Thane Coastal Road Reaches 45 Per Cent Completion
ROADS & HIGHWAYS

Thane Coastal Road Reaches 45 Per Cent Completion

The Thane Coastal Road-1 project has reached 45 per cent completion after the Mumbai Metropolitan Region Development Authority (MMRDA) erected 10 I-girders in a single day. The girders were installed on 14 October 2026 as part of construction work on the access-controlled corridor.

The daily achievement exceeded the project’s usual output of four to six girders, according to an official statement issued by MMRDA. The authority described the installation as a construction milestone and said it represented a significant step in the project’s progress.

The corridor is 13.45 km long and has six lanes. It is being developed to connect NH-3 and NH-48 at Kharegaon Toll Naka with Gaimukh, creating a direct transport link across the Thane region.

Once completed, the road is expected to provide an alternative route to Ghodbunder Road. The project’s access-controlled design is intended to support smoother movement along the corridor, while the girder installation marks progress on the structures required for the route.

MMRDA’s latest update focused on the pace of girder erection and the overall completion level. The authority did not provide a revised completion date or additional details about the remaining construction work in the statement. The 45 per cent progress figure covers the project as a whole, while the 10-girder installation reflects output recorded on a single working day.

The update comes as construction continues on the Thane Coastal Road-1 project. With the latest installation, the authority has recorded a daily performance above its normal range of four to six girders, while work proceeds towards completion of the planned 13.45-km connection between Kharegaon Toll Naka and Gaimukh.

The Thane Coastal Road-1 project has reached 45 per cent completion after the Mumbai Metropolitan Region Development Authority (MMRDA) erected 10 I-girders in a single day. The girders were installed on 14 October 2026 as part of construction work on the access-controlled corridor. The daily achievement exceeded the project’s usual output of four to six girders, according to an official statement issued by MMRDA. The authority described the installation as a construction milestone and said it represented a significant step in the project’s progress. The corridor is 13.45 km long and has six lanes. It is being developed to connect NH-3 and NH-48 at Kharegaon Toll Naka with Gaimukh, creating a direct transport link across the Thane region. Once completed, the road is expected to provide an alternative route to Ghodbunder Road. The project’s access-controlled design is intended to support smoother movement along the corridor, while the girder installation marks progress on the structures required for the route. MMRDA’s latest update focused on the pace of girder erection and the overall completion level. The authority did not provide a revised completion date or additional details about the remaining construction work in the statement. The 45 per cent progress figure covers the project as a whole, while the 10-girder installation reflects output recorded on a single working day. The update comes as construction continues on the Thane Coastal Road-1 project. With the latest installation, the authority has recorded a daily performance above its normal range of four to six girders, while work proceeds towards completion of the planned 13.45-km connection between Kharegaon Toll Naka and Gaimukh.

Related Stories

Gold Stories

Next Story
Infrastructure Urban

Welspun One unveils Diwali campaign for World Trade Center Thane

Welspun One has unveiled A Dream Diwali, a festive brand film promoting World Trade Center Thane, its proposed mixed-use development in the Mumbai Metropolitan Region (MMR). The campaign uses individual interpretations of an ideal Diwali to introduce the experiences and offerings planned at the development.The film follows different characters as they share their festive wishes and go about activities such as shopping, meeting friends, playing games and spending time with family. Through these everyday moments, the campaign presents the idea that celebrations are personal and that different ge..

Next Story
Equipment

BorgWarner secures three turbocharger contracts with global powertrain leader

BorgWarner has secured three new turbocharger contracts with a global powertrain technology company. The wins comprise one contract for its variable turbine geometry (VTG) turbocharger and two for its wastegate turbocharger. The technologies will be deployed in the customer's light-vehicle gasoline platforms in South America and Europe, with production scheduled to begin in 2027.The VTG turbochargers are designed for gasoline engines operating under demanding conditions and high-boost pressure requirements. They are engineered to support Miller-cycle engines and withstand exhaust temperatures ..

Next Story
Infrastructure Transport

International Digi Yatra Trials Begin at Seven Airports

India has begun trials of Digi Yatra for international passengers at seven airports, allowing eligible Indian passport holders to use facial recognition at selected airport checkpoints. The facility is currently limited to Indian nationals with e-passports travelling on selected international flights operated by Air India and IndiGo. The Civil Aviation Ministry announced the trials on 1 November, with testing scheduled through December 2026. A wider rollout is expected in 2027 after the ministry assesses passenger feedback gathered during the trial period, according to PTI. The system is inten..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

SPECIAL OFFER
QR Code