Incident at Dwarka Expressway package-1 under construction
ROADS & HIGHWAYS

Incident at Dwarka Expressway package-1 under construction

It was reported that under the erection span P8-P9 of the flyover, which is a part of the Shiv Murti interchange on the Dwarka Expressway, had toppled around 9:30 AM on June 14. It was mentioned that a team of NHAI officers, Authority Engineer, and Bridge Experts had immediately rushed to the site.

It was stated that the span had been in the process of being erected and reportedly was resting on temporary stools and hydraulic jacks.

The span had been pre-stressed on June 2, 2023. The construction work on this flyover had begun with the diversion of NH-48 traffic on March 18, for a duration of 90 days. During this period, a total of 13 spans had been erected.

Based on the site reports, it was stated that prima facie, the incident appeared to be a case of mechanical failure, as the structural elements of both the superstructure and substructure were in sound condition.

In order to determine the reasons behind the incident, a three-member team of Bridge Experts had been formed. It was mentioned that two members of the team were already inspecting the site, and the third member would arrive at the site the following morning. The committee would thoroughly examine all the issues and submit a detailed report within four weeks.

Also read:
BMC progresses on Mumbai's underground sewage tunnel for flood control
Trilateral Bangkok-Kolkata highway set to be completed in 3-4 Years


It was reported that under the erection span P8-P9 of the flyover, which is a part of the Shiv Murti interchange on the Dwarka Expressway, had toppled around 9:30 AM on June 14. It was mentioned that a team of NHAI officers, Authority Engineer, and Bridge Experts had immediately rushed to the site. It was stated that the span had been in the process of being erected and reportedly was resting on temporary stools and hydraulic jacks. The span had been pre-stressed on June 2, 2023. The construction work on this flyover had begun with the diversion of NH-48 traffic on March 18, for a duration of 90 days. During this period, a total of 13 spans had been erected. Based on the site reports, it was stated that prima facie, the incident appeared to be a case of mechanical failure, as the structural elements of both the superstructure and substructure were in sound condition. In order to determine the reasons behind the incident, a three-member team of Bridge Experts had been formed. It was mentioned that two members of the team were already inspecting the site, and the third member would arrive at the site the following morning. The committee would thoroughly examine all the issues and submit a detailed report within four weeks. Also read: BMC progresses on Mumbai's underground sewage tunnel for flood controlTrilateral Bangkok-Kolkata highway set to be completed in 3-4 Years

Related Stories

Gold Stories

Next Story
Infrastructure Urban

Sabarmati Riverfront Two Plots Up for Auction at Rs2.24 bn Base Price

Two commercial plots on the western bank of the Sabarmati Riverfront will be auctioned with a base price of Rs 112 crore each, equivalent to Rs 1.12 bn apiece and Rs 2.24 billion in total. The parcels are located adjacent to the Metro Rail Bridge in Ahmedabad and form the first commercial offering after a prolonged pause. The Riverfront Development Corporation has framed the sale as part of a phased commercial release to revive development along the riverfront. The combined base valuation has been set by the corporation to reflect market rates along the riverfront. The corporation has fixed a ..

Next Story
Infrastructure Urban

Andhra Pradesh to Connect Over One Million Streetlights

Andhra Pradesh will undertake a statewide smart streetlighting programme across all 123 Urban Local Bodies (ULBs), bringing around 1.05 million (mn) streetlights under an AI enabled monitoring and management system. The programme will be implemented by Energy Efficiency Services Limited (EESL) with the Commissioner and Director of Municipal Administration under the state Municipal Administration and Urban Development Department. The project aims to convert conventional streetlighting into a digitally managed municipal service monitored and maintained remotely. The initial phase will cover abou..

Next Story
Infrastructure Urban

AMC To Procure Four Machines For Guard Rail Cleaning

Ahmedabad Municipal Corporation will introduce four specialised machines for cleaning guard railings along major roads and the central verges of BRTS and Metro corridors. The civic body plans to replace manual labour with mechanised cleaning to improve maintenance of road infrastructure and greenery. The purchase is estimated at Rs 82.8 million (mn), excluding GST. The proposal sets the base price of each machine at about Rs 20.7 million (mn) so four units total Rs 82.8 million (mn) before GST. 18 per cent GST will be applicable separately. During the warranty period each machine will operate ..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement