66 percent of Lokhandwala-Vikhroli subway line complete
RAILWAYS & METRO RAIL

66 percent of Lokhandwala-Vikhroli subway line complete

The 15.31-kilometer Swami Samarth Nagar (Lokhandwala Complex) to Vikhroli Metro Line 6 is 66 per cent complete, but the car depot that is necessary to make the route work is nowhere to be found.

The suburbs are connected by this second mass rapid transit link; Mumbai Metro 1 was the popular line that used to connect Versova and Ghatkopar.

The Mumbai Metropolitan Region Development Authority (MMRDA) provided an update on the line that is currently in the process of construction on Monday. Civil work on 13 stations is finished at 51.50 per cent. The civil work on 13 stations connecting the eastern and western suburbs is 51.50 per cent complete, and the viaduct is 71 per cent ready, breaking the project down into its individual parts.

This double-deck structure crosses the Jogeshwari Vikhroli Link Road. The lower deck is an elevated road or flyover, and the upper deck is the Metro viaduct, which is an elevated civil structure that carries a rail line.

The engineering structure's elevated vehicular road section of 2.58 km will connect the Western Express Highway and Eastern Express Highway without the need for a signal. While the Metro line will transport commuters to and from work and home.

The Mumbai Metro Lines 2A (Dahisar East to DN Nagar), 3 (Colaba-Bandra-SEEPZ), 4 (Wadala-Ghatkopar-Thane-Kasarvadavli-Gaimukh), and 7 (Dahisar East to Gundavali) will all be integrated with this link.

In addition, Mumbai Metro 1 will be connected to Jogeshwari and Kanjurmarg stations in the same way that Andheri and Ghatkopar stations are.

However, the project's greatest obstacle is the lack of available land for a car depot. The MMRDA had intended to establish a depot at Kanjurmarg, but the matter has become contentious, and previous administrations have failed to resolve it. The State Government attempted to transfer a portion of the land to the Centre a few months ago, but has so far been unsuccessful.

"MMRDA is constructing the Metro network to provide mass rapid transit services to people within a short travel distance," stated Metropolitan Commissioner SVR Srinivas. The much-needed rail-based connectivity between the western and eastern suburbs will be provided by Metro Line 6, which will also contribute to an integrated public transportation network for Mumbaikars.

The 15.31-kilometer Swami Samarth Nagar (Lokhandwala Complex) to Vikhroli Metro Line 6 is 66 per cent complete, but the car depot that is necessary to make the route work is nowhere to be found. The suburbs are connected by this second mass rapid transit link; Mumbai Metro 1 was the popular line that used to connect Versova and Ghatkopar. The Mumbai Metropolitan Region Development Authority (MMRDA) provided an update on the line that is currently in the process of construction on Monday. Civil work on 13 stations is finished at 51.50 per cent. The civil work on 13 stations connecting the eastern and western suburbs is 51.50 per cent complete, and the viaduct is 71 per cent ready, breaking the project down into its individual parts. This double-deck structure crosses the Jogeshwari Vikhroli Link Road. The lower deck is an elevated road or flyover, and the upper deck is the Metro viaduct, which is an elevated civil structure that carries a rail line. The engineering structure's elevated vehicular road section of 2.58 km will connect the Western Express Highway and Eastern Express Highway without the need for a signal. While the Metro line will transport commuters to and from work and home. The Mumbai Metro Lines 2A (Dahisar East to DN Nagar), 3 (Colaba-Bandra-SEEPZ), 4 (Wadala-Ghatkopar-Thane-Kasarvadavli-Gaimukh), and 7 (Dahisar East to Gundavali) will all be integrated with this link. In addition, Mumbai Metro 1 will be connected to Jogeshwari and Kanjurmarg stations in the same way that Andheri and Ghatkopar stations are. However, the project's greatest obstacle is the lack of available land for a car depot. The MMRDA had intended to establish a depot at Kanjurmarg, but the matter has become contentious, and previous administrations have failed to resolve it. The State Government attempted to transfer a portion of the land to the Centre a few months ago, but has so far been unsuccessful. MMRDA is constructing the Metro network to provide mass rapid transit services to people within a short travel distance, stated Metropolitan Commissioner SVR Srinivas. The much-needed rail-based connectivity between the western and eastern suburbs will be provided by Metro Line 6, which will also contribute to an integrated public transportation network for Mumbaikars.

Next Story
Infrastructure Urban

Jyoti Structures FY26 profit rises 56.5%

Jyoti Structures (JSL) recently reported strong financial results for the quarter and year ended 31 March 2026, driven by disciplined execution, cost management and steady progress across its order book.For Q4 FY2025-26, total income rose 44.2 per cent to Rs 2.41 billion from Rs 1.67 billion in Q4 FY2024-25. EBITDA increased 58.6 per cent to Rs 237 million, while EBITDA margin improved by 89 basis points to 9.84 per cent. Profit before tax grew 53.3 per cent to Rs 188.5 million, and net profit rose 51.9 per cent to Rs 181.4 million.For FY2025-26, total income grew 53.1 per cent to Rs 7.72 bill..

Next Story
Infrastructure Energy

Cat BEPU to Power Doppstadt Separator at IFAT 2026

Caterpillar’s Cat Battery Electric Power Unit (BEPU) has been selected by Doppstadt to power its SWS 6 Spiral Shaft Separator, which will be showcased for the first time at IFAT 2026 in Munich, Germany, from 4–7 May.The compact plug-and-play BEPU is designed to replace a diesel engine within the same space, using the same mounting locations and relative machine position. It integrates the battery, motor, inverter, onboard charging, cooling and controls, enabling OEMs to electrify existing chassis platforms without extensive redesign.Caterpillar and Cat dealer Zeppelin Power Systems have be..

Next Story
Infrastructure Urban

VECV sales rise 6.9% in April 2026

VE Commercial Vehicles, a joint venture between Volvo Group and Eicher Motors, recorded sales of 7,318 units in April 2026, compared to 6,846 units in April 2025, registering 6.9 per cent growth. The total included 7,159 units under the Eicher brand and 159 units under the Volvo brand.Eicher branded trucks and buses reported sales of 7,159 units during the month, up 6.6 per cent from 6,717 units in April 2025. In the domestic commercial vehicle market, Eicher sales rose 8.6 per cent to 6,797 units from 6,257 units a year earlier.Exports declined 21.3 per cent, with VECV recording 362 units in ..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement