Delhi Metro Phase IV Expansion Delayed to March 2026
RAILWAYS & METRO RAIL

Delhi Metro Phase IV Expansion Delayed to March 2026

The Delhi Metro Rail Corporation (DMRC) has faced a setback in the expansion of Delhi's Metro network as it has revised the deadlines for three corridors in Phase-IV. The Phase-IV expansion aims to add 65.20 km of new lines and 46 metro stations to the national capital, with 28 km underground and the rest elevated. As part of this expansion, there will be 11 new interchange stations.

The corridors included in Phase-IV are the Janakpuri West-RK Ashram Marg (29.04 km), Majlis Park-Maujpur (12.55 km), and Tughalakabad-Aerocity (23.62 km). The Janakpuri West-RK Ashram Marg and Majlis Park-Maujpur are extensions of the existing Magenta Line and Pink Line, respectively. The Tughalakabad-Aerocity corridor, known as the 'Silver Line,' connects the operational Violet Line and Airport Line from their respective ends.

According to the DMRC, the Janakpuri West-RK Ashram Marg corridor, spanning 29 km, will only be operational by March 2026, which is a delay from its initial deadline of September 2025. Similarly, the Majlis Park-Maujpur corridor is expected to be completed by March 2025 instead of the previous deadline of November 2024. The Tughlakabad-Aerocity corridor is also likely to be completed by March 2026, as opposed to the earlier deadline of September 2025.

In December 2018, the Delhi government approved six metro corridors, totaling 103.9 km, for Phase IV expansion. Among these, the Aerocity-Tughlakabad, Majlis Park-Maujpur, and Janakpuri West-RK Ashram corridors were categorised as priority corridors and received approval from the Union Cabinet in March 2019. However, the commencement of work on Phase IV was affected by the outbreak of the COVID-19 pandemic in March 2020.

Several corridors were proposed but not approved, including Rithala-Narela (21.73 km), Inderlok-Indraprastha (12.57 km), and Lajpat Nagar-Saket G-Block (7.96 km). These corridors aimed to provide last-mile connectivity to residents.

In December 2022, the DMRC took a significant step towards operationalizing Phase IV by signing a contract with Alstom Transport India for procuring 312 Metro coaches (52 trains). Out of these, 234 standard gauge coaches will be procured for the Majlis Park-Maujpur and Janakpuri West-RK Ashram Marg corridors, while 78 standard gauge coaches will be acquired for the Tughlakabad-Delhi Aerocity corridor. These trains will be compatible with driverless operations and will be manufactured at Alstom India's facility in SriCity near Chennai.

The Janakpuri West-RK Ashram Marg extension will receive 144 new coaches (24 trains), the Mukundpur-Maujpur extension of the Pink Line will have 90 new coaches (15 trains), and the Aerocity-Tughlakabad Silver Line will be equipped with 78 new coaches (13 trains).

Also read:
Gurugram Metro Network Set to Begin Construction
Hyderabad Metro Expands with Airport Metro Express Phase


The Delhi Metro Rail Corporation (DMRC) has faced a setback in the expansion of Delhi's Metro network as it has revised the deadlines for three corridors in Phase-IV. The Phase-IV expansion aims to add 65.20 km of new lines and 46 metro stations to the national capital, with 28 km underground and the rest elevated. As part of this expansion, there will be 11 new interchange stations. The corridors included in Phase-IV are the Janakpuri West-RK Ashram Marg (29.04 km), Majlis Park-Maujpur (12.55 km), and Tughalakabad-Aerocity (23.62 km). The Janakpuri West-RK Ashram Marg and Majlis Park-Maujpur are extensions of the existing Magenta Line and Pink Line, respectively. The Tughalakabad-Aerocity corridor, known as the 'Silver Line,' connects the operational Violet Line and Airport Line from their respective ends. According to the DMRC, the Janakpuri West-RK Ashram Marg corridor, spanning 29 km, will only be operational by March 2026, which is a delay from its initial deadline of September 2025. Similarly, the Majlis Park-Maujpur corridor is expected to be completed by March 2025 instead of the previous deadline of November 2024. The Tughlakabad-Aerocity corridor is also likely to be completed by March 2026, as opposed to the earlier deadline of September 2025. In December 2018, the Delhi government approved six metro corridors, totaling 103.9 km, for Phase IV expansion. Among these, the Aerocity-Tughlakabad, Majlis Park-Maujpur, and Janakpuri West-RK Ashram corridors were categorised as priority corridors and received approval from the Union Cabinet in March 2019. However, the commencement of work on Phase IV was affected by the outbreak of the COVID-19 pandemic in March 2020. Several corridors were proposed but not approved, including Rithala-Narela (21.73 km), Inderlok-Indraprastha (12.57 km), and Lajpat Nagar-Saket G-Block (7.96 km). These corridors aimed to provide last-mile connectivity to residents. In December 2022, the DMRC took a significant step towards operationalizing Phase IV by signing a contract with Alstom Transport India for procuring 312 Metro coaches (52 trains). Out of these, 234 standard gauge coaches will be procured for the Majlis Park-Maujpur and Janakpuri West-RK Ashram Marg corridors, while 78 standard gauge coaches will be acquired for the Tughlakabad-Delhi Aerocity corridor. These trains will be compatible with driverless operations and will be manufactured at Alstom India's facility in SriCity near Chennai. The Janakpuri West-RK Ashram Marg extension will receive 144 new coaches (24 trains), the Mukundpur-Maujpur extension of the Pink Line will have 90 new coaches (15 trains), and the Aerocity-Tughlakabad Silver Line will be equipped with 78 new coaches (13 trains). Also read: Gurugram Metro Network Set to Begin Construction Hyderabad Metro Expands with Airport Metro Express Phase

Next Story
Infrastructure Transport

MMRDA advances 250 m on Orange Gate–Marine Drive tunnel

The Mumbai Metropolitan Region Development Authority (MMRDA) has completed 250 m of underground tunnelling for the Orange Gate–Marine Drive Urban Road Tunnel using India’s largest slurry shield tunnel boring machine (TBM) deployed for an urban road project.The project involves twin tunnels extending over 7 km beneath critical transport corridors, including Central Railway, Western Railway and Metro Line 3. The work requires high-precision engineering to navigate densely developed urban infrastructure.Once completed, the tunnel is expected to reduce travel time between Orange Gate and Marin..

Next Story
Infrastructure Urban

Hindustan Zinc Pays Rs 188.46 Billion in FY26

Hindustan Zinc contributed Rs 188.46 billion to the public exchequer in FY 2025-26, according to its 9th Tax Transparency Report. The contribution, equivalent to 46 per cent of the company’s revenue, included direct and indirect taxes, government royalties, dividends to the Government of India, withholding taxes and other statutory levies.The company’s five-year cumulative contribution to the exchequer stood at Rs 915.72 billion. In FY26, Hindustan Zinc reported revenue of Rs 408.44 billion, EBITDA of Rs 221.62 billion and profit after tax of Rs 138.32 billion. It also achieved its highest..

Next Story
Infrastructure Urban

World of Concrete India 2026 Opens in Mumbai

Informa Markets in India will host the 12th edition of World of Concrete India 2026 from 3–5 June 2026 at the Bombay Exhibition Centre, Mumbai. The specialised B2B exhibition will bring together manufacturers, suppliers, contractors, developers, architects, consultants, infrastructure companies, project leaders and government stakeholders.The event is expected to feature over 350 brands and more than 18,000 trade professionals. It will cover concrete and cement, dry mortar, precast technologies, formwork, construction chemicals, industrial and commercial flooring, scaffolding, safety solutio..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

-->