NH-29 Package- III: NHIDCL receives three proposals
ROADS & HIGHWAYS

NH-29 Package- III: NHIDCL receives three proposals

The Guwahati High Court, Kohima Bench has been notified by the National Highways and Infrastructure Development Corporation Limited (NHIDCL) that it has received three bids and a project cost estimate for Package III of the NH 29 from M/S RAMKY-ECI (JV).

The proposals were made after the court ordered the NHIDCL authorities and RAMKY-ECI(JV) to consider the Package-III after observing that its progress "has become a non-starter creating a lot of annoyance to the commuters" on December 14.

Two contractors' contracts have already been terminated in relation to Package-III of the ongoing four-lane National Highway-29 project, which roughly corresponds to the Piphema to Jotsoma length (Design Km 152.490 to Km 166.700).

The NHIDCL authorities asked for some time to review the proposals, to further discuss them with the contractor of Package I & II (M/S RAMKY-ECI JV), and to then decide at the highest level whether the proposals were acceptable or not. The hearing on the ongoing sou motu public interest litigation on the NH-29 four-lane project resumed on Monday.

In addition, the General Manager of NHIDCL, who was also present in court, stated that if the solutions presented are rejected, more steps will be taken to propose a better solution for the completion of Package-III.

In addition, the General Manager gave the Division Bench of Justices LS Jamir and Songkhupchung Serto assurances that the two-lane in relation to Package-III, which is currently undergoing maintenance, would be completely finished before March 2023 in accordance with the project requirements.

The Bench instructed the NHIDCL and Contractor to further consider their options, reach a conclusion by no later than January 15, 2023, and submit an affidavit in light of the submissions.

If the current offers made by the Contractor are not acceptable, the NHIDCL authorities will also present an alternative plan for completion of Package-III in the aforementioned affidavit and submit it by January 17, 2023, as instructed.

The Bench stated that it was pleased with the NHIDCL's affidavit submitted on December 14 detailing the actions followed by its officials following receipt of the sum of 111.19Million from the previous contractor.

The M/S RAMKY-ECI JV was also instructed by the Bench to make sure that Packages I and II are finished on or before January 15, 2023.

When it became known to the Court that the project that was supposed to be finished in September 2019 hadn't been finished, this PIL was brought up in 2019.

The Guwahati High Court, Kohima Bench has been notified by the National Highways and Infrastructure Development Corporation Limited (NHIDCL) that it has received three bids and a project cost estimate for Package III of the NH 29 from M/S RAMKY-ECI (JV). The proposals were made after the court ordered the NHIDCL authorities and RAMKY-ECI(JV) to consider the Package-III after observing that its progress has become a non-starter creating a lot of annoyance to the commuters on December 14. Two contractors' contracts have already been terminated in relation to Package-III of the ongoing four-lane National Highway-29 project, which roughly corresponds to the Piphema to Jotsoma length (Design Km 152.490 to Km 166.700). The NHIDCL authorities asked for some time to review the proposals, to further discuss them with the contractor of Package I & II (M/S RAMKY-ECI JV), and to then decide at the highest level whether the proposals were acceptable or not. The hearing on the ongoing sou motu public interest litigation on the NH-29 four-lane project resumed on Monday. In addition, the General Manager of NHIDCL, who was also present in court, stated that if the solutions presented are rejected, more steps will be taken to propose a better solution for the completion of Package-III. In addition, the General Manager gave the Division Bench of Justices LS Jamir and Songkhupchung Serto assurances that the two-lane in relation to Package-III, which is currently undergoing maintenance, would be completely finished before March 2023 in accordance with the project requirements. The Bench instructed the NHIDCL and Contractor to further consider their options, reach a conclusion by no later than January 15, 2023, and submit an affidavit in light of the submissions. If the current offers made by the Contractor are not acceptable, the NHIDCL authorities will also present an alternative plan for completion of Package-III in the aforementioned affidavit and submit it by January 17, 2023, as instructed. The Bench stated that it was pleased with the NHIDCL's affidavit submitted on December 14 detailing the actions followed by its officials following receipt of the sum of 111.19Million from the previous contractor. The M/S RAMKY-ECI JV was also instructed by the Bench to make sure that Packages I and II are finished on or before January 15, 2023. When it became known to the Court that the project that was supposed to be finished in September 2019 hadn't been finished, this PIL was brought up in 2019.

Next Story
Real Estate

Indian Real Estate Sector Sees Highest Capital Inflow in Seven Years

Equirus Capital, a leading full-service investment banking firm, has reported that India’s real estate sector has witnessed its highest capital inflow in seven years, with funds raised reaching ₹23,080 crore across 12 deals.According to Equirus Capital’s analysis, the cumulative capital raised by the sector since FY18 stands at ₹72,331 crore. Of this, Real Estate Investment Trusts (REITs) accounted for the largest share at ₹31,241 crore, followed by large-cap real estate companies at ₹20,437 crore, mid-cap players at ₹12,496 crore, and small-cap firms contributing ₹8,156 crore...

Next Story
Real Estate

India’s Flex Office Market Set for Record Growth

myHQ by ANAROCK, India’s largest workspace discovery and flexible office solutions platform, has released its Flex Office Market in India 2025 Report, revealing that India is set to become the Asia-Pacific region’s largest flexible office market. The report highlights how flexible workspaces have become a mainstream component of India’s commercial real estate, capturing a growing share of national leasing activity.“Flexible workspaces have evolved from a cost-optimisation tool to a strategic necessity,” said Utkarsh Kawatra, CEO and Co-Founder, myHQ by ANAROCK. “Average corporate d..

Next Story
Real Estate

India Defies Regional Slowdown; Office Leasing on Track for Record High in 2025

India’s office market continues to outperform the broader Asia-Pacific region, emerging as a key growth driver amid regional headwinds, according to Knight Frank’s Asia-Pacific Office Highlights Q3 2025 report. With 8.8 million sq. ft. transacted in the third quarter alone, leasing momentum remains robust. Full-year volumes across Bengaluru, NCR, and Mumbai are projected to reach 50 million sq. ft., surpassing the previous record of 41 million sq. ft. set in 2024.The surge has been fuelled by sustained leasing from Global Capability Centres (GCCs) and renewed activity from third-party IT s..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Talk to us?