Mukkola-Karode bypass work likely to get delayed
ROADS & HIGHWAYS

Mukkola-Karode bypass work likely to get delayed

The standoff between the Geology and Mining Department and the National Highways Authority of India (NHAI) for excavating soil from a quarry at Perumkadavila in the district, to fill the remaining portions of the Mukkola-Karode national highway (NH) 66 bypass stretch is likely to delay the commissioning of the road.

The NHAI had promised that the road would be commissioned in August earlier. The delay from the geology department may prompt Larsen & Toubro (L&T) to withdraw from the construction work as it did in the Kanyakumari district earlier. Only 1.2 km of the 16.3 km stretch is remaining for construction. This stretch will be the first concrete national highway in the state.

NHAI project director P Pradeep told the media that the works are nearing fulfilment. At this stage, the geology department has reviewed and asked to stop the excavation citing mining rules. Now, authority is in shortage of soil, which is concerning the pending works in the Punnakulam and Thirupuram areas.

He said that the contractor of the project L&T can go forward with the work only if the geology department consents. NHAI approached the geology department to clear the file, but the approval is not yet received. Again the work will be delayed as the monsoon season will start soon.

Earlier, the geology and mining department had issued a stop memo to the NHAI to stop work after 5 pm. This had slowed down the construction work on 1.2 km of the total 16.3 km stretch at Kottukal and Thirupuram. The NH 66 bypass construction work has also been halted midway due to the soil or red earth's unavailability.

A top official of the geology department told the media that the department could not give consent for excavation owing to rules.

The official said that permits were given earlier. We are going by the rules. Currently, two houses and a building is located around the quarry where the excavation is taking place. So the NHAI or the contractor must get a No Objection Certificate (NOC) from the Irrigation department. Otherwise, they need to excavate at different places after stopping excavation at the present place.

The original deadline for the first concrete road completion in the state was May 31 last year. The deadline was changed several times owing to the Covid-19 pandemic.

Image Source

Also read: Govt targets 18,000 km highway construction in FY23

The standoff between the Geology and Mining Department and the National Highways Authority of India (NHAI) for excavating soil from a quarry at Perumkadavila in the district, to fill the remaining portions of the Mukkola-Karode national highway (NH) 66 bypass stretch is likely to delay the commissioning of the road. The NHAI had promised that the road would be commissioned in August earlier. The delay from the geology department may prompt Larsen & Toubro (L&T) to withdraw from the construction work as it did in the Kanyakumari district earlier. Only 1.2 km of the 16.3 km stretch is remaining for construction. This stretch will be the first concrete national highway in the state. NHAI project director P Pradeep told the media that the works are nearing fulfilment. At this stage, the geology department has reviewed and asked to stop the excavation citing mining rules. Now, authority is in shortage of soil, which is concerning the pending works in the Punnakulam and Thirupuram areas. He said that the contractor of the project L&T can go forward with the work only if the geology department consents. NHAI approached the geology department to clear the file, but the approval is not yet received. Again the work will be delayed as the monsoon season will start soon. Earlier, the geology and mining department had issued a stop memo to the NHAI to stop work after 5 pm. This had slowed down the construction work on 1.2 km of the total 16.3 km stretch at Kottukal and Thirupuram. The NH 66 bypass construction work has also been halted midway due to the soil or red earth's unavailability. A top official of the geology department told the media that the department could not give consent for excavation owing to rules. The official said that permits were given earlier. We are going by the rules. Currently, two houses and a building is located around the quarry where the excavation is taking place. So the NHAI or the contractor must get a No Objection Certificate (NOC) from the Irrigation department. Otherwise, they need to excavate at different places after stopping excavation at the present place. The original deadline for the first concrete road completion in the state was May 31 last year. The deadline was changed several times owing to the Covid-19 pandemic. Image Source Also read: Govt targets 18,000 km highway construction in FY23

Next Story
Infrastructure Urban

3i Infotech Reports Rs 7.25 Bn Revenue for FY25

3i Infotech, a leading provider of digital transformation, technology services and technology solutions, announced its consolidated financial results for the fourth quarter and full year FY25, ended on March 31st, 2025. The company maintained its growth momentum, displaying consistent progress for the 3rd consecutive quarter.In Q4 FY25, 3i Infotech reported revenue of Rs 1.87 billion, reflecting steady performance compared to Rs 1.81 billion in Q3 FY25 and Rs 1.97 billion in Q4 FY24. The company delivered strong profitability improvements, with gross margin growing by 14.8 per cent Q-o-Q and 1..

Next Story
Infrastructure Urban

Emerald Finance Joins Baya PTE to Boost SME Bill Discounting

Emerald Finance is a dynamic company offering a spectrum of financial products and services including its flagship Earned Wage Access (EWA) in India, has entered into a strategic partnership with Singapore-based Baya PTE through its Indian subsidiary. This collaboration aims to strengthen bill discounting services for Small and Medium Enterprises (SMEs), enabling faster access to working capital and improved cash flow management.The initiative is designed to support SMEs that supply to large corporates such as JSW Steel, Delhivery, and PVR INOX, among others. By facilitating timely invoice dis..

Next Story
Infrastructure Urban

BLS E-Services Crosses Rs 5 Bn Revenue Mark in FY25

BLS E-Services, a technology-enabled digital service provider, announced its audited consolidated financial results for the quarter and full year period ended 31 March 2025.Speaking about the performance and recent updates, Shikhar Aggarwal, Chairman, BLS E- Services said, “We are delighted to report a remarkable performance in FY25, as we achieved several milestones during the fiscal year. FY25 marked our highest-ever financial performance, as we surpassed Rs 5 billion milestone in Total Income during the year, which was reported at Rs 5.45 billion, a notable YoY growth of 76 per cent. The ..

Advertisement

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Advertisement

Talk to us?