+
PMC Extends Road Repair Deadline to June 7 as Work Progresses
ROADS & HIGHWAYS

PMC Extends Road Repair Deadline to June 7 as Work Progresses

The Pune Municipal Corporation (PMC) extended the deadline for completing road repair and reinstatement work from June 1 to June 7, as several departments had failed to meet the original target. Despite an earlier directive to finish all digging and road-related activities before the monsoon season, many parts of the city remained under excavation.

This extension was decided after a review meeting held on Monday, chaired by PMC additional commissioner Omprakash Diwate, with heads of the road, drainage, water supply, and electrical departments in attendance.

Diwate explained that the early arrival of the monsoon this year had caused delays in work at many locations. He added that while several projects were nearing completion, agencies were now required to finish the remaining work without further delays. He warned that contractors would not be paid if roads were not properly reinstated.

Originally, the civic body had set June 1 as the final date for all road excavation, pipeline laying, and related work. However, a report by Hindustan Times on Monday pointed out that road digging continued beyond this deadline in several areas such as Baner, Kothrud, Yerawada, and Hadapsar, causing traffic disruptions and safety hazards during rainfall.

Diwate instructed each department to submit status reports and ensure that road reinstatement was completed by June 7 without fail. Officials were also directed to closely monitor progress on the ground and take action against contractors responsible for delays or poor-quality work.

The Pune Municipal Corporation (PMC) extended the deadline for completing road repair and reinstatement work from June 1 to June 7, as several departments had failed to meet the original target. Despite an earlier directive to finish all digging and road-related activities before the monsoon season, many parts of the city remained under excavation.This extension was decided after a review meeting held on Monday, chaired by PMC additional commissioner Omprakash Diwate, with heads of the road, drainage, water supply, and electrical departments in attendance.Diwate explained that the early arrival of the monsoon this year had caused delays in work at many locations. He added that while several projects were nearing completion, agencies were now required to finish the remaining work without further delays. He warned that contractors would not be paid if roads were not properly reinstated.Originally, the civic body had set June 1 as the final date for all road excavation, pipeline laying, and related work. However, a report by Hindustan Times on Monday pointed out that road digging continued beyond this deadline in several areas such as Baner, Kothrud, Yerawada, and Hadapsar, causing traffic disruptions and safety hazards during rainfall.Diwate instructed each department to submit status reports and ensure that road reinstatement was completed by June 7 without fail. Officials were also directed to closely monitor progress on the ground and take action against contractors responsible for delays or poor-quality work.

Next Story
Infrastructure Urban

Naidu Seeks Rs 563 Crore For AP Sports Infrastructure

Andhra Pradesh Chief Minister N Chandrababu Naidu has sought Rs 563 crore from the Centre to boost sports infrastructure in the state, including Rs 538 crore for stadium development and Rs 25 crore to host the Khelo India Martial Arts Games 2025. Naidu made the request during a meeting with Union Youth Services and Sports Minister Mansukh Mandaviya in New Delhi on Wednesday.The CM urged early completion of Khelo India infrastructure projects in Tirupati, Rajahmundry, Kakinada, and Narasaraopeta, and called for an international-standard badminton training centre and a national aquatic sports hu..

Next Story
Infrastructure Transport

Tough Bidding Norms Slow NHAI Road Project Awards

Stringent bidding rules imposed by the Ministry of Road Transport & Highways (MoRTH) have led to a slowdown in project awards by the National Highways Authority of India (NHAI), despite a robust Rs 3.5 trillion pipeline. According to an HDFC Securities report, the shift to more cautious developer models now favours firms with strong balance sheets, as tighter qualification norms limit aggressive bidders.The revised norms mandate additional performance security, targeting the exclusion of players that previously submitted low bids—often 25 to 40 per cent below NHAI cost estimates—raisin..

Next Story
Infrastructure Transport

Mumbai Gets Coastal Nod for Next Promenade Phase

As Mumbai prepares to open two major sections of its expansive seafront promenade this week, the city’s civic authority has secured a key coastal clearance to advance further construction. The Maharashtra Coastal Zone Management Authority (MCZMA) has approved the commencement of work on the segment between Haji Ali and Baroda Palace, with tendering expected soon after project cost assessments.The promenade, stretching 7.5 km in length and 20 metres wide, is being designed as a flagship open space for walkers, joggers, and cyclists. Two critical stretches—2.75 km from Tata Garden to Haji Al..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Talk to us?