Delhi Government Plans 8 Km Elevated Corridor with Four Flyovers
ROADS & HIGHWAYS

Delhi Government Plans 8 Km Elevated Corridor with Four Flyovers

The Delhi government is planning an 8 km elevated corridor with four flyovers along Mehrauli-Badarpur Road to address persistent traffic congestion in south Delhi. The proposed corridor is intended to improve connectivity between Saket, Ambedkar Nagar, Khanpur, Sangam Vihar and Pul Prahladpur while reducing travel times and easing traffic movement.

The Public Works Department has secured approval for two of the projects. The government sanctioned Rs. 14.71 bn for the work in March this year, while consultants have been appointed to examine the remaining two stretches. The PWD has also approached the Delhi Development Authority to seek the transfer of land required for construction.

The first stretch, measuring 2.41 km between Saket G and Sangam Vihar, has crossed the halfway mark in construction. The Delhi Metro Rail Corporation is executing the project, which involves an integrated flyover above an underground metro corridor.

Construction has also started on the 2.56 km section connecting Maa Anandmayee Marg with Pul Prahladpur, for which funding has been sanctioned. Together, the two approved stretches account for a substantial portion of the planned corridor and are at different stages of execution.

The remaining sections comprise a 2.72 km flyover between Sangam Vihar and Maa Anandmayee Marg and a 450-metre flyover between Pul Prahladpur and Badarpur. Consultants have been appointed for both sections, with the required technical and feasibility studies currently in progress.

Once the full corridor is completed, it is expected to provide a continuous elevated route across several heavily congested locations in south Delhi. The project will link major residential and transport hubs, although the timeline for completing the two sections still under study has not been specified.

The Delhi government is planning an 8 km elevated corridor with four flyovers along Mehrauli-Badarpur Road to address persistent traffic congestion in south Delhi. The proposed corridor is intended to improve connectivity between Saket, Ambedkar Nagar, Khanpur, Sangam Vihar and Pul Prahladpur while reducing travel times and easing traffic movement. The Public Works Department has secured approval for two of the projects. The government sanctioned Rs. 14.71 bn for the work in March this year, while consultants have been appointed to examine the remaining two stretches. The PWD has also approached the Delhi Development Authority to seek the transfer of land required for construction. The first stretch, measuring 2.41 km between Saket G and Sangam Vihar, has crossed the halfway mark in construction. The Delhi Metro Rail Corporation is executing the project, which involves an integrated flyover above an underground metro corridor. Construction has also started on the 2.56 km section connecting Maa Anandmayee Marg with Pul Prahladpur, for which funding has been sanctioned. Together, the two approved stretches account for a substantial portion of the planned corridor and are at different stages of execution. The remaining sections comprise a 2.72 km flyover between Sangam Vihar and Maa Anandmayee Marg and a 450-metre flyover between Pul Prahladpur and Badarpur. Consultants have been appointed for both sections, with the required technical and feasibility studies currently in progress. Once the full corridor is completed, it is expected to provide a continuous elevated route across several heavily congested locations in south Delhi. The project will link major residential and transport hubs, although the timeline for completing the two sections still under study has not been specified.

Related Stories

Gold Stories

Next Story
Infrastructure Transport

Shillong Airport Expansion on Track for December 2027 Finish

Work on the expansion of Shillong Airport and its runway is progressing according to schedule, with completion targeted for December 2027, Transport and Civil Aviation Department Secretary Sanjay Goyal said. The construction is being carried out under the approved master plan, and officials are monitoring progress to ensure the planned timeline is maintained. Goyal said the work was in full swing and there was currently no reason to anticipate a delay. The project is intended to improve the airport’s capacity and strengthen air connectivity to and from the region as demand for air travel inc..

Next Story
Infrastructure Transport

GMR Hyderabad Airport Enhances Cargo Capacity

GMR Hyderabad International Airport has enhanced its cargo-handling infrastructure by commissioning an upgraded Elevated Transfer Vehicle (ETV)-based storage system at its Cargo Terminal. The facility has been upgraded within the existing terminal footprint, allowing the airport to expand capacity without requiring additional space. The new system has increased Unit Load Device (ULD) storage capacity from 33 to 80 ULDs. This represents an increase of more than double and is intended to provide greater operational flexibility as cargo volumes and freighter activity expand. The additional storag..

Next Story
Infrastructure Urban

Visteon Expands Chennai Manufacturing with Cellular NAD Line

Visteon has launched a production line for Cellular Network Access Device (NAD) modules at its manufacturing plant in Chennai, Tamil Nadu. The investment expands the automotive technology company’s local manufacturing capabilities and strengthens its regional supply chain. The line was inaugurated by Sachin Lawande, Visteon’s President and Chief Executive Officer, along with members of the company’s leadership team. Production in Chennai positions India as a manufacturing base for Cellular NAD technology and enables the company to serve customers in international markets from the region...

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

SPECIAL OFFER
QR Code