Mukkola-Karode bypass work likely to get delayed
ROADS & HIGHWAYS

Mukkola-Karode bypass work likely to get delayed

The standoff between the Geology and Mining Department and the National Highways Authority of India (NHAI) for excavating soil from a quarry at Perumkadavila in the district, to fill the remaining portions of the Mukkola-Karode national highway (NH) 66 bypass stretch is likely to delay the commissioning of the road.

The NHAI had promised that the road would be commissioned in August earlier. The delay from the geology department may prompt Larsen & Toubro (L&T) to withdraw from the construction work as it did in the Kanyakumari district earlier. Only 1.2 km of the 16.3 km stretch is remaining for construction. This stretch will be the first concrete national highway in the state.

NHAI project director P Pradeep told the media that the works are nearing fulfilment. At this stage, the geology department has reviewed and asked to stop the excavation citing mining rules. Now, authority is in shortage of soil, which is concerning the pending works in the Punnakulam and Thirupuram areas.

He said that the contractor of the project L&T can go forward with the work only if the geology department consents. NHAI approached the geology department to clear the file, but the approval is not yet received. Again the work will be delayed as the monsoon season will start soon.

Earlier, the geology and mining department had issued a stop memo to the NHAI to stop work after 5 pm. This had slowed down the construction work on 1.2 km of the total 16.3 km stretch at Kottukal and Thirupuram. The NH 66 bypass construction work has also been halted midway due to the soil or red earth's unavailability.

A top official of the geology department told the media that the department could not give consent for excavation owing to rules.

The official said that permits were given earlier. We are going by the rules. Currently, two houses and a building is located around the quarry where the excavation is taking place. So the NHAI or the contractor must get a No Objection Certificate (NOC) from the Irrigation department. Otherwise, they need to excavate at different places after stopping excavation at the present place.

The original deadline for the first concrete road completion in the state was May 31 last year. The deadline was changed several times owing to the Covid-19 pandemic.

Image Source

Also read: Govt targets 18,000 km highway construction in FY23

The standoff between the Geology and Mining Department and the National Highways Authority of India (NHAI) for excavating soil from a quarry at Perumkadavila in the district, to fill the remaining portions of the Mukkola-Karode national highway (NH) 66 bypass stretch is likely to delay the commissioning of the road. The NHAI had promised that the road would be commissioned in August earlier. The delay from the geology department may prompt Larsen & Toubro (L&T) to withdraw from the construction work as it did in the Kanyakumari district earlier. Only 1.2 km of the 16.3 km stretch is remaining for construction. This stretch will be the first concrete national highway in the state. NHAI project director P Pradeep told the media that the works are nearing fulfilment. At this stage, the geology department has reviewed and asked to stop the excavation citing mining rules. Now, authority is in shortage of soil, which is concerning the pending works in the Punnakulam and Thirupuram areas. He said that the contractor of the project L&T can go forward with the work only if the geology department consents. NHAI approached the geology department to clear the file, but the approval is not yet received. Again the work will be delayed as the monsoon season will start soon. Earlier, the geology and mining department had issued a stop memo to the NHAI to stop work after 5 pm. This had slowed down the construction work on 1.2 km of the total 16.3 km stretch at Kottukal and Thirupuram. The NH 66 bypass construction work has also been halted midway due to the soil or red earth's unavailability. A top official of the geology department told the media that the department could not give consent for excavation owing to rules. The official said that permits were given earlier. We are going by the rules. Currently, two houses and a building is located around the quarry where the excavation is taking place. So the NHAI or the contractor must get a No Objection Certificate (NOC) from the Irrigation department. Otherwise, they need to excavate at different places after stopping excavation at the present place. The original deadline for the first concrete road completion in the state was May 31 last year. The deadline was changed several times owing to the Covid-19 pandemic. Image Source Also read: Govt targets 18,000 km highway construction in FY23

Next Story
Real Estate

Shriram Properties Backs Neerathon 2025 to Promote Water Conservation

Shriram Properties Limited (SPL), one of India’s leading residential developers in the mid-market and mid-premium segments, reaffirmed its commitment to sustainability and community welfare by supporting IPA Neerathon 2025 in Chennai as the Title Sponsor. The event, which attracted thousands of participants across 10K, 5K and 3K categories at Island Grounds, was more than a race — it was a movement for water conservation and environmental stewardship.For SPL, this partnership aligns with its long-standing efforts to support initiatives beyond real estate, promoting sustainable communities ..

Next Story
Infrastructure Transport

DMRC revives plan for Dwarka–Gurgaon Metro corridor

Nearly a decade after it was shelved, the Delhi Metro Rail Corporation (DMRC) is reconsidering a long-discussed plan to extend the Metro from Dwarka to Gurgaon.The proposed 12-km corridor would run from Yashobhoomi station in Dwarka Sector-25, on the Airport Express Line, to IFFCO Chowk along the Delhi–Jaipur Expressway. Planned stations include Bharthal, Bijwasan, Carterpuri, and Tau Devi Lal Park in Sector 23. An interchange is expected with the Gurugram Metro corridor at Sector 23.If implemented, the extension would provide direct metro access from Dwarka to key commercial hubs including ..

Next Story
Infrastructure Urban

Ola, Uber, Rapido get nod for Mumbai bike taxi services

The Maharashtra State Transport Authority (STA) has granted provisional licences to Ola, Uber, and Rapido to operate bike taxi services in the Mumbai Metropolitan Region. The move follows the implementation of the Maharashtra Bike Taxi Rules 2025.As per STA’s approval, the minimum fare has been fixed at Rs 15 for the first 1.5 km, with an additional Rs 10.27 per km thereafter. The licences are valid for one month, during which operators must apply for permanent permits by fulfilling all regulatory conditions.Smart-Ride’s application was rejected for failing to meet the prescribed norms. Of..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Talk to us?