Sangam Ropeway Project Finally Set to Take Off in Prayagraj
ROADS & HIGHWAYS

Sangam Ropeway Project Finally Set to Take Off in Prayagraj

After remaining stalled for seven years, the long-delayed Sangam Ropeway Project in Prayagraj is finally moving ahead. The Ministry of Road Transport and Highways has cleared the administrative and technical hurdles that had held it back, assigning National Highways Logistics Management Limited (NHLML) to oversee its construction.

The ropeway will be developed under a public-private partnership (PPP) model with a revenue-sharing structure, designed to ensure both financial viability and operational efficiency.

Revised Design and Route

The updated alignment situates the main station between Lal Sadak and Kali Sadak, close to the Parade Ground, adjacent to the Maha Kumbh Parade Police Station and Prayagraj Mela Authority headquarters. This marks a shift from the earlier location near Shankar Viman Mandapam, improving accessibility for pilgrims and local commuters. The second station will be built near Triveni Pushp in Arail, extending coverage across the wider Sangam area.

The 2.2-kilometre-long ropeway will feature three support pillars and fourteen trolleys, each capable of carrying eight passengers, allowing 112 visitors to travel simultaneously while enjoying aerial views of the Sangam — the confluence of the Ganga, Yamuna, and mythical Saraswati rivers.

Project Cost and Implementation

Valued at Rs 2.1 billion, the project has been awarded to a Rajasthan-based firm after detailed surveys and design assessments. A physical model of the ropeway was recently displayed at the Prayagraj Mela Authority headquarters, providing officials with a visual representation of the infrastructure layout.

Background and Significance

Initially proposed seven years ago, the Sangam Ropeway was conceived to ease congestion and improve pilgrim mobility during major religious gatherings such as the Kumbh Mela and Maha Kumbh. Despite multiple revisions — including attempts before Kumbh 2019 and Maha Kumbh 2025 — the project faced repeated administrative and technical delays until approvals were finalised between 2023 and 2024.

Officials said the project will serve as a major tourist attraction, especially during mass gatherings, while providing a safe, sustainable, and scenic mode of transport. The elevated route will also reduce pressure on ground transportation, enhancing both mobility and visitor experience.

Modernising Pilgrimage Infrastructure

The initiative aligns with broader government efforts to modernise pilgrimage cities through sustainable infrastructure and eco-friendly transport systems. By adopting the PPP model, authorities aim to blend professional management, fiscal accountability, and long-term sustainability.

Construction is expected to begin soon following environmental and safety clearances. Once operational, the Sangam Ropeway will not only improve connectivity in Prayagraj but also elevate its tourism appeal, fulfilling a long-standing ambition of city planners and religious institutions alike.

After remaining stalled for seven years, the long-delayed Sangam Ropeway Project in Prayagraj is finally moving ahead. The Ministry of Road Transport and Highways has cleared the administrative and technical hurdles that had held it back, assigning National Highways Logistics Management Limited (NHLML) to oversee its construction. The ropeway will be developed under a public-private partnership (PPP) model with a revenue-sharing structure, designed to ensure both financial viability and operational efficiency. Revised Design and Route The updated alignment situates the main station between Lal Sadak and Kali Sadak, close to the Parade Ground, adjacent to the Maha Kumbh Parade Police Station and Prayagraj Mela Authority headquarters. This marks a shift from the earlier location near Shankar Viman Mandapam, improving accessibility for pilgrims and local commuters. The second station will be built near Triveni Pushp in Arail, extending coverage across the wider Sangam area. The 2.2-kilometre-long ropeway will feature three support pillars and fourteen trolleys, each capable of carrying eight passengers, allowing 112 visitors to travel simultaneously while enjoying aerial views of the Sangam — the confluence of the Ganga, Yamuna, and mythical Saraswati rivers. Project Cost and Implementation Valued at Rs 2.1 billion, the project has been awarded to a Rajasthan-based firm after detailed surveys and design assessments. A physical model of the ropeway was recently displayed at the Prayagraj Mela Authority headquarters, providing officials with a visual representation of the infrastructure layout. Background and Significance Initially proposed seven years ago, the Sangam Ropeway was conceived to ease congestion and improve pilgrim mobility during major religious gatherings such as the Kumbh Mela and Maha Kumbh. Despite multiple revisions — including attempts before Kumbh 2019 and Maha Kumbh 2025 — the project faced repeated administrative and technical delays until approvals were finalised between 2023 and 2024. Officials said the project will serve as a major tourist attraction, especially during mass gatherings, while providing a safe, sustainable, and scenic mode of transport. The elevated route will also reduce pressure on ground transportation, enhancing both mobility and visitor experience. Modernising Pilgrimage Infrastructure The initiative aligns with broader government efforts to modernise pilgrimage cities through sustainable infrastructure and eco-friendly transport systems. By adopting the PPP model, authorities aim to blend professional management, fiscal accountability, and long-term sustainability. Construction is expected to begin soon following environmental and safety clearances. Once operational, the Sangam Ropeway will not only improve connectivity in Prayagraj but also elevate its tourism appeal, fulfilling a long-standing ambition of city planners and religious institutions alike.

Next Story
Building Material

Shalimar Paints Launches New Durable Luxury Interior and Exterior Range

Shalimar Paints has introduced three additions to its portfolio: Hero Insignia Luxury Interior Emulsion, Superlac PU Gloss Enamel and Hero Weather Guard 12 Luxury Exterior Emulsion. The new range is designed to combine finish, durability and environmental responsibility for modern residential spaces.Hero Insignia is a water-based luxury interior emulsion formulated with hybrid binder technology, providing a silky finish, stain resistance and protection from scuff marks. It offers more than 2,000 colour options, a 10-year promise and zero VOC levels, and can be applied on plaster, concrete and ..

Next Story
Resources

Trimble Promotes Harsh Pareek as VP Direct Sales for APAC

Trimble has promoted Harsh Pareek to Vice President, Direct Sales, Asia-Pacific for its Architecture, Engineering, Construction and Operations (AECO) division. Mr Pareek joined the company in 2017 and has more than 27 years of industry experience. He most recently served as Regional Sales Director for India for over eight years, during which he played a major role in accelerating Trimble’s growth and expanding its footprint across the Indian Subcontinent.Expressing his focus for the new role, Mr Pareek said that the AECO sector in Asia-Pacific is entering a phase driven by technology, sustai..

Next Story
Infrastructure Energy

Rajasthan Moves Mining Processes Fully Online From 15 December

The Rajasthan government will make all mining-related processes entirely paperless from 15 December, a senior official said. The Mines, Geology and Petroleum Department will halt all offline work across its mining modules, requiring officials to operate exclusively through online systems. Principal Secretary (Mines) T Ravikant said compliance monitoring will begin on 1 December while addressing an orientation workshop for officials from the Jaipur, Bharatpur, Ajmer, Kota and Bikaner zones. Ravikant explained that the department has developed two mobile applications and fourteen online modules..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement