Mukkola-Karode bypass work likely to get delayed
ROADS & HIGHWAYS

Mukkola-Karode bypass work likely to get delayed

The standoff between the Geology and Mining Department and the National Highways Authority of India (NHAI) for excavating soil from a quarry at Perumkadavila in the district, to fill the remaining portions of the Mukkola-Karode national highway (NH) 66 bypass stretch is likely to delay the commissioning of the road.

The NHAI had promised that the road would be commissioned in August earlier. The delay from the geology department may prompt Larsen & Toubro (L&T) to withdraw from the construction work as it did in the Kanyakumari district earlier. Only 1.2 km of the 16.3 km stretch is remaining for construction. This stretch will be the first concrete national highway in the state.

NHAI project director P Pradeep told the media that the works are nearing fulfilment. At this stage, the geology department has reviewed and asked to stop the excavation citing mining rules. Now, authority is in shortage of soil, which is concerning the pending works in the Punnakulam and Thirupuram areas.

He said that the contractor of the project L&T can go forward with the work only if the geology department consents. NHAI approached the geology department to clear the file, but the approval is not yet received. Again the work will be delayed as the monsoon season will start soon.

Earlier, the geology and mining department had issued a stop memo to the NHAI to stop work after 5 pm. This had slowed down the construction work on 1.2 km of the total 16.3 km stretch at Kottukal and Thirupuram. The NH 66 bypass construction work has also been halted midway due to the soil or red earth's unavailability.

A top official of the geology department told the media that the department could not give consent for excavation owing to rules.

The official said that permits were given earlier. We are going by the rules. Currently, two houses and a building is located around the quarry where the excavation is taking place. So the NHAI or the contractor must get a No Objection Certificate (NOC) from the Irrigation department. Otherwise, they need to excavate at different places after stopping excavation at the present place.

The original deadline for the first concrete road completion in the state was May 31 last year. The deadline was changed several times owing to the Covid-19 pandemic.

Image Source

Also read: Govt targets 18,000 km highway construction in FY23

The standoff between the Geology and Mining Department and the National Highways Authority of India (NHAI) for excavating soil from a quarry at Perumkadavila in the district, to fill the remaining portions of the Mukkola-Karode national highway (NH) 66 bypass stretch is likely to delay the commissioning of the road. The NHAI had promised that the road would be commissioned in August earlier. The delay from the geology department may prompt Larsen & Toubro (L&T) to withdraw from the construction work as it did in the Kanyakumari district earlier. Only 1.2 km of the 16.3 km stretch is remaining for construction. This stretch will be the first concrete national highway in the state. NHAI project director P Pradeep told the media that the works are nearing fulfilment. At this stage, the geology department has reviewed and asked to stop the excavation citing mining rules. Now, authority is in shortage of soil, which is concerning the pending works in the Punnakulam and Thirupuram areas. He said that the contractor of the project L&T can go forward with the work only if the geology department consents. NHAI approached the geology department to clear the file, but the approval is not yet received. Again the work will be delayed as the monsoon season will start soon. Earlier, the geology and mining department had issued a stop memo to the NHAI to stop work after 5 pm. This had slowed down the construction work on 1.2 km of the total 16.3 km stretch at Kottukal and Thirupuram. The NH 66 bypass construction work has also been halted midway due to the soil or red earth's unavailability. A top official of the geology department told the media that the department could not give consent for excavation owing to rules. The official said that permits were given earlier. We are going by the rules. Currently, two houses and a building is located around the quarry where the excavation is taking place. So the NHAI or the contractor must get a No Objection Certificate (NOC) from the Irrigation department. Otherwise, they need to excavate at different places after stopping excavation at the present place. The original deadline for the first concrete road completion in the state was May 31 last year. The deadline was changed several times owing to the Covid-19 pandemic. Image Source Also read: Govt targets 18,000 km highway construction in FY23

Next Story
Equipment

Liebherr Wheel Loaders and Circular Economy in Switzerland

Every year, the Verein für Abfallentsorgung (Association for Waste Disposal, or VfA for short) processes around 50,000 m³ of green waste in the Swiss canton of St. Gallen. A decomposition process lasting several months results in the finest fresh compost, which is refined by the company Terre Suisse, as one of several customers, in further processing steps to form high-quality substrates and potting soil. Both the latest generation and older models of mid-sized Liebherr wheel loaders play an important role in this production process, especially when it comes to loading and heaping soil. They..

Next Story
Infrastructure Urban

Covestro India's Greater Noida Site Achieves ISCC PLUS

Covestro's sustainability journey in India has reached a significant milestone with its Greater Noida polycarbonate compounding facility receiving the prestigious ISCC (International Sustainability and Carbon Certification) PLUS certification on May 5, 2025. This certification enables the facility to produce the RE series of renewable attributed polycarbonate products, under the CQ (Circular Intelligence) product portfolio offered by Covestro. The RE series is used across electrical and electronics, automotive, and healthcare industries, and further enables these sectors to advance their clima..

Next Story
Infrastructure Urban

MoHUA Plans New Role for Smart City SPVs

In a significant policy move, the Ministry of Housing and Urban Affairs (MoHUA) has issued an advisory encouraging the continued use and repurposing of Special Purpose Vehicles (SPVs) formed under the Smart Cities Mission (SCM). This marks a step toward sustaining urban transformation by leveraging institutional capabilities and infrastructure developed over the past decade.Initiated in 2015, the Smart Cities Mission introduced a new era of urban planning in India, with each of the 100 selected cities forming SPVs under the Companies Act, 2013. These entities, jointly owned by state government..

Advertisement

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Advertisement

Talk to us?