Roads: Order book to execution ratio
ROADS & HIGHWAYS

Roads: Order book to execution ratio

Reports reveal that the order book for 66 construction companies is three times their current revenue. Is there an ideal ratio to be followed?
According to Vijay Agrawal, Executive Director, Equirus Capital, “Generally, the ideal order book to execution ratio should be between three to four times of revenue. A good visibility of the next three-year order book gives comfort to investors.” Rajeshwar Burla, Assistant Vice-President & Associate Head - Corporate Ratings, ICRA, says, “The thumb rule is that the ratio should be close to the average execution period of the segment the contractor is operating in.”
Now, time for a reality check!

KNR’s existing EPC road projects amount to Rs 12.104 billion and HAM projects in the EPC mode to Rs 39.75 billion, taking the company’s total road EPC order book to Rs 51.854 billion. The company’s current order book to execution ratio is 2.5:1. 

“At Dilip Buildcon, our order book to execution ratio is 2 to 2.5 times the current revenue,” says Devendra Jain, CEO & Executive Director, Dilip Buildcon. The company’s total order book is Rs 230 billion. This includes Rs 130 billion worth of HAM projects and Rs 100 billion of EPC works. EPC works include roads as well as urban development, rails and metro, and mining.

The EPC order book of PNC Infratech as on December 31, 2018, was around Rs 80 billion. The company has seven highway projects on HAM with an aggregate bid project cost of over Rs 95 billion. “Four are already in the construction phase; for three projects, we have achieved financial closure and appointed dates for the same are awaited from NHAI,” says Yogesh Kumar Jain, Managing Director, PNC Infratech. The company has seven BOT toll and BOT annuity projects, which are already operational.

As on 31 December, 2018, out of the total Balance Order Book of 95 Billion, Ashoka Buildcon the order book in the road sector for own BOT projects is of Rs 48.93 billion. This primarily constitutes HAM projects worth Rs 47.75 billion, with the balance Rs 1.18 billion consisting of orders of certain annuity projects (not HAM). “These include seven HAM projects,” says Paresh Mehta, CFO, Ashoka Buildcon. “While two have been under execution for more than one-and-a-half years, five are recent additions.”

SHRIYAL SETHUMADHAVAN

Reports reveal that the order book for 66 construction companies is three times their current revenue. Is there an ideal ratio to be followed?According to Vijay Agrawal, Executive Director, Equirus Capital, “Generally, the ideal order book to execution ratio should be between three to four times of revenue. A good visibility of the next three-year order book gives comfort to investors.” Rajeshwar Burla, Assistant Vice-President & Associate Head - Corporate Ratings, ICRA, says, “The thumb rule is that the ratio should be close to the average execution period of the segment the contractor is operating in.”Now, time for a reality check!KNR’s existing EPC road projects amount to Rs 12.104 billion and HAM projects in the EPC mode to Rs 39.75 billion, taking the company’s total road EPC order book to Rs 51.854 billion. The company’s current order book to execution ratio is 2.5:1. “At Dilip Buildcon, our order book to execution ratio is 2 to 2.5 times the current revenue,” says Devendra Jain, CEO & Executive Director, Dilip Buildcon. The company’s total order book is Rs 230 billion. This includes Rs 130 billion worth of HAM projects and Rs 100 billion of EPC works. EPC works include roads as well as urban development, rails and metro, and mining.The EPC order book of PNC Infratech as on December 31, 2018, was around Rs 80 billion. The company has seven highway projects on HAM with an aggregate bid project cost of over Rs 95 billion. “Four are already in the construction phase; for three projects, we have achieved financial closure and appointed dates for the same are awaited from NHAI,” says Yogesh Kumar Jain, Managing Director, PNC Infratech. The company has seven BOT toll and BOT annuity projects, which are already operational.As on 31 December, 2018, out of the total Balance Order Book of 95 Billion, Ashoka Buildcon the order book in the road sector for own BOT projects is of Rs 48.93 billion. This primarily constitutes HAM projects worth Rs 47.75 billion, with the balance Rs 1.18 billion consisting of orders of certain annuity projects (not HAM). “These include seven HAM projects,” says Paresh Mehta, CFO, Ashoka Buildcon. “While two have been under execution for more than one-and-a-half years, five are recent additions.”SHRIYAL SETHUMADHAVAN

Next Story
Infrastructure Transport

Tata, Airbus to Build India’s First Private Helicopter Line

In a landmark development for India’s aerospace sector, Tata Advanced Systems Limited (TASL) and Airbus will establish the country’s first private-sector helicopter assembly line in Vemagal, Karnataka. The facility will manufacture the Airbus H125 and H125M, marking a significant milestone in India’s push for self-reliance in aviation and defence manufacturing. The new Final Assembly Line (FAL) will produce the H125, the world’s best-selling single-engine helicopter, known for its versatility and performance in extreme environments. The first ‘Made in India’ H125 is expected to ro..

Next Story
Infrastructure Urban

NeGD to Support Bharat Taxi in Building Cooperative Ride Platform

In a significant move for India’s digital and mobility transformation, the National e-Governance Division (NeGD) of the Digital India Corporation, under the Ministry of Electronics and Information Technology (MeitY), has entered into an advisory partnership with Sahakar Taxi Cooperative Limited, the company behind Bharat Taxi — a first-of-its-kind, cooperative-led national ride-hailing platform. A Memorandum of Understanding (MoU) has been signed between NeGD and Sahakar Taxi to provide strategic advisory and technical support covering key areas such as platform integration, cybersecurity..

Next Story
Technology

MeitY Hosts Pre-Summit for India–AI Impact Summit 2026

The Ministry of Electronics and Information Technology (MeitY), Government of India, hosted a series of Pre-Summit events for the upcoming India–AI Impact Summit 2026 at the India Mobile Congress (IMC) 2025 in New Delhi. These sessions mark a key milestone ahead of the main summit, scheduled for 19–20 February 2026 at Bharat Mandapam, New Delhi. Delivering the inaugural address, S. Krishnan, Secretary, MeitY, highlighted India’s innovative and frugal approach to AI development. “We have adopted innovative means by learning from others’ experiences to build projects and products that..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Talk to us?