HCC completes first tunnel for Mumbai Metro-III project
RAILWAYS & METRO RAIL

HCC completes first tunnel for Mumbai Metro-III project

Hindustan Construction Company (HCC) emerged as the sole contractor among all packages to finish the entire length of a tunnel after it completed the south bound tunnel between CST and Mumbai Central stations. 

As communicated by the company, the construction team built the 3.82-km tunnel in tough geological and urban conditions. These included the proximity of the project to the sea; the fact that the land to be tunnelled through was heterogeneous reclaimed area; congested working areas; and the need to leave buildings (most over 100 years old) undisturbed while tunnelling directly below them. 

MMRCL had awarded the contract to HCC in July 2016, for the design and construction of twin tunnels by tunnel-boring machine (TBM) method and the construction of four underground metro stations, including one at CST.

Two TBMs were procured from China with 117-m-long, single-shield, dual-mode hard rock with a 6.68 m diameter and weighing around 848 mt. They are equipped to operate in both open and closed mode, in the predominantly fresh and slightly to moderately weathered basalt and breccia anticipated in the Mumbai Metro project. After months of geotechnical investigations, planning and a lengthy procurement phase, the HCC team launched Vaitarna I (the first TBM) from the project site at CST on December 04, 2017. This TBM requires around 32 people to operate, which includes operators, engineers and labourers.

As the alignment of the tunnel passes through one of Mumbai’s most thickly populated residential areas, a thorough geological survey was conducted along the entire stretch of the project. Prior to tunnelling, a structural survey was carried out across a 30-m influence zone on either side of the alignment to assess the impact of tunnelling on the buildings. 

The construction of station buildings is currently underway. While all the station buildings are unique in design, the CST station is a completely cut-and-cover station; the remaining three stations will be made by NATM method. Vaitarna II was launched in February 2018 and is expected to complete its tunnelling by December 2019.

Hindustan Construction Company (HCC) emerged as the sole contractor among all packages to finish the entire length of a tunnel after it completed the south bound tunnel between CST and Mumbai Central stations. As communicated by the company, the construction team built the 3.82-km tunnel in tough geological and urban conditions. These included the proximity of the project to the sea; the fact that the land to be tunnelled through was heterogeneous reclaimed area; congested working areas; and the need to leave buildings (most over 100 years old) undisturbed while tunnelling directly below them. MMRCL had awarded the contract to HCC in July 2016, for the design and construction of twin tunnels by tunnel-boring machine (TBM) method and the construction of four underground metro stations, including one at CST.Two TBMs were procured from China with 117-m-long, single-shield, dual-mode hard rock with a 6.68 m diameter and weighing around 848 mt. They are equipped to operate in both open and closed mode, in the predominantly fresh and slightly to moderately weathered basalt and breccia anticipated in the Mumbai Metro project. After months of geotechnical investigations, planning and a lengthy procurement phase, the HCC team launched Vaitarna I (the first TBM) from the project site at CST on December 04, 2017. This TBM requires around 32 people to operate, which includes operators, engineers and labourers.As the alignment of the tunnel passes through one of Mumbai’s most thickly populated residential areas, a thorough geological survey was conducted along the entire stretch of the project. Prior to tunnelling, a structural survey was carried out across a 30-m influence zone on either side of the alignment to assess the impact of tunnelling on the buildings. The construction of station buildings is currently underway. While all the station buildings are unique in design, the CST station is a completely cut-and-cover station; the remaining three stations will be made by NATM method. Vaitarna II was launched in February 2018 and is expected to complete its tunnelling by December 2019.

Next Story
Infrastructure Urban

DCPC Prepares for Special Campaign 5.0 with Focus on E-Waste

The Department of Chemicals and Petrochemicals (DCPC), Ministry of Chemicals and Fertilisers, is gearing up for Special Campaign 5.0, to be held from 2nd to 31st October 2025. The initiative will focus on e-waste disposal as per MoEFCC’s E-Waste Management Rules 2022, space optimisation, and enhancing workplace efficiency across field offices.Special Campaign 4.0, conducted between October 2023 and October 2024, delivered notable results in record management, grievance redressal, scrap disposal, and cleanliness drives.Key outcomes of Special Campaign 4.0Records management: 2,443 physical fil..

Next Story
Real Estate

BlackRock India Leases 1.4 Lakh Sq Ft in Bengaluru

BlackRock Services India, the domestic arm of global asset manager BlackRock, has leased 1.4 lakh sq ft of office space at IndiQube Symphony in Bengaluru, according to Propstack data. The 10-year deal is valued at around Rs 4.10 billion.The lease, among the largest transactions in India’s co-working sector, highlights the growing preference of global institutions for flexible office providers. The agreement, commencing October 1, 2025, covers ground plus five floors in KNG Tower 1 at Ashoknagar, MG Road — one of Bengaluru’s prime commercial hubs.As per the lease document, BlackRock will ..

Next Story
Infrastructure Transport

L&T Bags Rs 25–50 Bn Order for Mumbai-Ahmedabad Bullet Train Track Works

Larsen & Toubro’s (L&T) Transportation Infrastructure business has secured an order valued between Rs 25 crore and Rs 50 billion from the National High Speed Rail Corporation Limited (NHSRCL) for the Mumbai-Ahmedabad High Speed Rail (MAHSR) corridor.The contract, Package T1, involves the design, supply, construction, testing, and commissioning of 156 route km of high-speed ballastless track on a Design-Build Lump Sum Price basis. The stretch runs from Mumbai’s Bandra-Kurla Complex to Zaroli village in Gujarat and includes 21 km of underground track and 135 km of elevated viaduct.Se..

Advertisement

Subscribe to Our Newsletter

Get daily newsletters around different themes from Construction world.

STAY CONNECTED

Advertisement

Advertisement

Advertisement

Talk to us?