold Stories

Next Story
Infrastructure Transport

Shillong Airport Expansion on Track for December 2027 Finish

Work on the expansion of Shillong Airport and its runway is progressing according to schedule, with completion targeted for December 2027, Transport and Civil Aviation Department Secretary Sanjay Goyal said. The construction is being carried out under the approved master plan, and officials are monitoring progress to ensure the planned timeline is maintained. Goyal said the work was in full swing and there was currently no reason to anticipate a delay. The project is intended to improve the airport’s capacity and strengthen air connectivity to and from the region as demand for air travel inc..

Next Story
Infrastructure Transport

GMR Hyderabad Airport Enhances Cargo Capacity

GMR Hyderabad International Airport has enhanced its cargo-handling infrastructure by commissioning an upgraded Elevated Transfer Vehicle (ETV)-based storage system at its Cargo Terminal. The facility has been upgraded within the existing terminal footprint, allowing the airport to expand capacity without requiring additional space. The new system has increased Unit Load Device (ULD) storage capacity from 33 to 80 ULDs. This represents an increase of more than double and is intended to provide greater operational flexibility as cargo volumes and freighter activity expand. The additional storag..

Next Story
Infrastructure Urban

Visteon Expands Chennai Manufacturing with Cellular NAD Line

Visteon has launched a production line for Cellular Network Access Device (NAD) modules at its manufacturing plant in Chennai, Tamil Nadu. The investment expands the automotive technology company’s local manufacturing capabilities and strengthens its regional supply chain. The line was inaugurated by Sachin Lawande, Visteon’s President and Chief Executive Officer, along with members of the company’s leadership team. Production in Chennai positions India as a manufacturing base for Cellular NAD technology and enables the company to serve customers in international markets from the region...

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

SPECIAL OFFER
QR Code