Srinagar Upgrades 118.06 km of Roads, Widening Projects Face Delays
ROADS & HIGHWAYS

Srinagar Upgrades 118.06 km of Roads, Widening Projects Face Delays

As many as 118.06 km of roads have been macadamised or upgraded across Srinagar district during the current financial year, although several road-widening projects remain delayed by land acquisition, compensation and litigation issues. Deputy Chief Minister Surinder Kumar Choudhary provided the details in the Legislative Assembly while replying to a question from MLA Ali Mohammad Sagar.

Choudhary said 15.43 km of roads had been upgraded in the Khanyar constituency under special development directives. On Syed Meerakshah Road, 2.68 km of the 10.33-km stretch has been fully widened, representing 25.95 per cent physical progress. Acquisition and settlement have been completed for 132 of the 332 affected structures.

The Government placed the project’s total compensation liability at Rs. 3.36 bn, of which Rs. 612.93 mn had been released, leaving Rs. 2.75 bn pending. It attributed the delay to litigation, land and ownership disputes, missing Section 4 notifications and compensation-related matters.

The 12.45-km Khanyar-Zadibal-Pandrath Road has undergone around 2 km of widening, with 161 of 314 structures acquired and approximately 16 per cent physical progress. On Koolipora-Budoo Bagh Road, 231 metres of the 435-metre stretch has been completed, while 14 of 29 structures have been cleared. The project has been approved at an estimated cost of Rs. 45 mn.

The Government is pursuing bottleneck removal through the High-Level Committee (HLC). The Devi Angan-Hawal Road proposal has been submitted under the Central Road and Infrastructure Fund (CRIF) at an estimated Rs. 312.5 mn, including Rs. 300 mn for land acquisition and utility shifting. Alamgiri Bazar Chowk work has been authorised at Rs. 33.5 mn, including the acquisition of five structures and junction redesigning. Acquisition cases involving 34 structures have been taken up on Buchpora-Hazratbal Road, with two completed. Four structures remain on Babapora-Habba Kadal Road, while 24 are pending on Habba Kadal-Gowkadal Road. Choudhary said court cases, family title disputes and compensation assessments were also delaying projects, and that a streamlined mechanism was being implemented to settle outstanding claims.

As many as 118.06 km of roads have been macadamised or upgraded across Srinagar district during the current financial year, although several road-widening projects remain delayed by land acquisition, compensation and litigation issues. Deputy Chief Minister Surinder Kumar Choudhary provided the details in the Legislative Assembly while replying to a question from MLA Ali Mohammad Sagar. Choudhary said 15.43 km of roads had been upgraded in the Khanyar constituency under special development directives. On Syed Meerakshah Road, 2.68 km of the 10.33-km stretch has been fully widened, representing 25.95 per cent physical progress. Acquisition and settlement have been completed for 132 of the 332 affected structures. The Government placed the project’s total compensation liability at Rs. 3.36 bn, of which Rs. 612.93 mn had been released, leaving Rs. 2.75 bn pending. It attributed the delay to litigation, land and ownership disputes, missing Section 4 notifications and compensation-related matters. The 12.45-km Khanyar-Zadibal-Pandrath Road has undergone around 2 km of widening, with 161 of 314 structures acquired and approximately 16 per cent physical progress. On Koolipora-Budoo Bagh Road, 231 metres of the 435-metre stretch has been completed, while 14 of 29 structures have been cleared. The project has been approved at an estimated cost of Rs. 45 mn. The Government is pursuing bottleneck removal through the High-Level Committee (HLC). The Devi Angan-Hawal Road proposal has been submitted under the Central Road and Infrastructure Fund (CRIF) at an estimated Rs. 312.5 mn, including Rs. 300 mn for land acquisition and utility shifting. Alamgiri Bazar Chowk work has been authorised at Rs. 33.5 mn, including the acquisition of five structures and junction redesigning. Acquisition cases involving 34 structures have been taken up on Buchpora-Hazratbal Road, with two completed. Four structures remain on Babapora-Habba Kadal Road, while 24 are pending on Habba Kadal-Gowkadal Road. Choudhary said court cases, family title disputes and compensation assessments were also delaying projects, and that a streamlined mechanism was being implemented to settle outstanding claims.

Related Stories

Gold Stories

Next Story
Resources

Hettich India And ECO Schulte Form Joint Venture In India

Hettich India and German company ECO Schulte have announced a strategic joint venture to strengthen their presence in India's architectural hardware market. The partnership was announced at ACETECH Mumbai on November 20, 2026, bringing together the two family-owned businesses with a combined engineering heritage of 238 years.The venture combines Hettich's expertise in furniture fittings and interior solutions with ECO Schulte's experience in architectural door hardware and engineered door systems. Its focus will span residential, commercial, institutional and infrastructure projects.Hettich, w..

Next Story
Real Estate

Address Maker sells over 200 Apollo Address plots in six weeks

The Address Maker Group has sold more than two-thirds of the inventory at its Apollo Address villa-plot development in Nelamangala, North-West Bengaluru, within six weeks of its launch. With over 200 plots purchased and approximately 100 remaining, the project has recorded the fastest sales pace in the developer's history.Spread across 23 acres within a larger 90-acre township, Apollo Address offers villa plots ranging from 1,200 to 2,400 sq ft. Inspired by classical Greek architecture, the development features planned infrastructure, landscaped open spaces and residential amenities.Nearly 30 ..

Next Story
Equipment

Zoomlion strengthens equipment partnerships in Australia

Zoomlion Heavy Industry Science & Technology has reaffirmed its commitment to expanding operations in Australia, with Chairman and CEO Zhan Chunxin meeting customers and business partners in Sydney to strengthen long-term partnerships and discuss opportunities for closer collaboration.The meeting, held on 4 November 2026, focused on equipment quality, technical support, spare parts availability, local training and customer service improvements. Representatives from the tower crane, concrete machinery, earthmoving, aerial work platform, agricultural machinery and financial sectors participa..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

SPECIAL OFFER
QR Code