Sangam Ropeway Project Finally Set to Take Off in Prayagraj
ROADS & HIGHWAYS

Sangam Ropeway Project Finally Set to Take Off in Prayagraj

After remaining stalled for seven years, the long-delayed Sangam Ropeway Project in Prayagraj is finally moving ahead. The Ministry of Road Transport and Highways has cleared the administrative and technical hurdles that had held it back, assigning National Highways Logistics Management Limited (NHLML) to oversee its construction.

The ropeway will be developed under a public-private partnership (PPP) model with a revenue-sharing structure, designed to ensure both financial viability and operational efficiency.

Revised Design and Route

The updated alignment situates the main station between Lal Sadak and Kali Sadak, close to the Parade Ground, adjacent to the Maha Kumbh Parade Police Station and Prayagraj Mela Authority headquarters. This marks a shift from the earlier location near Shankar Viman Mandapam, improving accessibility for pilgrims and local commuters. The second station will be built near Triveni Pushp in Arail, extending coverage across the wider Sangam area.

The 2.2-kilometre-long ropeway will feature three support pillars and fourteen trolleys, each capable of carrying eight passengers, allowing 112 visitors to travel simultaneously while enjoying aerial views of the Sangam — the confluence of the Ganga, Yamuna, and mythical Saraswati rivers.

Project Cost and Implementation

Valued at Rs 2.1 billion, the project has been awarded to a Rajasthan-based firm after detailed surveys and design assessments. A physical model of the ropeway was recently displayed at the Prayagraj Mela Authority headquarters, providing officials with a visual representation of the infrastructure layout.

Background and Significance

Initially proposed seven years ago, the Sangam Ropeway was conceived to ease congestion and improve pilgrim mobility during major religious gatherings such as the Kumbh Mela and Maha Kumbh. Despite multiple revisions — including attempts before Kumbh 2019 and Maha Kumbh 2025 — the project faced repeated administrative and technical delays until approvals were finalised between 2023 and 2024.

Officials said the project will serve as a major tourist attraction, especially during mass gatherings, while providing a safe, sustainable, and scenic mode of transport. The elevated route will also reduce pressure on ground transportation, enhancing both mobility and visitor experience.

Modernising Pilgrimage Infrastructure

The initiative aligns with broader government efforts to modernise pilgrimage cities through sustainable infrastructure and eco-friendly transport systems. By adopting the PPP model, authorities aim to blend professional management, fiscal accountability, and long-term sustainability.

Construction is expected to begin soon following environmental and safety clearances. Once operational, the Sangam Ropeway will not only improve connectivity in Prayagraj but also elevate its tourism appeal, fulfilling a long-standing ambition of city planners and religious institutions alike.

After remaining stalled for seven years, the long-delayed Sangam Ropeway Project in Prayagraj is finally moving ahead. The Ministry of Road Transport and Highways has cleared the administrative and technical hurdles that had held it back, assigning National Highways Logistics Management Limited (NHLML) to oversee its construction. The ropeway will be developed under a public-private partnership (PPP) model with a revenue-sharing structure, designed to ensure both financial viability and operational efficiency. Revised Design and Route The updated alignment situates the main station between Lal Sadak and Kali Sadak, close to the Parade Ground, adjacent to the Maha Kumbh Parade Police Station and Prayagraj Mela Authority headquarters. This marks a shift from the earlier location near Shankar Viman Mandapam, improving accessibility for pilgrims and local commuters. The second station will be built near Triveni Pushp in Arail, extending coverage across the wider Sangam area. The 2.2-kilometre-long ropeway will feature three support pillars and fourteen trolleys, each capable of carrying eight passengers, allowing 112 visitors to travel simultaneously while enjoying aerial views of the Sangam — the confluence of the Ganga, Yamuna, and mythical Saraswati rivers. Project Cost and Implementation Valued at Rs 2.1 billion, the project has been awarded to a Rajasthan-based firm after detailed surveys and design assessments. A physical model of the ropeway was recently displayed at the Prayagraj Mela Authority headquarters, providing officials with a visual representation of the infrastructure layout. Background and Significance Initially proposed seven years ago, the Sangam Ropeway was conceived to ease congestion and improve pilgrim mobility during major religious gatherings such as the Kumbh Mela and Maha Kumbh. Despite multiple revisions — including attempts before Kumbh 2019 and Maha Kumbh 2025 — the project faced repeated administrative and technical delays until approvals were finalised between 2023 and 2024. Officials said the project will serve as a major tourist attraction, especially during mass gatherings, while providing a safe, sustainable, and scenic mode of transport. The elevated route will also reduce pressure on ground transportation, enhancing both mobility and visitor experience. Modernising Pilgrimage Infrastructure The initiative aligns with broader government efforts to modernise pilgrimage cities through sustainable infrastructure and eco-friendly transport systems. By adopting the PPP model, authorities aim to blend professional management, fiscal accountability, and long-term sustainability. Construction is expected to begin soon following environmental and safety clearances. Once operational, the Sangam Ropeway will not only improve connectivity in Prayagraj but also elevate its tourism appeal, fulfilling a long-standing ambition of city planners and religious institutions alike.

Next Story
Infrastructure Transport

Lucknow Metro East-West Corridor Consultancy Contract Awarded

The Uttar Pradesh Metro Rail Corporation has awarded the first construction-related consultancy contract for the Lucknow Metro East West Corridor to a joint venture of AYESA Ingenieria Arquitectura SAU and AYESA India Pvt Ltd. The firm was declared the lowest bidder for the Detailed Design Consultant contract for Lucknow Metro Line-2 under Phase 1B and the contract was recommended following the financial bid. The contract is valued at Rs 159.0 million (mn), covering design services for the corridor. Lucknow Metro Line-2 envisages the construction of an 11.165 kilometre corridor connecting Cha..

Next Story
Infrastructure Urban

Div Com Kashmir Urges Fast Tracking Of Jhelum Water Transport Project

The Divisional Commissioner of Kashmir has called for the fast-tracking of the Jhelum water transport project, urging district administrations and relevant agencies to accelerate planning and clearances. In a meeting convened at the divisional headquarters, the commissioner instructed officials from irrigation, public health engineering and municipal departments to prioritise the project and coordinate survey and design work. The directive emphasised removal of administrative bottlenecks and close monitoring to ensure timely mobilisation of resources and contractors. Officials were told to in..

Next Story
Infrastructure Urban

Interarch Reports Strong Q3 And Nine Month Results

Interarch Building Solutions Limited reported unaudited results for the third quarter and nine months ended 31 December 2025, recording strong revenue growth driven by execution and a robust order book. Net revenue for the third quarter rose by 43.7 per cent to Rs 5.225 billion (bn), compared with Rs 3.636 bn a year earlier, reflecting heightened demand in pre-engineered building projects. The company’s total order book as at 31 January 2026 stood at Rs 16.85 bn, supporting near-term visibility. EBITDA excluding other income for the quarter increased by 43.2 per cent to Rs 503 million (mn),..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Open In App