NH-29 Package- III: NHIDCL receives three proposals
ROADS & HIGHWAYS

NH-29 Package- III: NHIDCL receives three proposals

The Guwahati High Court, Kohima Bench has been notified by the National Highways and Infrastructure Development Corporation Limited (NHIDCL) that it has received three bids and a project cost estimate for Package III of the NH 29 from M/S RAMKY-ECI (JV).

The proposals were made after the court ordered the NHIDCL authorities and RAMKY-ECI(JV) to consider the Package-III after observing that its progress "has become a non-starter creating a lot of annoyance to the commuters" on December 14.

Two contractors' contracts have already been terminated in relation to Package-III of the ongoing four-lane National Highway-29 project, which roughly corresponds to the Piphema to Jotsoma length (Design Km 152.490 to Km 166.700).

The NHIDCL authorities asked for some time to review the proposals, to further discuss them with the contractor of Package I & II (M/S RAMKY-ECI JV), and to then decide at the highest level whether the proposals were acceptable or not. The hearing on the ongoing sou motu public interest litigation on the NH-29 four-lane project resumed on Monday.

In addition, the General Manager of NHIDCL, who was also present in court, stated that if the solutions presented are rejected, more steps will be taken to propose a better solution for the completion of Package-III.

In addition, the General Manager gave the Division Bench of Justices LS Jamir and Songkhupchung Serto assurances that the two-lane in relation to Package-III, which is currently undergoing maintenance, would be completely finished before March 2023 in accordance with the project requirements.

The Bench instructed the NHIDCL and Contractor to further consider their options, reach a conclusion by no later than January 15, 2023, and submit an affidavit in light of the submissions.

If the current offers made by the Contractor are not acceptable, the NHIDCL authorities will also present an alternative plan for completion of Package-III in the aforementioned affidavit and submit it by January 17, 2023, as instructed.

The Bench stated that it was pleased with the NHIDCL's affidavit submitted on December 14 detailing the actions followed by its officials following receipt of the sum of 111.19Million from the previous contractor.

The M/S RAMKY-ECI JV was also instructed by the Bench to make sure that Packages I and II are finished on or before January 15, 2023.

When it became known to the Court that the project that was supposed to be finished in September 2019 hadn't been finished, this PIL was brought up in 2019.

The Guwahati High Court, Kohima Bench has been notified by the National Highways and Infrastructure Development Corporation Limited (NHIDCL) that it has received three bids and a project cost estimate for Package III of the NH 29 from M/S RAMKY-ECI (JV). The proposals were made after the court ordered the NHIDCL authorities and RAMKY-ECI(JV) to consider the Package-III after observing that its progress has become a non-starter creating a lot of annoyance to the commuters on December 14. Two contractors' contracts have already been terminated in relation to Package-III of the ongoing four-lane National Highway-29 project, which roughly corresponds to the Piphema to Jotsoma length (Design Km 152.490 to Km 166.700). The NHIDCL authorities asked for some time to review the proposals, to further discuss them with the contractor of Package I & II (M/S RAMKY-ECI JV), and to then decide at the highest level whether the proposals were acceptable or not. The hearing on the ongoing sou motu public interest litigation on the NH-29 four-lane project resumed on Monday. In addition, the General Manager of NHIDCL, who was also present in court, stated that if the solutions presented are rejected, more steps will be taken to propose a better solution for the completion of Package-III. In addition, the General Manager gave the Division Bench of Justices LS Jamir and Songkhupchung Serto assurances that the two-lane in relation to Package-III, which is currently undergoing maintenance, would be completely finished before March 2023 in accordance with the project requirements. The Bench instructed the NHIDCL and Contractor to further consider their options, reach a conclusion by no later than January 15, 2023, and submit an affidavit in light of the submissions. If the current offers made by the Contractor are not acceptable, the NHIDCL authorities will also present an alternative plan for completion of Package-III in the aforementioned affidavit and submit it by January 17, 2023, as instructed. The Bench stated that it was pleased with the NHIDCL's affidavit submitted on December 14 detailing the actions followed by its officials following receipt of the sum of 111.19Million from the previous contractor. The M/S RAMKY-ECI JV was also instructed by the Bench to make sure that Packages I and II are finished on or before January 15, 2023. When it became known to the Court that the project that was supposed to be finished in September 2019 hadn't been finished, this PIL was brought up in 2019.

Next Story
Infrastructure Urban

Coal Ministry Achieves Milestones under Special Campaign 5.0

The Ministry of Coal and its Public Sector Undertakings (PSUs) have achieved notable milestones under the Special Campaign 5.0, focusing on cleanliness, operational efficiency, and sustainability across the coal sector. During the implementation phase from 2–31 October 2025, over 1,205 sites were cleaned, covering 68,04,087 sq ft, nearing the target of 82,51,511 sq ft. Scrap disposal of 5,813 MT against a target of 8,678 MT generated Rs 228.7 million in revenue. In addition, 1,11,248 physical and 30,331 electronic files were reviewed, with 74,123 weeded out or closed. Key initiatives showc..

Next Story
Infrastructure Energy

Vesting Orders Issued for Three Coal Blocks under Commercial Auctions

The Ministry of Coal’s Nominated Authority has issued vesting orders for three coal blocks under commercial coal block auctions on 23 October 2025. The Coal Mine Development and Production Agreements (CMDPAs) for these mines were earlier signed on 21 August 2025. The three blocks include Rajgamar Dipside (Deavnara), Tangardihi North, and Mahuagarhi. Of these, two are partially explored while one is fully explored, with a combined peak rated capacity of around 1 MTPA and geological reserves of approximately 1,484.41 million tonnes. These mines are expected to generate annual revenue of abou..

Next Story
Infrastructure Urban

TEC, IIT-Hyderabad Partner to Boost 6G and Telecom Standards

The Telecommunication Engineering Centre (TEC), technical arm of the Department of Telecommunications (DoT), has signed a Memorandum of Understanding (MoU) with the Indian Institute of Technology Hyderabad (IIT Hyderabad) for joint research and technical collaboration in advanced telecom technologies and standardisation. The partnership focuses on developing India-specific standards and test frameworks for next-generation networks, including 6G, Artificial Intelligence (AI), and Non-Terrestrial Networks (NTNs). It also aims to enhance India’s participation in international standardisation f..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Talk to us?