Mukkola-Karode bypass work likely to get delayed
ROADS & HIGHWAYS

Mukkola-Karode bypass work likely to get delayed

The standoff between the Geology and Mining Department and the National Highways Authority of India (NHAI) for excavating soil from a quarry at Perumkadavila in the district, to fill the remaining portions of the Mukkola-Karode national highway (NH) 66 bypass stretch is likely to delay the commissioning of the road.

The NHAI had promised that the road would be commissioned in August earlier. The delay from the geology department may prompt Larsen & Toubro (L&T) to withdraw from the construction work as it did in the Kanyakumari district earlier. Only 1.2 km of the 16.3 km stretch is remaining for construction. This stretch will be the first concrete national highway in the state.

NHAI project director P Pradeep told the media that the works are nearing fulfilment. At this stage, the geology department has reviewed and asked to stop the excavation citing mining rules. Now, authority is in shortage of soil, which is concerning the pending works in the Punnakulam and Thirupuram areas.

He said that the contractor of the project L&T can go forward with the work only if the geology department consents. NHAI approached the geology department to clear the file, but the approval is not yet received. Again the work will be delayed as the monsoon season will start soon.

Earlier, the geology and mining department had issued a stop memo to the NHAI to stop work after 5 pm. This had slowed down the construction work on 1.2 km of the total 16.3 km stretch at Kottukal and Thirupuram. The NH 66 bypass construction work has also been halted midway due to the soil or red earth's unavailability.

A top official of the geology department told the media that the department could not give consent for excavation owing to rules.

The official said that permits were given earlier. We are going by the rules. Currently, two houses and a building is located around the quarry where the excavation is taking place. So the NHAI or the contractor must get a No Objection Certificate (NOC) from the Irrigation department. Otherwise, they need to excavate at different places after stopping excavation at the present place.

The original deadline for the first concrete road completion in the state was May 31 last year. The deadline was changed several times owing to the Covid-19 pandemic.

Image Source

Also read: Govt targets 18,000 km highway construction in FY23

The standoff between the Geology and Mining Department and the National Highways Authority of India (NHAI) for excavating soil from a quarry at Perumkadavila in the district, to fill the remaining portions of the Mukkola-Karode national highway (NH) 66 bypass stretch is likely to delay the commissioning of the road. The NHAI had promised that the road would be commissioned in August earlier. The delay from the geology department may prompt Larsen & Toubro (L&T) to withdraw from the construction work as it did in the Kanyakumari district earlier. Only 1.2 km of the 16.3 km stretch is remaining for construction. This stretch will be the first concrete national highway in the state. NHAI project director P Pradeep told the media that the works are nearing fulfilment. At this stage, the geology department has reviewed and asked to stop the excavation citing mining rules. Now, authority is in shortage of soil, which is concerning the pending works in the Punnakulam and Thirupuram areas. He said that the contractor of the project L&T can go forward with the work only if the geology department consents. NHAI approached the geology department to clear the file, but the approval is not yet received. Again the work will be delayed as the monsoon season will start soon. Earlier, the geology and mining department had issued a stop memo to the NHAI to stop work after 5 pm. This had slowed down the construction work on 1.2 km of the total 16.3 km stretch at Kottukal and Thirupuram. The NH 66 bypass construction work has also been halted midway due to the soil or red earth's unavailability. A top official of the geology department told the media that the department could not give consent for excavation owing to rules. The official said that permits were given earlier. We are going by the rules. Currently, two houses and a building is located around the quarry where the excavation is taking place. So the NHAI or the contractor must get a No Objection Certificate (NOC) from the Irrigation department. Otherwise, they need to excavate at different places after stopping excavation at the present place. The original deadline for the first concrete road completion in the state was May 31 last year. The deadline was changed several times owing to the Covid-19 pandemic. Image Source Also read: Govt targets 18,000 km highway construction in FY23

Next Story
Infrastructure Energy

South West Pinnacle Wins Rs 30 Cr Oman Mining Contract

South West Pinnacle Exploration Ltd has secured a Rs 30 crore contract from Minerals Development Oman (MDO) for mining exploration in concession areas 12B and 13.The two-year project will be carried out via Alara Resources LLC, a JV in Oman. MDO, backed by Oman’s investment authorities, focuses on monetising mineral wealth.The contract covers copper, gold, and chromite and highlights South West Pinnacle’s growing footprint in international exploration and mining services. ..

Next Story
Equipment

Godrej GEG Boosts Intralogistics with AI and Green Tech

Godrej Enterprises Group (GEG) is revolutionising warehouse and factory logistics through its Material Handling Equipment and Storage Solutions arms by integrating AI, IoT, and automation.With 20–25% market share and 85% local sourcing, GEG champions Atmanirbhar Bharat and sustainability. The Chennai plant, a green manufacturing leader, uses RoHS-compliant materials and has slashed energy consumption by 60%.GEG serves e-commerce, FMCG, retail, and cold chains with high-performance racking and electric forklifts. Upcoming IoT-enabled forklifts and telematics solutions aim to improve speed, sa..

Next Story
Infrastructure Urban

Amit Shah Inaugurates Key Projects Across Gujarat

Union Home Minister Amit Shah inaugurated and laid the foundation stone for various projects in Gujarat’s Panchmahal district and Ahmedabad.In Godhra, he inaugurated the Center of Excellence building, sports complex, reservoir, and Miyawaki plantation. In Ahmedabad, he unveiled a new cooperative complex in Adaroda village and a primary school in Juwal.These projects, under the Model Co-op Village scheme, aim to boost education, sustainability, and rural development across the state. ..

Advertisement

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Advertisement

Talk to us?