Sangam Ropeway Project Finally Set to Take Off in Prayagraj
ROADS & HIGHWAYS

Sangam Ropeway Project Finally Set to Take Off in Prayagraj

After remaining stalled for seven years, the long-delayed Sangam Ropeway Project in Prayagraj is finally moving ahead. The Ministry of Road Transport and Highways has cleared the administrative and technical hurdles that had held it back, assigning National Highways Logistics Management Limited (NHLML) to oversee its construction.

The ropeway will be developed under a public-private partnership (PPP) model with a revenue-sharing structure, designed to ensure both financial viability and operational efficiency.

Revised Design and Route

The updated alignment situates the main station between Lal Sadak and Kali Sadak, close to the Parade Ground, adjacent to the Maha Kumbh Parade Police Station and Prayagraj Mela Authority headquarters. This marks a shift from the earlier location near Shankar Viman Mandapam, improving accessibility for pilgrims and local commuters. The second station will be built near Triveni Pushp in Arail, extending coverage across the wider Sangam area.

The 2.2-kilometre-long ropeway will feature three support pillars and fourteen trolleys, each capable of carrying eight passengers, allowing 112 visitors to travel simultaneously while enjoying aerial views of the Sangam — the confluence of the Ganga, Yamuna, and mythical Saraswati rivers.

Project Cost and Implementation

Valued at Rs 2.1 billion, the project has been awarded to a Rajasthan-based firm after detailed surveys and design assessments. A physical model of the ropeway was recently displayed at the Prayagraj Mela Authority headquarters, providing officials with a visual representation of the infrastructure layout.

Background and Significance

Initially proposed seven years ago, the Sangam Ropeway was conceived to ease congestion and improve pilgrim mobility during major religious gatherings such as the Kumbh Mela and Maha Kumbh. Despite multiple revisions — including attempts before Kumbh 2019 and Maha Kumbh 2025 — the project faced repeated administrative and technical delays until approvals were finalised between 2023 and 2024.

Officials said the project will serve as a major tourist attraction, especially during mass gatherings, while providing a safe, sustainable, and scenic mode of transport. The elevated route will also reduce pressure on ground transportation, enhancing both mobility and visitor experience.

Modernising Pilgrimage Infrastructure

The initiative aligns with broader government efforts to modernise pilgrimage cities through sustainable infrastructure and eco-friendly transport systems. By adopting the PPP model, authorities aim to blend professional management, fiscal accountability, and long-term sustainability.

Construction is expected to begin soon following environmental and safety clearances. Once operational, the Sangam Ropeway will not only improve connectivity in Prayagraj but also elevate its tourism appeal, fulfilling a long-standing ambition of city planners and religious institutions alike.

After remaining stalled for seven years, the long-delayed Sangam Ropeway Project in Prayagraj is finally moving ahead. The Ministry of Road Transport and Highways has cleared the administrative and technical hurdles that had held it back, assigning National Highways Logistics Management Limited (NHLML) to oversee its construction. The ropeway will be developed under a public-private partnership (PPP) model with a revenue-sharing structure, designed to ensure both financial viability and operational efficiency. Revised Design and Route The updated alignment situates the main station between Lal Sadak and Kali Sadak, close to the Parade Ground, adjacent to the Maha Kumbh Parade Police Station and Prayagraj Mela Authority headquarters. This marks a shift from the earlier location near Shankar Viman Mandapam, improving accessibility for pilgrims and local commuters. The second station will be built near Triveni Pushp in Arail, extending coverage across the wider Sangam area. The 2.2-kilometre-long ropeway will feature three support pillars and fourteen trolleys, each capable of carrying eight passengers, allowing 112 visitors to travel simultaneously while enjoying aerial views of the Sangam — the confluence of the Ganga, Yamuna, and mythical Saraswati rivers. Project Cost and Implementation Valued at Rs 2.1 billion, the project has been awarded to a Rajasthan-based firm after detailed surveys and design assessments. A physical model of the ropeway was recently displayed at the Prayagraj Mela Authority headquarters, providing officials with a visual representation of the infrastructure layout. Background and Significance Initially proposed seven years ago, the Sangam Ropeway was conceived to ease congestion and improve pilgrim mobility during major religious gatherings such as the Kumbh Mela and Maha Kumbh. Despite multiple revisions — including attempts before Kumbh 2019 and Maha Kumbh 2025 — the project faced repeated administrative and technical delays until approvals were finalised between 2023 and 2024. Officials said the project will serve as a major tourist attraction, especially during mass gatherings, while providing a safe, sustainable, and scenic mode of transport. The elevated route will also reduce pressure on ground transportation, enhancing both mobility and visitor experience. Modernising Pilgrimage Infrastructure The initiative aligns with broader government efforts to modernise pilgrimage cities through sustainable infrastructure and eco-friendly transport systems. By adopting the PPP model, authorities aim to blend professional management, fiscal accountability, and long-term sustainability. Construction is expected to begin soon following environmental and safety clearances. Once operational, the Sangam Ropeway will not only improve connectivity in Prayagraj but also elevate its tourism appeal, fulfilling a long-standing ambition of city planners and religious institutions alike.

Related Stories

Gold Stories

Next Story
Resources

Schindler named among Forbes’ World’s Best Employers 2026

Schindler has been named among Forbes’ World’s Best Employers 2026, a global ranking recognising companies for their workplace environments.Compiled by Forbes in partnership with Statista, the ranking is based on independent employee feedback, including whether employees would recommend their organisation to friends and family.The company said the recognition reflected its focus on creating a workplace where employees can develop their expertise and build careers. ..

Next Story
Infrastructure Urban

India needs an export-execution mindset: Vishesh Jain

Interview with Vishesh Jain, Founder & CEO, EximpleWhat gaps in India’s global trade ecosystem led you to build Eximple, and what problem did you see businesses struggling with most?Eximple came out of a problem that all three founders had seen from different choke points in the trade ecosystem. India has millions of MSMEs and manufacturers, and many of them can make products that are genuinely competitive on quality. Yet only a small fraction is able to build meaningful international businesses. In our experience, the gap is usually not manufacturing capability; it is the ability to exe..

Next Story
Building Material

Nuvoco reports 13.5% revenue growth in Q2 FY27

Nuvoco Vistas Corp. Ltd. reported consolidated revenue of Rs 27.9 billion for Q2 FY27, up 13.5% year on year. Cement sales volume rose 9% to 4.7 million tonnes (MMT), while EBITDA increased 11% to Rs 4.11 billion.The company said it began its cement operations in 2014 with a 2.3 MMT per annum (MMTPA) operation at Nimbol. It now aims to reach 35 MMTPA of cement capacity by FY28, nearly 15 times its initial capacity. Its portfolio spans cement, ready-mix concrete and modern building materials.On sustainability and cost efficiency, Nuvoco partnered with CleanMax for a 46.4 MW wind-solar hybrid re..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

SPECIAL OFFER
QR Code